NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA BRASOV -
TARGU MURES - CLUJ -
ORADEA
30+550 59+100
ASOCIEREA TRAMECO SA –
VAHOSTAV -SK A.S. – DRUMURI
BIHOR SA – DRUM ASFALT SRL –
EAST WATER DRILLINGS SRL
SECTIUNEA 3C, SUBSECTIUNEA 3C2
CHIRIBIS - BIHARIA
SUBSECTIUNEA 3C2: CHIRIBIS -
BIHARIA28.55 0.50% 0%
14.09.2020 -
EMITERE ORDIN
DE INCEPERE
PENTRU ETAPA
DE PROIECTARE
(PROIECT TEHNIC)
MARTIE 2022
(CONFORM
CONTRACT)
IUNIE 2022
(CONFORM
PROGRAM)
ANUL 2022 6 LUNI - ETAPA
DE PROIECTARE; 18 LUNI -
ETAPA DE EXECUTIE
LUCRARI; 120 LUNI -
PERIOADA DE GARANTIE
326.51 MIL. LEI
FARA TVA
CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 11.08. 2020.
A FOST TRANSMISA CATRE ANTREPRENOR ADRESA CU ORDINUL DE INCEPERE PENTRU DATA DE 14.09.2020. A FOST ACORDAT DREPTUL DE ACCES IN SANTIER ANTREPRENORULUI.
DURATA CONTRACTULUI ESTE DE 144 DE LUNI DIN CARE:
6 LUNI - ETAPA DE PROIECTARE; FINALIZARE PUNCT DE REFERINTA NR. 1 IN 09.11.2020.
18 LUNI - ETAPA DE EXECUTIE LUCRARI
120 LUNI - PERIOADA DE GARANTIE
2AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA BRASOV -
TARGU MURES - CLUJ -
ORADEA
8+700 38+760
ASOCIEREA S.C. SPEDITION UMB
S.R.L. – S.C. TEHNOSTRADE S.R.L. –
S.C. ELECTROMONTAJ S.A
SECTIUNEA 3A SI SECTIUNEA 3B,
SUBSECTIUNEA 3A2: NADASELU -
MIHAIESTI SI 3B1: MIHAESTI ZIMBOR
SUBSECTIUNEA 3A2
NADASELU - MIHAIESTI KM
8+700 - 25+500+ 3B1,
MIHAIESTI – ZIMBOR KM
0+000 - 13+260
30.06 0% 0% 25.01.2021 2023 ANUL 20231.390,614 MIL.
LEI FARA TVA
SEMNARE CONTRACT PROIECTARE SI EXECUTIE IN DATA DE 28.12.2020. PRETUL PE KM DE AUTOSTRADA ESTE DE CCA. 46,261,293.92 LEI FARA TVA, REPREZENTAND CCA. 9,383,629 EURO FARA TVA.
DURATA CONTRACTULUI ESTE DE 96 DE LUNI, DIN CARE:
• 12 LUNI PERIOADA DE PROIECTARE,
• 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,
• 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.
AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3A2 IN LUNA APRILIE 2021.
AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3B1 IN 01.07.2021
PROIECT TEHNIC DE EXECUTIE PENTRU 3A2 AVIZAT IN CTE - CNAIR IN DATA DE 20.08.2021
PROIECT TEHNIC IN CURS DE ELABORARE PENTRU 3B1 - TERMEN ESTIMAT AVIZARE PROIECT TEHNIC: DEC. 2021
3AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA BRASOV -
TARGU MURES - CLUJ -
ORADEA
66+500 80+054 NUROL INSAAT VE TICARET S.ASECTIUNEA 3B, SUBSECTIUNEA 3B5
NUSFALAU - SUPLACU DE BARCAU
SUBSECTIUNEA 3B5:
NUSFALAU - SUPLACU DE
BARCAU
13.55 4.34% 15.75% 01.02.2021 FEBRUARIE 2023 FEBRUARIE 2023384.14 MIL. LEI
FARA TVA
CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN 30.09.2020;
6 LUNI PERIOADA DE PROIECTARE
; 18 LUNI PERIOADA DE EXECUTIE
; 120 LUNI PERIOADA DE GARANTIE
LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 12 STRUCTURI (4 PASAJE SI 8 PODURI), RESPECTIV UN NOD RUTIER LA KM 67+500
FINALIZARE ETAPA PROIECTARE (PTE) - PROIECTUL TEHNIC DE EXECUTIE A FOST AVIZAT IN CADRUL CTE IN DATA DE 02.08.2021
4AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA BRASOV -
TARGU MURES - CLUJ -
ORADEA
13+260 25+500
ASOCIEREA SC SA&PE CONSTRUCT
SRL - SC SPEDITION UMB SRL - SC
TEHNOSTRADE SRL
SECTIUNEA 3B, SUBSECTIUNEA 3B2:
ZIMBOR - POARTA SALAJULUI
SUBSECTIUNEA 3B2: ZIMBOR -
POARTA SALAJULUI12.24 0% 0%
31.05.2021 -
ORDIN DE
INCEPERE
2023 ANUL 2023680.40 MIL. LEI
FARA TVA
CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 01.07.2020;
DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE:
12 LUNI PERIOADA DE PROIECTARE,
24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,
120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR
A FOST CONSTITUITA GARANTIA DE BUNA EXECUTIE A LUCRARILOR, ORDINUL DE INCEPERE A LUCRARILOR EMIS PENTRU DATA DE 31.05.2021
5AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA BRASOV -
TARGU MURES - CLUJ -
ORADEA
0+000 4+500 S.C. STRABAG S.R.L. SECTOR 1C: TG. MURES - OGRA
LOT 1 - TARGU MURES -
UNGHENI (4.5 KM) + DRUM
DE LEGATURA (4.7 KM)
9.2 79.50% 63.87%
ORDIN DE
INCEPERE
PENTRU EXECUTIE
- 22 IULIE 2020
2022 (CONFORM
CONTRACT)
2021 -
CONFORM
ESTIMARE
ANTREPRENOR/
CNAIR SA
ANUL 2022192.06 MIL. LEI
FARA TVA
1. CONTRACT DE EXECUTIE SEMNAT IN DATA DE 29.05.2020.
2. AUTORIZATIE DE CONSTRUIRE VALABILA PENTRU ACEST SECTOR.
3. DURATA DE REALIZARE A ACESTUI CONTRACT ESTE URMATOAREA:
18 LUNI - PERIOADA DE EXECUTIE A LUCRARILOR;
108 LUNI (9 ANI) - PERIOADA DE GARANTIE A LUCRARILOR;
LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 3 PODURI SI PASAJE PE DRUMURI DE LEGATURA, 6 PODURI SI PASAJE PE AUTOSTRADA, PRECUM SI DOUA NODURI RUTIERE PENTRU CONECTAREA AUTOSTRAZII LA RETEAUA
DE DRUMURI EXISTENTA.
6AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA DE
CENTURA A
MUNICIPIULUI
BUCURESTI (A0)
47+600 52+070
ASOCIEREA S.C. SA&PE CONSTRUCT
S.R.L. - S.C. SPEDITION UMB S.R.L. -
S.C. TEHNOSTRADE S.R.L.
SECTOR NORD LOT 4 4.47 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024312.63 MIL. LEI
FARA TVA
IN DATA DE 17.05.2020, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL "PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 4 KM 47+600 - KM 52+070”, CU OFERTANTUL DECLARAT
CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.
VALOAREA CONTRACTULUI: 312.633.554,09 LEI FARA TVA.
LUNGIME: 4.47 KM
SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE.
DURATA CONTRACTULUI ESTE DE 150 LUNI, DIN CARE:
12 LUNI PERIOADA DE PROIECTARE,
18 LUNI PERIOADA DE EXECUTIE A LUCRARILOR
120 LUNI PERIOADA DE GARANTIE A LUCRARILOR
7AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA DE
CENTURA A
MUNICIPIULUI
BUCURESTI (A0)
20+000 39+000
ASOCIEREA SC SA & PE CONSTRUCT
SRL (LIDER DE ASOCIERE) -
SPEDITION UMB - TEHNOSTRADE
S.R.L.
SECTOR NORD LOT 2 19 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024831.92 MIL. LEI
FARA TVA
IN DATA DE 12.05.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL "PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 2 KM 20+000 - KM 39+000”, CU OFERTANTUL DECLARAT
CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.
VALOAREA CONTRACTULUI: 831.920.653,34 LEI FARA TVA.
LUNGIME: 19 KM
SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE.
DURATA CONTRACTULUI ESTE DE 154 LUNI, DIN CARE:
12 LUNI PERIOADA DE PROIECTARE,
22 LUNI PERIOADA DE EXECUȚIE A LUCRĂRILOR
120 LUNI PERIOADA DE GARANȚIE A LUCRĂRILOR
A FOST EMIS ORDIN DE INCEPERE IN DATA DE 16.08.2021
AUTOSTRĂZI
SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - OCTOMBRIE 2021
AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI - OCTOMBRIE 2021
8AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA DE
CENTURA A
MUNICIPIULUI
BUCURESTI (A0)
69+000 85+300ALSIM ALARKO SANAYI TESISLERI VE
TICARET A.S.SECTOR SUD LOT 2: VIDRA - BRAGADIRU 16.3 27.43%
34.75% -
PROGRES
FINANCIAR
(INCLUSIV AVANS
LUCRARI SI
ACTUALIZARI
PRETURI)
10.04.2019 -
ORDIN DE
INCEPERE A
ACTIVITATII DE
PROIECTARE
18.08.2020 -
ORDIN INCEPERE
LUCRARI KM
69+000 - KM
70+700
FEBRUARIE 2023 FEBRUARIE 2023750.85 MIL. LEI
FARA TVA
ORDIN DE INCEPERE A LUCRARILOR 18.08.2020 ETAPA 1: KM 69+000 - KM 70+700
DECIZIA PENTRU EXPROPRIERI AFERENTA HG 675/2020 A FOST EMISA IN DATA DE 15.10.2020
A FOST ACORDAT AVANSUL PENTRU EXECUTIE LUCRARI (15% DIN VALOAREA LUCRARILOR)
ORDINUL DE INCEPERE PENTRU ETAPA 2, CONSTAND IN INTREG ALINIAMENTUL LOTULUI 2, A FOST EMIS IN DATA DE 29.10.2020, DATA DE INCEPERE FIIND 05.11.2020 (14,6 KM)
A FOST PUBLICAT IN MONITORIUL OFICIAL HG NR. 1139/30.12.2020 PRIVIND IMOBILELE AFLATE PE CULOARUL SUPLIMENTAR, INCLUSIV DECIZIA DE EXPROPRIERE NR. 378/17.02.2021.
IN DATA DE 12.03.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 11 PENTRU ETAPA III, EXPROPRIERI SUPLIMENTARE
9AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA DE
CENTURA A
MUNICIPIULUI
BUCURESTI (A0)
52+070 69+000ALSIM ALARKO SANAYI TESISLERI VE
TICARET A.S.
SECTOR NORD - KM 52+070 – KM
52+770; SECTOR SUD - KM 52+770 –
KM 69+000
LOT 1: GLINA - VIDRA 16.93 10.75%
19.73% -
PROGRES
FINANCIAR
(INCLUSIV AVANS
LUCRARI)
03.10.2019 -
DATA DE
INCEPERE A
ACTIVITATII DE
PROIECTARE
IUNIE 2023 ANUL 2023830.68 MIL. LEI
FARA TVA
A FOST EMISA AUTORIZATIA DE CONSTRUIRE NR. 66/25.11.2020
A FOST APROBAT PROIECTUL TEHNIC DE EXECUTIE IN DATA DE 11.02.2021.
ORDIN DE INCEPERE LUCRARI 01.03.2021
A FOST PUBLICAT IN MONITORIUL OFICIAL HG 861/2021 PRIVIND IMOBILELE AFLATE PE CULOARUL SUPLIMENTAR
10AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA DE
CENTURA A
MUNICIPIULUI
BUCURESTI (A0)
85+300 -
100+765
SUD
0+000 -
2+500
NORD
ASOCIEREA AKTOR TECHNICAL
SOCIETE ANONYME (AKTOR S.A.) -
S.C. EURO CONSTRUCT TRADING 98
S.R.L.
SECTOR SUD - KM 85+300 - KM
100+765; SECTOR NORD - KM 0+000
+ KM 2+500
LOT 3: BRAGADIRU - JOITA 17.965 0.00%
1,03% (PROGRES
FINANCIAR
INCLUSIV AVANS
PROIECTARE)
23.05.2019 -
DATA DE
INCEPERE A
ACTIVITATII DE
PROIECTARE
DECEMBRIE 2022 DECEMBRIE 2022853.42 MIL. LEI
FARA TVA
ANTREPRENORUL A FINALIZAT DECLARATIA DE PROIECTARE (INREGISTRAND INTARZIERI MAJORE IN ACTIVITATEA DE PROIECTARE), FIIND PENALIZAT CONFORM CONTRACTULUI PENTRU NEINDEPLINIREA PUCTULUI DE REFERINTA NR 1 (FINALIZAREA DECLARATIEI DE
PROIECTARE).
PAC A FOST ANALIZAT SI APROBAT IN CADRUL CTE CNAIR IN DATA DE 11.06.2021.
A FOST EMISA AUTORIZATIA DE CONSTRUIRE nr. 33/01.07.2021 - etapa I (km 86+700 - km 100+765, km 0+000 - km 2+500)
LA DATA PREZENTEI, BENEFICIARUL A EMIS OBSERVATII ASUPRA PTE - REVIZIA 2, URMAND CA ACESTA SA ELABOREZE O NOUA REVIZIE A PROIECTULUI TEHNIC
11AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA SEBES -
TURDA17+000 41+250
ASOCIEREA AKTOR TECHNICAL
SOCIETE ANONYME (AKTOR S.A.) -
S.C. EURO CONSTRUCT TRADING 98
S.R.L.
SANTIMBRU - AIUD LOT 2 24.25 89.00% 87.74% 02.12.2014
APRILIE 2022 -
CONFORM
GRAFIC DE
LUCRARI
ESTIMARE DESCHIDERE
TRAFIC - NOIEMBRIE 2021
549.33 MIL. LEI
FARA TVA
TERMENUL DE DESCHIDERE A TRAFICULUI ESTE ESTIMAT PENTRU FINALUL ANULUI 2021, RECEPTIA LA TERMINAREA LUCRARILOR FIIND ESTIMATA PENTRU APRILIE 2022.
CONTRACT PROIECTARE SI EXECUTIE CU INTARZIERI MAJORE INREGISTRATE, DATORATE SLABEI MOBILIZARI A CONSTRUCTORULUI DIN ANII ANTERIORI, DAR SI DIN PREZENT, DATORATA LIPSEI RESURSELOR FINANCIARE PROPRII PENTRU SUSTINEREA SANTIERULUI;
PE ROLUL INSTANTELOR, SE AFLA DOUA DOSARE PRIVIND CONTESTATII ALE UNOR EXECUTARI SILITE PENTRU IMOBILELE NECESARE EXECUTIEI LUCRARILOR. STADIU PROCESUAL: APEL.
IN DATA DE 18.06.2021, ANTREPRENORUL SI-A ASUMAT SOLUTIA FINALA IN VEDEREA STABILIZARII NECESARE IN ZONA KM 19+300, IN BAZA EXPERTIZEI TEHNICE REALIZATA DE ACESTA. CNAIR SA VA FACE O CONTRAEXPERTIZA, CARE SA VERIFICE CAUZELE ALUNECARII DE
TEREN (ESTE FINALIZATA DOCUMENTATIA, IN SAPTAMANA 04.10 - 08.10.2021 VOR FI TRANSMISE INVITATIILKE DE PARTICIPARE).
APLICARE MECANISM PREVAZUT DE OUG 7/ 2016 PENTRU PLATA CAD NR. 1 - IN DATA DE 28.06.2021, AU FOST APROBATE DE CATRE ORDONATORUL PRINCIPAL DE CREDITE DOCUMENTELE PREVAZUTE PRIN ORDINUL MT 205/ 2021 . IN DATA DE 30.06.2021, A FOST
EFECTUATA PLATA SUMEI PREVAZUTA PRIN DECIZIA CAD NR. 1 (ESTE INCLUSA IN PROGRESUL FINANCIAR.
12AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA SEBES -
TURDA0+000 17+000
ASOCIEREA IMPRESA PIZZAROTTI & C
SPA POMPONIO CONSTRUCTII SRLLANCRAM - SANTIMBRU LOT 1 17 98.00% 96.62% 02.12.2014
DESCHIDERE
TRAFIC -
03.12.2020
FINALIZARE
CONTRACT:
OCTOMBRIE 2021
DESCHIS TRAFIC:15,5 KM
AUTOSTRADA, INTEGRAL
NOD RUTIER SEBES,NOD
RUTIER ALBA SUD
DESCARCARE PRIN NOD
RUTIER ALBA NORD IN
DATA DE 30.07.2021.IN
DATA DE 03.12.2020, A
FOST DESCHIS TRAFICUL
DOAR PRIN 2 BRETELE NOD
SEBES SI SECT PANA LA NOD
ALBA NORD
541.73 MIL. LEI
FARA TVA
TERMENUL DE FINALIZARE A LUCRARILOR IN DATA DE 15.08.2021 A FOST COMUNICAT DE CATRE ANTREPRENOR (CARE DORESTE RECEPTIA LA TERMINAREA LUCRARILOR), DAR NU A FOST RESPECTAT. TERMENUL ESTIMAT DE CNAIR SA PENTRU RECEPTIA LA TERMINAREA
LUCRARILOR ESTE 30.10.2021.
IN DATA DE 03.12.2020 S-A DESCHIS TRAFICUL PE UN TRONSON DE 15.5 KM. IN DATA DE 30.07.2021, A FOST DESCHIS IN INTEGRALITATE TRAFICUL LA NODUL SEBES, CARE FACE LEGATURA INTRE AUTOSTRADA A10 SI A1.
DESCHIDEREA TRAFICULUI PE TOATA LUNGIMEA SECTORULUI DE AUTOSTRADA VA AVEA LOC DOAR DUPA FINALIZAREA LUCRARILOR SI PE LOTUL 2, DEOARECE DESCARCAREA TRAFICULUI ESTE POSIBILA DOAR PRIN NODUL ALBA IULIA NORD DE LA KM 15+500.
APLICAREA DE PENALITATI ANTREPRENORULUI PRIN EMITEREA UNEI FACTURI DE PENALITĂȚI PENTRU SUMA STABILITĂ DE CĂTRE INGINER PRIN MODUL DE SOLUȚIONARE A REVENDICĂRII BENEFICIARULUI PRIVIND EȘECUL ANTREPRENORULUI DE A RESPECTA
PREVEDERILE SUB-CLAUZEI 8.2 [DURATA DE EXECUȚIE] IN VALOARE DE 81.260.870,58 LEI
APLICAREA DE PENALITATI ANTREPRENORULUI PRIN EMITEREA UNEI FACTURI DE PENALITĂȚI PENTRU SUMA STABILITĂ DE CĂTRE INGINER PRIN MODUL DE SOLUȚIONARE A REVENDICĂRII BENEFICIARULUI PRIVIND ÎNTÂRZIERI ÎN REMITEREA PROGRAMULUI DE EXECUȚIE
PL ST002E, IN VALOARE DE 3.250.000.00 LEI
13AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA SIBIU -
PITESTI91+761 122+110 ASTALDI SPA (ITALIA) CURTEA DE ARGES - PITESTI SECTIUNEA 5 30.35 0% 3.31%
IUNIE 2020 -
EMITERE ORDIN
ETAPA DE
PROIECTARE,
AUTORIZATIA DE
CONSTRUIRE
NR.31/17.06.202
1
IN DATA DE
01.09.2021 S-A
EMIS ORDINUL DE
INCEPERE A
EXECUTIEI
LUCRARILOR
2025 IN CF CU
PREVEDERILE CTR
DURATA DE
REALIZARE A
ACESTUI CTR ESTE
DE 60 DE LUNI,
RESPECTIV: 12
LUNI PERIODA DE
PROIECTARE SI 48
DE LUNI PENTRU
EXECUTIA
LUCRARILOR.
PERIOADA DE
GARANTIE A
LUCRARILOR
OFERTATA DE
ASTALDI SPA ESTE
DE 120 DE LUNI
ANUL 20251710 MIL. LEI
FARA TVA
22.06.2020 – ORDIN DE INCEPERE FAZA PROIECTARE (12 LUNI)
CONTRACT DE SERVICII NR.92/58937/11.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 5 – CURTEA DE ARGES – PITESTI KM 92+600-KM 122+950"""" SEMNAT CU ASOCIAREA EGIS INTERNATIONAL S.A.S – SEARCH CORPORATION S.R.L.- ITALROM
INGINERIE INTERNATIONALA S.R.L.- METROUL S.A, A INLOCUIT SUPERVIZORUL DRDP BUCURESTI INCEPAND CU DATA DE 01.10.2020
IN DATA DE 30.12.2020 A FOST PUBLICATA HOTARAREA DE GUVERN NR.1134 PENTRU REALIZAREA EXPROPRIERILOR PENTRU SUPRAFETELE DE TEREN AFLATE PE AZA LOCALITATILOR BUDEASA, CURTEA DE ARGES, MALURENI SI MUNICIPIUL PITESTI, DIN JUDETUL ARGES.
17.02.2021 - S-A EMIS DECIZIA DE EXPROPRIERE NR. 377/2020 PENTRU IMOBILELE DE PE RAZA LOCALITATILOR BUDEASA, CURTEA DE ARGES, MALURENI SI MUN. PITESTI
PROCEDURA DE EXPROPRIERE INTERGAL FINALIZATA
IN DATA DE 16.06.2021 S-A OBTINUT AUTORIZATIA DE CONSTRUIRE
IN DATA DE 01.09.2021 S-A EMIS ORDINUL DE INCEPERE A LUCRARILOR
IN DATA DE 16.09.2021, A FOST AVIZAT IN CTE CNAIR PROIECTUL TEHNIC DE EXECUTIE.
14AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA SIBIU -
PITESTI0+000 13+170 PORR CONSTRUCT SRL LOT 1: KM 0+000 - KM 13+170
SECTIUNEA 1: SIBIU - BOITA
(KM 0+000 - KM 14+150), LOT
1
13.17 50.00% 48.41%
29.05.2019 -
EMITERE ORDIN
DE INCEPERE
ETAPA DE
PROIECTARE,
30.03.2020 -
EMITERE ORDIN
DE INCEPERE
ETAPA EXECUTIE
LUCRARI
28.05.2023 ANUL 2023612.65 MIL. LEI
FARA TVA
PROIECTUL TEHNIC A FOST FINALIZAT SI APROBAT DE CATRE CNAIR SA IN DATA DE 01.04.2020.
AUTORIZATIA DE CONSTRUIRE A FOST EMISA IN DATA DE 09.03.2020.
CONTRACT DE SERVICII NR. 92/61673/22.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 1 –SIBIU – BOITA KM 0+000-KM 14+150"" ASOCIEREA TPF INGINERIE S.R.L. - SEPTEMBRIE CONSULTING S.R.L. A INLOCUIT SUPERVIZORUL DRDP BUCURESTI
INCEPAND CU DATA DE 19.10.2020
15AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIDRUM NATIONAL POD BRAILA
ASOCIEREA ASTALDI S.P. A - IHI
INFRASTRUCTURE SYSTEM CO. LTD.
POD SUSPENDAT PESTE DUNARE IN
ZONA BRAILA1
DRUM BRAILA-
JIJILA - 19,095
KM;
DRUM DE
LEGATURA CU
DN22 SMARDAN-
MACIN - 4,328
KM
48.50% 60.60% 21.12.2018
SECTIUNEA 2
DECEMBRIE 2021
TOTAL
CONTRACT:
ESTIMAT
DECEMBRIE 2022
DECEMBRIE 2021
SECTIUNEA 2 PODUL
SUSPENDAT
1.996 MLD. LEI
FARA TVACONTRACT IN DERULARE.
NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA BRASOV -
TARGU MURES - CLUJ -
ORADEA
30+550 59+100
ASOCIEREA TRAMECO SA –
VAHOSTAV -SK A.S. – DRUMURI
BIHOR SA – DRUM ASFALT SRL –
EAST WATER DRILLINGS SRL
SECTIUNEA 3C, SUBSECTIUNEA 3C2
CHIRIBIS - BIHARIA
SUBSECTIUNEA 3C2: CHIRIBIS -
BIHARIA28.55 0.50% 0%
14.09.2020 -
EMITERE ORDIN
DE INCEPERE
PENTRU ETAPA
DE PROIECTARE
(PROIECT TEHNIC)
MARTIE 2022
(CONFORM
CONTRACT)
IUNIE 2022
(CONFORM
PROGRAM)
ANUL 2022 6 LUNI - ETAPA
DE PROIECTARE; 18 LUNI -
ETAPA DE EXECUTIE
LUCRARI; 120 LUNI -
PERIOADA DE GARANTIE
326.51 MIL. LEI
FARA TVA
CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 11.08. 2020.
A FOST TRANSMISA CATRE ANTREPRENOR ADRESA CU ORDINUL DE INCEPERE PENTRU DATA DE 14.09.2020. A FOST ACORDAT DREPTUL DE ACCES IN SANTIER ANTREPRENORULUI.
DURATA CONTRACTULUI ESTE DE 144 DE LUNI DIN CARE:
6 LUNI - ETAPA DE PROIECTARE; FINALIZARE PUNCT DE REFERINTA NR. 1 IN 09.11.2020.
18 LUNI - ETAPA DE EXECUTIE LUCRARI
120 LUNI - PERIOADA DE GARANTIE
2AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA BRASOV -
TARGU MURES - CLUJ -
ORADEA
8+700 38+760
ASOCIEREA S.C. SPEDITION UMB
S.R.L. – S.C. TEHNOSTRADE S.R.L. –
S.C. ELECTROMONTAJ S.A
SECTIUNEA 3A SI SECTIUNEA 3B,
SUBSECTIUNEA 3A2: NADASELU -
MIHAIESTI SI 3B1: MIHAESTI ZIMBOR
SUBSECTIUNEA 3A2
NADASELU - MIHAIESTI KM
8+700 - 25+500+ 3B1,
MIHAIESTI – ZIMBOR KM
0+000 - 13+260
30.06 0% 0% 25.01.2021 2023 ANUL 20231.390,614 MIL.
LEI FARA TVA
SEMNARE CONTRACT PROIECTARE SI EXECUTIE IN DATA DE 28.12.2020. PRETUL PE KM DE AUTOSTRADA ESTE DE CCA. 46,261,293.92 LEI FARA TVA, REPREZENTAND CCA. 9,383,629 EURO FARA TVA.
DURATA CONTRACTULUI ESTE DE 96 DE LUNI, DIN CARE:
• 12 LUNI PERIOADA DE PROIECTARE,
• 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,
• 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.
AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3A2 IN LUNA APRILIE 2021.
AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3B1 IN 01.07.2021
PROIECT TEHNIC DE EXECUTIE PENTRU 3A2 AVIZAT IN CTE - CNAIR IN DATA DE 20.08.2021
PROIECT TEHNIC IN CURS DE ELABORARE PENTRU 3B1 - TERMEN ESTIMAT AVIZARE PROIECT TEHNIC: DEC. 2021
3AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA BRASOV -
TARGU MURES - CLUJ -
ORADEA
66+500 80+054 NUROL INSAAT VE TICARET S.ASECTIUNEA 3B, SUBSECTIUNEA 3B5
NUSFALAU - SUPLACU DE BARCAU
SUBSECTIUNEA 3B5:
NUSFALAU - SUPLACU DE
BARCAU
13.55 4.34% 15.75% 01.02.2021 FEBRUARIE 2023 FEBRUARIE 2023384.14 MIL. LEI
FARA TVA
CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN 30.09.2020;
6 LUNI PERIOADA DE PROIECTARE
; 18 LUNI PERIOADA DE EXECUTIE
; 120 LUNI PERIOADA DE GARANTIE
LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 12 STRUCTURI (4 PASAJE SI 8 PODURI), RESPECTIV UN NOD RUTIER LA KM 67+500
FINALIZARE ETAPA PROIECTARE (PTE) - PROIECTUL TEHNIC DE EXECUTIE A FOST AVIZAT IN CADRUL CTE IN DATA DE 02.08.2021
4AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA BRASOV -
TARGU MURES - CLUJ -
ORADEA
13+260 25+500
ASOCIEREA SC SA&PE CONSTRUCT
SRL - SC SPEDITION UMB SRL - SC
TEHNOSTRADE SRL
SECTIUNEA 3B, SUBSECTIUNEA 3B2:
ZIMBOR - POARTA SALAJULUI
SUBSECTIUNEA 3B2: ZIMBOR -
POARTA SALAJULUI12.24 0% 0%
31.05.2021 -
ORDIN DE
INCEPERE
2023 ANUL 2023680.40 MIL. LEI
FARA TVA
CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 01.07.2020;
DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE:
12 LUNI PERIOADA DE PROIECTARE,
24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,
120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR
A FOST CONSTITUITA GARANTIA DE BUNA EXECUTIE A LUCRARILOR, ORDINUL DE INCEPERE A LUCRARILOR EMIS PENTRU DATA DE 31.05.2021
5AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA BRASOV -
TARGU MURES - CLUJ -
ORADEA
0+000 4+500 S.C. STRABAG S.R.L. SECTOR 1C: TG. MURES - OGRA
LOT 1 - TARGU MURES -
UNGHENI (4.5 KM) + DRUM
DE LEGATURA (4.7 KM)
9.2 79.50% 63.87%
ORDIN DE
INCEPERE
PENTRU EXECUTIE
- 22 IULIE 2020
2022 (CONFORM
CONTRACT)
2021 -
CONFORM
ESTIMARE
ANTREPRENOR/
CNAIR SA
ANUL 2022192.06 MIL. LEI
FARA TVA
1. CONTRACT DE EXECUTIE SEMNAT IN DATA DE 29.05.2020.
2. AUTORIZATIE DE CONSTRUIRE VALABILA PENTRU ACEST SECTOR.
3. DURATA DE REALIZARE A ACESTUI CONTRACT ESTE URMATOAREA:
18 LUNI - PERIOADA DE EXECUTIE A LUCRARILOR;
108 LUNI (9 ANI) - PERIOADA DE GARANTIE A LUCRARILOR;
LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 3 PODURI SI PASAJE PE DRUMURI DE LEGATURA, 6 PODURI SI PASAJE PE AUTOSTRADA, PRECUM SI DOUA NODURI RUTIERE PENTRU CONECTAREA AUTOSTRAZII LA RETEAUA
DE DRUMURI EXISTENTA.
6AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA DE
CENTURA A
MUNICIPIULUI
BUCURESTI (A0)
47+600 52+070
ASOCIEREA S.C. SA&PE CONSTRUCT
S.R.L. - S.C. SPEDITION UMB S.R.L. -
S.C. TEHNOSTRADE S.R.L.
SECTOR NORD LOT 4 4.47 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024312.63 MIL. LEI
FARA TVA
IN DATA DE 17.05.2020, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL "PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 4 KM 47+600 - KM 52+070”, CU OFERTANTUL DECLARAT
CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.
VALOAREA CONTRACTULUI: 312.633.554,09 LEI FARA TVA.
LUNGIME: 4.47 KM
SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE.
DURATA CONTRACTULUI ESTE DE 150 LUNI, DIN CARE:
12 LUNI PERIOADA DE PROIECTARE,
18 LUNI PERIOADA DE EXECUTIE A LUCRARILOR
120 LUNI PERIOADA DE GARANTIE A LUCRARILOR
7AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA DE
CENTURA A
MUNICIPIULUI
BUCURESTI (A0)
20+000 39+000
ASOCIEREA SC SA & PE CONSTRUCT
SRL (LIDER DE ASOCIERE) -
SPEDITION UMB - TEHNOSTRADE
S.R.L.
SECTOR NORD LOT 2 19 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024831.92 MIL. LEI
FARA TVA
IN DATA DE 12.05.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL "PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 2 KM 20+000 - KM 39+000”, CU OFERTANTUL DECLARAT
CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.
VALOAREA CONTRACTULUI: 831.920.653,34 LEI FARA TVA.
LUNGIME: 19 KM
SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE.
DURATA CONTRACTULUI ESTE DE 154 LUNI, DIN CARE:
12 LUNI PERIOADA DE PROIECTARE,
22 LUNI PERIOADA DE EXECUȚIE A LUCRĂRILOR
120 LUNI PERIOADA DE GARANȚIE A LUCRĂRILOR
A FOST EMIS ORDIN DE INCEPERE IN DATA DE 16.08.2021
AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI - OCTOMBRIE 2021
8AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA DE
CENTURA A
MUNICIPIULUI
BUCURESTI (A0)
69+000 85+300ALSIM ALARKO SANAYI TESISLERI VE
TICARET A.S.SECTOR SUD LOT 2: VIDRA - BRAGADIRU 16.3 27.43%
34.75% -
PROGRES
FINANCIAR
(INCLUSIV AVANS
LUCRARI SI
ACTUALIZARI
PRETURI)
10.04.2019 -
ORDIN DE
INCEPERE A
ACTIVITATII DE
PROIECTARE
18.08.2020 -
ORDIN INCEPERE
LUCRARI KM
69+000 - KM
70+700
FEBRUARIE 2023 FEBRUARIE 2023750.85 MIL. LEI
FARA TVA
ORDIN DE INCEPERE A LUCRARILOR 18.08.2020 ETAPA 1: KM 69+000 - KM 70+700
DECIZIA PENTRU EXPROPRIERI AFERENTA HG 675/2020 A FOST EMISA IN DATA DE 15.10.2020
A FOST ACORDAT AVANSUL PENTRU EXECUTIE LUCRARI (15% DIN VALOAREA LUCRARILOR)
ORDINUL DE INCEPERE PENTRU ETAPA 2, CONSTAND IN INTREG ALINIAMENTUL LOTULUI 2, A FOST EMIS IN DATA DE 29.10.2020, DATA DE INCEPERE FIIND 05.11.2020 (14,6 KM)
A FOST PUBLICAT IN MONITORIUL OFICIAL HG NR. 1139/30.12.2020 PRIVIND IMOBILELE AFLATE PE CULOARUL SUPLIMENTAR, INCLUSIV DECIZIA DE EXPROPRIERE NR. 378/17.02.2021.
IN DATA DE 12.03.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 11 PENTRU ETAPA III, EXPROPRIERI SUPLIMENTARE
9AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA DE
CENTURA A
MUNICIPIULUI
BUCURESTI (A0)
52+070 69+000ALSIM ALARKO SANAYI TESISLERI VE
TICARET A.S.
SECTOR NORD - KM 52+070 – KM
52+770; SECTOR SUD - KM 52+770 –
KM 69+000
LOT 1: GLINA - VIDRA 16.93 10.75%
19.73% -
PROGRES
FINANCIAR
(INCLUSIV AVANS
LUCRARI)
03.10.2019 -
DATA DE
INCEPERE A
ACTIVITATII DE
PROIECTARE
IUNIE 2023 ANUL 2023830.68 MIL. LEI
FARA TVA
A FOST EMISA AUTORIZATIA DE CONSTRUIRE NR. 66/25.11.2020
A FOST APROBAT PROIECTUL TEHNIC DE EXECUTIE IN DATA DE 11.02.2021.
ORDIN DE INCEPERE LUCRARI 01.03.2021
A FOST PUBLICAT IN MONITORIUL OFICIAL HG 861/2021 PRIVIND IMOBILELE AFLATE PE CULOARUL SUPLIMENTAR
10AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA DE
CENTURA A
MUNICIPIULUI
BUCURESTI (A0)
85+300 -
100+765
SUD
0+000 -
2+500
NORD
ASOCIEREA AKTOR TECHNICAL
SOCIETE ANONYME (AKTOR S.A.) -
S.C. EURO CONSTRUCT TRADING 98
S.R.L.
SECTOR SUD - KM 85+300 - KM
100+765; SECTOR NORD - KM 0+000
+ KM 2+500
LOT 3: BRAGADIRU - JOITA 17.965 0.00%
1,03% (PROGRES
FINANCIAR
INCLUSIV AVANS
PROIECTARE)
23.05.2019 -
DATA DE
INCEPERE A
ACTIVITATII DE
PROIECTARE
DECEMBRIE 2022 DECEMBRIE 2022853.42 MIL. LEI
FARA TVA
ANTREPRENORUL A FINALIZAT DECLARATIA DE PROIECTARE (INREGISTRAND INTARZIERI MAJORE IN ACTIVITATEA DE PROIECTARE), FIIND PENALIZAT CONFORM CONTRACTULUI PENTRU NEINDEPLINIREA PUCTULUI DE REFERINTA NR 1 (FINALIZAREA DECLARATIEI DE
PROIECTARE).
PAC A FOST ANALIZAT SI APROBAT IN CADRUL CTE CNAIR IN DATA DE 11.06.2021.
A FOST EMISA AUTORIZATIA DE CONSTRUIRE nr. 33/01.07.2021 - etapa I (km 86+700 - km 100+765, km 0+000 - km 2+500)
LA DATA PREZENTEI, BENEFICIARUL A EMIS OBSERVATII ASUPRA PTE - REVIZIA 2, URMAND CA ACESTA SA ELABOREZE O NOUA REVIZIE A PROIECTULUI TEHNIC
11AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA SEBES -
TURDA17+000 41+250
ASOCIEREA AKTOR TECHNICAL
SOCIETE ANONYME (AKTOR S.A.) -
S.C. EURO CONSTRUCT TRADING 98
S.R.L.
SANTIMBRU - AIUD LOT 2 24.25 89.00% 87.74% 02.12.2014
APRILIE 2022 -
CONFORM
GRAFIC DE
LUCRARI
ESTIMARE DESCHIDERE
TRAFIC - NOIEMBRIE 2021
549.33 MIL. LEI
FARA TVA
TERMENUL DE DESCHIDERE A TRAFICULUI ESTE ESTIMAT PENTRU FINALUL ANULUI 2021, RECEPTIA LA TERMINAREA LUCRARILOR FIIND ESTIMATA PENTRU APRILIE 2022.
CONTRACT PROIECTARE SI EXECUTIE CU INTARZIERI MAJORE INREGISTRATE, DATORATE SLABEI MOBILIZARI A CONSTRUCTORULUI DIN ANII ANTERIORI, DAR SI DIN PREZENT, DATORATA LIPSEI RESURSELOR FINANCIARE PROPRII PENTRU SUSTINEREA SANTIERULUI;
PE ROLUL INSTANTELOR, SE AFLA DOUA DOSARE PRIVIND CONTESTATII ALE UNOR EXECUTARI SILITE PENTRU IMOBILELE NECESARE EXECUTIEI LUCRARILOR. STADIU PROCESUAL: APEL.
IN DATA DE 18.06.2021, ANTREPRENORUL SI-A ASUMAT SOLUTIA FINALA IN VEDEREA STABILIZARII NECESARE IN ZONA KM 19+300, IN BAZA EXPERTIZEI TEHNICE REALIZATA DE ACESTA. CNAIR SA VA FACE O CONTRAEXPERTIZA, CARE SA VERIFICE CAUZELE ALUNECARII DE
TEREN (ESTE FINALIZATA DOCUMENTATIA, IN SAPTAMANA 04.10 - 08.10.2021 VOR FI TRANSMISE INVITATIILKE DE PARTICIPARE).
APLICARE MECANISM PREVAZUT DE OUG 7/ 2016 PENTRU PLATA CAD NR. 1 - IN DATA DE 28.06.2021, AU FOST APROBATE DE CATRE ORDONATORUL PRINCIPAL DE CREDITE DOCUMENTELE PREVAZUTE PRIN ORDINUL MT 205/ 2021 . IN DATA DE 30.06.2021, A FOST
EFECTUATA PLATA SUMEI PREVAZUTA PRIN DECIZIA CAD NR. 1 (ESTE INCLUSA IN PROGRESUL FINANCIAR.
12AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA SEBES -
TURDA0+000 17+000
ASOCIEREA IMPRESA PIZZAROTTI & C
SPA POMPONIO CONSTRUCTII SRLLANCRAM - SANTIMBRU LOT 1 17 98.00% 96.62% 02.12.2014
DESCHIDERE
TRAFIC -
03.12.2020
FINALIZARE
CONTRACT:
OCTOMBRIE 2021
DESCHIS TRAFIC:15,5 KM
AUTOSTRADA, INTEGRAL
NOD RUTIER SEBES,NOD
RUTIER ALBA SUD
DESCARCARE PRIN NOD
RUTIER ALBA NORD IN
DATA DE 30.07.2021.IN
DATA DE 03.12.2020, A
FOST DESCHIS TRAFICUL
DOAR PRIN 2 BRETELE NOD
SEBES SI SECT PANA LA NOD
ALBA NORD
541.73 MIL. LEI
FARA TVA
TERMENUL DE FINALIZARE A LUCRARILOR IN DATA DE 15.08.2021 A FOST COMUNICAT DE CATRE ANTREPRENOR (CARE DORESTE RECEPTIA LA TERMINAREA LUCRARILOR), DAR NU A FOST RESPECTAT. TERMENUL ESTIMAT DE CNAIR SA PENTRU RECEPTIA LA TERMINAREA
LUCRARILOR ESTE 30.10.2021.
IN DATA DE 03.12.2020 S-A DESCHIS TRAFICUL PE UN TRONSON DE 15.5 KM. IN DATA DE 30.07.2021, A FOST DESCHIS IN INTEGRALITATE TRAFICUL LA NODUL SEBES, CARE FACE LEGATURA INTRE AUTOSTRADA A10 SI A1.
DESCHIDEREA TRAFICULUI PE TOATA LUNGIMEA SECTORULUI DE AUTOSTRADA VA AVEA LOC DOAR DUPA FINALIZAREA LUCRARILOR SI PE LOTUL 2, DEOARECE DESCARCAREA TRAFICULUI ESTE POSIBILA DOAR PRIN NODUL ALBA IULIA NORD DE LA KM 15+500.
APLICAREA DE PENALITATI ANTREPRENORULUI PRIN EMITEREA UNEI FACTURI DE PENALITĂȚI PENTRU SUMA STABILITĂ DE CĂTRE INGINER PRIN MODUL DE SOLUȚIONARE A REVENDICĂRII BENEFICIARULUI PRIVIND EȘECUL ANTREPRENORULUI DE A RESPECTA
PREVEDERILE SUB-CLAUZEI 8.2 [DURATA DE EXECUȚIE] IN VALOARE DE 81.260.870,58 LEI
APLICAREA DE PENALITATI ANTREPRENORULUI PRIN EMITEREA UNEI FACTURI DE PENALITĂȚI PENTRU SUMA STABILITĂ DE CĂTRE INGINER PRIN MODUL DE SOLUȚIONARE A REVENDICĂRII BENEFICIARULUI PRIVIND ÎNTÂRZIERI ÎN REMITEREA PROGRAMULUI DE EXECUȚIE
PL ST002E, IN VALOARE DE 3.250.000.00 LEI
13AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA SIBIU -
PITESTI91+761 122+110 ASTALDI SPA (ITALIA) CURTEA DE ARGES - PITESTI SECTIUNEA 5 30.35 0% 3.31%
IUNIE 2020 -
EMITERE ORDIN
ETAPA DE
PROIECTARE,
AUTORIZATIA DE
CONSTRUIRE
NR.31/17.06.202
1
IN DATA DE
01.09.2021 S-A
EMIS ORDINUL DE
INCEPERE A
EXECUTIEI
LUCRARILOR
2025 IN CF CU
PREVEDERILE CTR
DURATA DE
REALIZARE A
ACESTUI CTR ESTE
DE 60 DE LUNI,
RESPECTIV: 12
LUNI PERIODA DE
PROIECTARE SI 48
DE LUNI PENTRU
EXECUTIA
LUCRARILOR.
PERIOADA DE
GARANTIE A
LUCRARILOR
OFERTATA DE
ASTALDI SPA ESTE
DE 120 DE LUNI
ANUL 20251710 MIL. LEI
FARA TVA
22.06.2020 – ORDIN DE INCEPERE FAZA PROIECTARE (12 LUNI)
CONTRACT DE SERVICII NR.92/58937/11.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 5 – CURTEA DE ARGES – PITESTI KM 92+600-KM 122+950"""" SEMNAT CU ASOCIAREA EGIS INTERNATIONAL S.A.S – SEARCH CORPORATION S.R.L.- ITALROM
INGINERIE INTERNATIONALA S.R.L.- METROUL S.A, A INLOCUIT SUPERVIZORUL DRDP BUCURESTI INCEPAND CU DATA DE 01.10.2020
IN DATA DE 30.12.2020 A FOST PUBLICATA HOTARAREA DE GUVERN NR.1134 PENTRU REALIZAREA EXPROPRIERILOR PENTRU SUPRAFETELE DE TEREN AFLATE PE AZA LOCALITATILOR BUDEASA, CURTEA DE ARGES, MALURENI SI MUNICIPIUL PITESTI, DIN JUDETUL ARGES.
17.02.2021 - S-A EMIS DECIZIA DE EXPROPRIERE NR. 377/2020 PENTRU IMOBILELE DE PE RAZA LOCALITATILOR BUDEASA, CURTEA DE ARGES, MALURENI SI MUN. PITESTI
PROCEDURA DE EXPROPRIERE INTERGAL FINALIZATA
IN DATA DE 16.06.2021 S-A OBTINUT AUTORIZATIA DE CONSTRUIRE
IN DATA DE 01.09.2021 S-A EMIS ORDINUL DE INCEPERE A LUCRARILOR
IN DATA DE 16.09.2021, A FOST AVIZAT IN CTE CNAIR PROIECTUL TEHNIC DE EXECUTIE.
14AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIAUTOSTRADA
AUTOSTRADA SIBIU -
PITESTI0+000 13+170 PORR CONSTRUCT SRL LOT 1: KM 0+000 - KM 13+170
SECTIUNEA 1: SIBIU - BOITA
(KM 0+000 - KM 14+150), LOT
1
13.17 50.00% 48.41%
29.05.2019 -
EMITERE ORDIN
DE INCEPERE
ETAPA DE
PROIECTARE,
30.03.2020 -
EMITERE ORDIN
DE INCEPERE
ETAPA EXECUTIE
LUCRARI
28.05.2023 ANUL 2023612.65 MIL. LEI
FARA TVA
PROIECTUL TEHNIC A FOST FINALIZAT SI APROBAT DE CATRE CNAIR SA IN DATA DE 01.04.2020.
AUTORIZATIA DE CONSTRUIRE A FOST EMISA IN DATA DE 09.03.2020.
CONTRACT DE SERVICII NR. 92/61673/22.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 1 –SIBIU – BOITA KM 0+000-KM 14+150"" ASOCIEREA TPF INGINERIE S.R.L. - SEPTEMBRIE CONSULTING S.R.L. A INLOCUIT SUPERVIZORUL DRDP BUCURESTI
INCEPAND CU DATA DE 19.10.2020
15AUTOSTRAZI IN EXECUTIE / PROIECTARE SI
EXECUTIE LUCRARIDRUM NATIONAL POD BRAILA
ASOCIEREA ASTALDI S.P. A - IHI
INFRASTRUCTURE SYSTEM CO. LTD.
POD SUSPENDAT PESTE DUNARE IN
ZONA BRAILA1
DRUM BRAILA-
JIJILA - 19,095
KM;
DRUM DE
LEGATURA CU
DN22 SMARDAN-
MACIN - 4,328
KM
48.50% 60.60% 21.12.2018
SECTIUNEA 2
DECEMBRIE 2021
TOTAL
CONTRACT:
ESTIMAT
DECEMBRIE 2022
DECEMBRIE 2021
SECTIUNEA 2 PODUL
SUSPENDAT
1.996 MLD. LEI
FARA TVACONTRACT IN DERULARE.
NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA
AUTOSTRADA BRASOV -
BACAU 0+000 165+000
SEARCH CORPORATION&
PRIMACONS GRUP SRL - CONTRACT
PROIECTARE ELABORARE STUDIU DE
FEZABILITATE SI PROIECT TEHNIC
(VALOARE CONTRACT PROIECTARE:
20.093.359,86 LEI FARA TVA)
BRASOV - BACAU LOT 1 165 0% 0%
22.05.2020 -
DATA SEMNARII
CONTRACTULUI
DE PRESTARI
SERVICII DE
PROIECTARE
(STUDIU DE
FEZABILITATE SI
ELABORARE
PROIECT TEHNIC)
10.07.2020 -
ORDIN INCEPERE
ETAPA DE
PROIECTARE
2023 -
FINALIZARE
PROIECTARE
(SF+PT)
ANUL 2023 - FINALIZARE
PROIECTARE (SF+PT)
8858.21 MIL. LEI
FARA TVA
DURATA CONTRACTULUI ESTE DE 30 LUNI.
ORDINUL DE INCEPERE: 10.07.2020
PRESTATORUL A ELABORAT ANALIZA MULTICRITERIALA PRIVIND ALEGEREA ALTERNATIVELOR DE TRASEU, ETAPA 1.
A FOST AVIZAT IN CTE CNAIR SA - ANALIZA MULTICRITERIALA ETAPA 1.
AU FOST FINALIZATE STUDIILE DE TEREN AFERENT PROIECTULUI PRELIMINAR (STUDII TOPOGRAFICE SI GEOTEHNICE).
A FOST INAINTATA ANALIZA MULTICRITERIALA NR. 2, IN ANALIZA JASPERS
2AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA A1 SI A3 SEARCH CORPORATION SRL
ELABORARE STUDIU DE
FEZABILITATE SI PROIECT TEHNIC DE
EXECUTIE PENTRU 6 NODURI
RUTIERE PE A1 SI A3 IN ZONA DE
VEST A ROMANIEI
A1(KM 326+155) - DJ
704(CUGHIR),A1(KM
362+813) - DC
129(SANTUHALM),A1(KM
485+030 - DJ
609E(RECAS),A1(KM 450+210)
- DJ 609(BETTHAUSEN),A1(KM
528+509) - DJ
682G(CRUCENI),A3(KM
39+940) - DN1P(SPINUS)
0% 0% 22.04.2021 22.06.2022
CONTRACT SEMNAT IN DATA DE 17.03.2021
ORDINUL DE INCEPERE A ACTIVITATII DE PROIECTARE A FOST EMIS IN DATA DE 22.04.2021
DURATA CONTRACTULUI ESTE DE 14 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI, DIN CARE:
-6 LUNI PENTRU ELABORAREA STUDIULUI DE FEZABILITATE,
- 4 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA LUCRARILOR DE CONSTRUIRE,
- 3 LUNI PENTRU ELABORAREA PROIECTULUI TEHNIC DE EXECUTIE SI
- 1 LUNI PENTRU ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFICIARULUI.
A AVUT LOC SEDINTA DE INCEPUT IN DATA DE 22.04.2021. A FOST APROBAT RAPORTUL DE PROGRES NR.3
3AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA
AUTOSTRADA TARGU
NEAMT - IASI -
UNGHENI
0+000 100+140 SC CONSITRANS S.R.L.TARGU NEAMT - IASI (LETCANI) -
UNGHENI100.14
2021 - SERVICII
DE PROIECTARE
FAZA S.F. + P.A.C.
+ P.T.E. SECTIUNE
TARGU NEAMT -
IASI-UNGHENI
2023 -
FINALIZARE
PROIECTARE
ANUL 2025 - PERIOADA
ESTIMATA DESCHIDERE
TRAFIC PENTRU PRIMELE
SECTIUNI
58.83 MIL. LEI
FARA TVA
(VALOARE
CONTRACT
COMPLETARE/RE
VIZUIRE/ACTUALI
ZARE S.F. SI
ELABORARE P.A.C.
+ P.A.D. + P.T.E)
IN DATA DE 08.04.2021 A FOST SEMNAT CONTRACTUL DE SERVICII „COMPLETARE/ REVIZUIRE/ ACTUALIZARE STUDIU DE FEZABILITATE SI ELABORARE P.A.C., P.A.D. SI P.T.E. PENTRU OBIECTIVUL „AUTOSTRADA TARGU-NEAMT – IASI – UNGHENI” CU SC CONSITRANS S.R.L.
PRETUL CONTRACTULUI ESTE DE 58.830.448,35 LEI FARA TVA
IN DATA DE 07.05.2021 A AVUT LOC SEDINTA DE INCEPUT
IN DATA DE 15.09.2021 A FOST INAINTATA DOCUMENTATIA ANALIZA MULTICRITERIALA ETAPA 1, IN PREZENT ACEASTA ESTE IN ANALIZA (TERMEN 05.10.2021)
DURATA DE REALIZARE A SERVICIILOR DE PROIECTARE ESTE DUPA CUM URMEAZA:
12 LUNI PENTRU REALIZAREA STUDIULUI DE FEZABILITATE;
5 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA EXECUTARII LUCRARILOR DE CONSTRUIRE (PAC) SI OBTINEREA AUTORIZATIEI DE CONSTRUIRE;
5 LUNI PENTRU REALIZAREA PROIECTULUI TEHNIC DE EXECUTIE (PTE)
4AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA
AUTOSTRADA SIBIU -
BRASOV 0+000 68+050
CONSITRANS
(VALOARE CONTRACT PROIECTARE:
16.313.855,49 FARA TVA)
SIBIU - FAGARAS LOT 1 68.05 22.00%
ORDIN DE
INCEPERE
11.05.2015
TRIM III 2021/
FINALIZARE
PROIECTARE FAZA
REVIZUIRE
STUDIU DE
FEZABILITATE
FINALIZARE PROIECTARE
(EMITERE ACORD DE
MEDIU) - TRIM. III 2021
5170 MIL. LEI
FARA TVACONTRACT REVIZUIRE STUDIU DE FEZABILITATE IN DERULARE - STUDIUL DE FEZABILITATE A FOST AVIZAT IN CADRUL CTE, PROCEDURA DE MEDIU IN DERULARE
5AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA
AUTOSTRADA SIBIU -
BRASOV 0+000 48+410
ASOCIEREA SEARCH CORPORATION
S.R.L. - PROTELCO S.A. - LIKE
CONSULTING S.R.L. – MEGA
MUHENDISLIK MUSAVIRLIK A.S.
(MEGA ENGINEERING CONSULTING
INC.)
FAGARAS - BRASOV LOT 2 48.41 0% 0% 2021 202318.17 MIL LEI
FARA TVA
IN DATA DE 23.08.2021, CNAIR A SEMNAT CONTRACTUL PENTRU „COMPLETARE STUDIU DE FEZABILITATE ȘI PROIECT TEHNIC PENTRU ""AUTOSTRADA BRAȘOV - FĂGĂRAȘ”, CU OFERTANTUL DECLARAT CÂȘTIGĂTOR ASOCIEREA SEARCH CORPORATION S.R.L. - PROTELCO
S.A. - LIKE CONSULTING S.R.L. – MEGA MUHENDISLIK MUSAVIRLIK A.S. (MEGA ENGINEERING CONSULTING INC.).
VALOAREA CONTRACTULUI ESTE DE 18.174.952,71 LEI FĂRĂ TVA.
SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE.
CONTRACTUL DE SERVICII ESTE STRUCTURAT ASTFEL:
• ETAPA I: 25 LUNI
STUDIU DE FEZABILITATE: 22 LUNI
PROIECT PENTRU AUTORIZAREA EXECUTĂRII LUCRĂRILOR DE CONSTRUIRE (P.A.C.) ȘI
ASISTENȚĂ TEHNICĂ ACORDATĂ BENEFICIARULUI PENTRU SUSŢINEREA APLICAŢIEI DE FINANŢARE: 3 LUNI
• ETAPA II: 6 LUNI
PROIECT TEHNIC (P.T.): 3 LUNI
ASISTENȚĂ TEHNICĂ ACORDATĂ BENEFICIARULUI PENTRU PROCEDURA DE ATRIBUIRE A EXECUŢIEI LUCRĂRILOR: 2 LUNI
RAPORT FINANCIAR FINAL: 1 LUNĂ.
• ETAPA III: 36 LUNI
ASISTENȚĂ TEHNICĂ ACORDATĂ BENEFICIARULUI PE DURATA EXECUŢIEI LUCRĂRILOR, CU CONDIŢIA DEMARĂRII LUCRĂRILOR NU MAI TÂRZIU DE 3 ANI DE LA APROBAREA PROIECTULUI TEHNIC.
6AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA
AUTOSTRADA TARGU
MURES - TARGU NEAMT 0+000 211+000
PROIECTANT: INGENIERIA
ESPECIALIZADA OBRA CIVIL E
INDUSTRIAL SA
TARGU MURES - TARGU NEAMT LOT 1 211 52% 11% 28.05.2019
25.07.2021
(CONFORM ACT
ADITIONAL LA
CTR DE PRESTARI
SERVICII)
ANUL 2021 - FINALIZARE
PROIECTARE
2025 - PERIOADA ESTIMATA
PENTRU DESCHIDEREA
PRIMELOR SECTIUNI
17.58 MIL. LEI
FARA TVA
IN DATA DE 28.05.2019 A FOST SEMNAT CONTRACTUL DE SERVICII 92/36788 AFERENT „COMPLETARE STUDIU DE FEZABILITATE PENTRU AUTOSTRADA TARGU MURES – TARGU NEAMT”.
TERMEN INITIAL DE FINALIZARE A REVIZUIRII STUDIULUI DE FEZABILITATE - 25.01.2021.
CONTRACT DE REVIZUIRE SF IN DERULARE
IN DATA DE 31.07.2020 A FOST SEMNAT ADITIONALUL NR. 1, PRIN CARE SE PRELUNGESTE TERMENUL DE FINALIZARE AL SERVICIILOR DE PROIECTARE CU 6 LUNI.
TERMEN DE FINALIZARE CONFORM ACT ADITIONAL - 25.07.2021
EMITEREA DECIZIEI ETAPEI DE INCADRARE INITIALE ANPM IN DATA DE 18.09.2020.
IN DATA DE 31.09.2020 A AVUT LOC SEDINTA PENTRU AVIZAREA IN CTE / CNAIR A TRASEULUI CORECTAT CONFORM CONSTRANGERILOR IDENTIFICATE. PENTRU FINALIZAREA AVIZARII CTE A FOST SOLICITATA COMPLETAREA DOCUMENTATIEI.
IN DATA DE 05.11.2020 A FOST AVIZAT TRASEUL FINAL IN COMISIA CTE CNAIR.
IN DATA DE 27.01.2021 A FOST APROBAT STUDIU TOPOGRAFIC. MASURATORI TOPOGRAFICE CU TEHNOLOGIA LIDAR
IN DATA DE 25.03.2021 A FOST APROBAT STUDIUL GEOTEHNIC AFERENT TRONSON: DITRAU - TARGU NEAMT, SECTOR 4 KM 95+600 – KM 118+800.
AU FOST FINALIZATE INVESTIGATIILE IN SITU PE JUD. MURES SI JUD. HARGHITA SI AU FOST AVIZATE STUDIILE ARHEOLOGICE ETAPA 2 JUD. HARGHITA SI JUD. MURES
- IN DATA DE 16.04.2021 A FOST INAINTATA O VARIANTA PRELIMINARA A STUDIULUI DE FEZABILITATE
AU FOST FINALIZATE INVESTIGATIILE IN SITU PE JUD. NEAMT SI JUD. IASI SI AU FOST AVIZATE STUDIILE ARHEOLOGICE ETAPA 2 JUD. NEAMT SI JUD. IASI
A FOST EMISA DECIZIA ETAPEI DE INCADRARE CU NR. 90 DIN 22.06.2021
AU FOST FINALIZATE INVESTIGATIILE GEOTEHNICE IN TEREN.
IN DATA DE 09.08.2021 A FOST INAINTAT STUDIUL DE FEZABILITATE PENTRU AUTOSTRADA TARGU MURES-TARGU NEAMT_REV1. IN DATA DE 30.07.2021 AU FOST EMISE OBSERVATII
IN PREZENT DOCUMENTATIA ESTE REVIZUITA DE CATRE PRESTATOR
AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) - OCTOMBRIE 2021
7AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA
AUTOSTRADA
TIMISOARA - MORAVITA0+000 60+000
SEARCH CORPORATION & EGIS
ROMANIA- CONTRACT PROIECTARE
ELABORARE SF SEMNAT IN DATA DE
4 MARTIE 2020
(VALOARE CONTRACT PROIECTARE:
8.727.474,68 FARA TVA)
TIMISOARA – MORAVITA LOT 1 6004.03.2020 -
ELABORARE SF
MAI 2022 -
TERMEN
FINALIZARE
PROIECTARE;
PERIOADA
CONTRACTUALA
DE PRESTARE A
SERVICIILOR - 24
LUNI
MAI 2022 - TERMEN
FINALIZARE PROIECTARE
141.6 MIL. LEI
FARA TVA
ETAPA DE PROIECTARE (ELABORARE STUDIU DE FEZABILITATE) IN DERULARE.
S-A AVIZAT IN CTE-CNAIR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU, ETAPA 1
A FOST TRANSMISA DOCUMENTATIA AMC ETAPA 2 REVIZIA 3.
DOCUMENTATIA AMC 2 REVIZIA 3 SE AFLA LA JASPERS PENTRU OBSERVATII.
8AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA
AUTOSTRADA BACAU -
PASCANI0+000 77+394
INGINERIA ESPECIALIZADA OBRA
CIVIL E INDUSTRIAL SA - CONTRACT
ELABORARE SF SI PT IN DERULARE
(VALOARE CONTRACT PROIECTARE:
16.950.944,23 FARA TVA)
BACAU - PASCANI LOT 1 77.283 0% 23%
ORDIN DE
INCEPERE
01.03.2019 -
ETAPA
PROIECTARE
2021ANUL 2021 - FINALIZARE
ETAPA PROIECTARE
1750.27 MIL. LEI
FARA TVA
ACTIVITATE DE PROIECTARE IN DERULARE/ FINALIZARE ANALIZA MULTICRITERIALA, AVIZARE IN CTE/ STABILIRE PROFIL DE AUTOSTRADA
AU FOST INAINTATE OBSERVATII PENTRU STUDIU DE FEZABILITATE,
A FOST EFECTUATA EVALUAREA DE IMPACT ASUPRA SIGURANTEI RUTIERE.
IN DATA DE 19.07.2021 A FOST INAINTAT STUDIUL DE FEZABILITATE REVIZUIT, AU FOST EMISE OBSERVATII
AU FOST EMISE OBSERVATII ASUPRA STUDIULUI DE FEZABLITATE REV 3 IN DATA DE 09.08.2021. OBSERVATIILE CU PRIVIRE LA STUDIUL GEOTEHNIC AU FOST EMISE IN DATA DE 13.08.2021.
IN DATA DE 02.08.2021 A FOST INAINTAT PROIECTUL TEHNIC, IN FORMAT ELECTRONIC.
ASUPRA PROIECTULUI TEHNIC BENEFICIARUL A EMIS OBSERVATII IN DATA DE 23.08.2021.
9AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA
AUTOSTRADA BUZAU -
FOCSANI0+000 82+440
CONSITRANS - CONTRACT
ELABORARE SF SI PT
(VALOARE CONTRACT PROIECTARE:
13.933.291,10 LEI, FARA TVA)
BUZAU - FOCSANI 82.44 23.75%
ORDIN DE
INCEPERE
12.11.2018 -
ETAPA
PROIECTARE
2021 FINALIZARE 20211270.62 MIL. LEI
FARA TVA
CONTRACT PROIECTARE IN DERULARE - ETAPA ELABORARE STUDIU DE FEZABILITATE ANALIZA MULTICRITERIALA ETAPA 1 SI ETAPA 2.
A FOST AVIZAT IN CADRUL CTE CNAIR STUDIUL SI RAPORTUL ALTERNATIVELOR DE TRASEU (AMC 1 SI AMC 2)
INVESTIGATIILE GEOTEHNICE AU FOST REALIZATE IN PROPORTIE DE 100%. IN CURS DE ELABORARE TESTELE DE LABORATOR.
A FOST AVIZAT IN CADRUL COMISIEI TEHNICE PENTRU SIGURANTA CIRCULATIEI NODURILE RUTIERE SI DOTARILE AUTOSTRAZII.
A FOST INAINTAT IN DATA DE 21.09.2021 STUDIUL DE FEZABILITATE FINAL.
PRESTATORUL A PREDAT IN DATA DE 17.09.2021 STUDIUL GEOTEHNIC FINAL - AU FOST EMISE OBSERVATII
A FOST INAINTAT PROIECTULUI TEHNIC - AU FOST EMISE OBSERVATII
10AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA
AUTOSTRADA FOCSANI -
BACAU0+000 96+052
CONSITRANS - CONTRACT
ELABORARE SF SI PT
(VALOARE CONTRACT PROIECTARE:
20.123.408,52 LEI, FARA TVA)
FOCSANI - BACAU 96.052 0% 0.37%
ORDIN DE
INCEPERE
10.01.2019 -
ETAPA
PROIECTARE
2021ANUL 2021 - FINALIZARE
ETAPA PROIECTARE
1927.35 MIL. LEI
FARA TVA
ETAPA DE PROIECTARE (ELABORARE STUDIU DE FEZABILITATE) IN DERULARE.
S-A AVIZAT IN CADRUL CTE CNAIR SA - STUDIUL SI RAPORTUL ALTERNATIVELOR DE TRASEU (ANALIZA MULTICRITERIALA ETAPA 1 SI ANALIZA MULTICRITERIALA ETAPA 2).
AU INCEPUT INVESTIGATIILE ARHEOLOGICE.
STUDIILE GEOTEHNICE IN CURS DE REALIZARE-PROCENTUL DE REALIZARE ESTE DE 61%.
STUDIUL ARHEOLOGIC ETAPA NR. 2 A FOST TRANSMIS LA MINISTERELE DE CULTURA DE PE RAZA JUDETELOR VRANCEA SI BACAU IN VEDEREA OBTINERII AVIZELOR.
IN DATA DE 09.03.2021 AU FOST ANALIZATE IN CADRUL COMISIEI TEHNICE PENTRU SIGURANTA CIRCULATIEI NODURILE RUTIERE SI DOTARILE AUTOSTRAZII
IN DATA DE 05.05.2021 A FOST INAINTAT STUDIUL DE FEZABILITATE SUB FORMA DRAFT- AU FOST EMISE OBSERVATII
11AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA
AUTOSTRADA SIBIU -
PITESTI44+800 68+000
SECTIUNEA 6, CONEXIUNE DN 73C
CU AUTOSTRADA SIBIU - PITESTI
(NOD TIGVENI) SI MODERNIZARE DN
73C (KM 44+800 – KM 68+000)
SECTIUNEA 6 23.2 0% 0% 2022 2023ANUL 2023 - FINALIZARE
PROIECTARE
VALORI
ESTIMATE: 2.099
MIL. LEI FARA TVA
- TIGVENI -
CURTEA DE
ARGES
3.926 MIL. LEI
FARA TVA -
AUTOSTRADA
SIBIU - PITESTI
DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL DE MAI JOS
12AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA
AUTOSTRADA PLOIESTI -
BRASOVSC CONSITRANS S.R.L.
PLOIESTI - BRASOV (FARA SECTOR
RASNOV - CRISTIAN)97.3 0% 0%
2021 -
DEMARARE
SERVICII DE
PROIECTARE FAZA
S.F. + P.A.C. +
P.T.E.
2023 -
FINALIZARE
SERVICII DE
PROIECTARE FAZA
S.F. + P.A.C. +
P.T.E.
1000.8 MIL. LEI
FARA TVA
CONTRACT IN DERULARE.
S-AU EFECTUAT VIZITE IN TEREN CU REPREZENTANTI DIN PARTEA BENEFICIARULUI SI DIN PARTEA PRESTATORULUI PENTRU IDENTIFICAREA EVENTUALELOR CONSTRANGERI.
A FOST APROBAT DE CATRE BENEFICIAR RAPORTUL DE PROGRES NR. 5.
13AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA POD PESTE PRUT LA
UNGHENI
S.C. EXPERT PROIECT 2002 S.R.L. POD PESTE PRUT LA UNGHENI 1 80% 45%
2016 -
DEMARARE
PROIECTARE POD
UNGHENI; 2020 -
DEMARARE
PROIECTARE
SECTIUNEA IASI -
UNGHENI
2021 -
FINALIZARE
PROIECTARE FAZA
SF, DEMARARE
SERVICII DE
PROIECTARE SI
EXECUTIE POD
UNGHENI
ANUL 2024 - DESCHIDERE
TRAFIC POD PESTE PRUT LA
UNGHENI
0.8 MIL. LEI FARA
TVA
2.POD UNGHENI - STUDIU DE FEZABILITATE FINALIZAT CU EXCEPTIA ACORDULUI DE MEDIU ;
PROCEDURA DE MEDIU IN DERULARE
OBTINERE DEROGARE DE LA ART ART. 23 ALIN. (2) SI ALE ART. 27 ALIN. (1) DIN ORDONANTA DE URGENTA A GUVERNULUI
NR. 57/2007 PRIVIND REGIMUL ARIILOR NATURALE PROTEJATE, PRIN OUG NR. 105/2020, SEMNARE MEMORANDUM IN VEDERE PROMOVARII ACORDULUI BILATERAL ROMANIA-MOLDOVA NECESAR OBTINERII ACORDULUI DE MEDIU.
ESTE IN PREGATIRE LA MTIC ACORDUL BILATEARAL ROMANIA-MOLDOVA.
IN DATA DE 24.08.2020 A FOST EMISA DECIZIA ETAPEI DE EVALUARE INITIALA DE CATRE A.N.P.M. IASI.
IN DATA DE 24.08.2020 A FOST EMISA DECIZIA ETAPEI DE INCADRARE INITIALA NR. 133/2020 ANMP .
PENTRU CONTINUAREA PROCEDURII DE OBTINERE A ACORDULUI DE MEDIU S-A TRANSMIS MEMORIUL DE PREZENTARE CATRE APM IASI.
IN DATA DE 22.02.2021 A FOST EMISA DECIZIA ETAPEI DE INCADRARE NR. 15 DE CATRE APM IASI.
14AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA A4 16+700 16+700 SEARCH CORPORATION SRL
ELABORARE STUDIU DE
FEZABILITATE SI PROIECT TEHNIC DE
EXECUTIE PENTRU NOD RUTIER
CUMPANA A4 (KM 16+700)-DN 39E
0% 0% 26.10.2020 NOIEMBRIE 2021
NOIEMBRIE 2021 -
FINALIZAR E PROIECT
TEHNIC
674,39 MIL LEI
FARA TVA
CONTRACT SEMNAT IN DATA DE 23.09.2020.
ORDINUL DE INCEPERE A ACTIVITATII DE PROIECTARE A FOST EMIS IN DATA DE 26.10.2020
DURATA CONTRACTULUI ESTE DE 8 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI, DIN CARE:
-3 LUNI PENTRU ELABORAREA STUDIULUI DE FEZABILITATE,
- 2 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA LUCRARILOR DE CONSTRUIRE,
- 1 LUNI PENTRU ELABORAREA PROIECTULUI TEHNIC DE EXECUTIE SI
- 1 LUNI PENTRU ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFICIARULUI.
A AVUT LOC SEDINTA DE INCEPUT IN DATA DE 26.10.2020.
S-A EMIS ORDINUL ADMINISTRATIV NR. 1 - APROBARE EXPERTI NON CHEIE.
CTR SUSPENDAT, ACTIVITATEA FIIND RELUATA INCEPAND CU DATA DE 16.04.2021
A FOST AVIZATA IN CADRUL CTE CNAIR IN DATA DE 20.05.2021 ANALIZA MULTICRITERIALA ETAPA 1.
AU FOST FINALIZATE STUDIILE GEOTEHNICE, TERMENUL ESTIMAT DE PREDARE A STUDIULUI DE FEZABILITATE ESTE 31 AUGUST 2021 SI ELABORARE PROIECT TEHNIC - NOIEMBRIE 2021
15AUTOSTRAZI IN PREGATIRE FAZA
PROIECTARE (SF, PT)AUTOSTRADA A1 , A2 si A3 SEARCH CORPORATION SRL
ELABORARE STUDIU DE
FEZABILITATE SI PROIECT TEHNIC DE
EXECUTIE PENTRU 3 NODURI
RUTIERE PE A1, A2, A3 IN ZONA DE
SUD EST A ROMANIEI
NOD RUTIER AUTOSTRADA A1
KM 73+100 CU DJ702F LA
IONESTI;
NOD RUTIER AUTOSTRADA A2
KM 90+100 CU DJ 306 SI
DN3A LA DRAGOS VODA;
NOD RUTIER AUTOSTRADA A3
KM 36+700 CU DJ 101C LA
GRUIU (SECTOR BUCUREȘTI –
PLOIESTI);
0% 0% 24.06.2021 24.04.2020
CONTRACT SEMNAT IN DATA DE 20.05.2021
ORDINUL DE INCEPERE A ACTIVITATII DE PROIECTARE A FOST EMIS IN DATA DE 24.06.2021
DURATA CONTRACTULUI ESTE DE 10 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI, DIN CARE:
- 4 LUNI PENTRU ELABORAREA STUDIULUI DE FEZABILITATE,
- 3 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA LUCRARILOR DE CONSTRUIRE,
- 2 LUNI PENTRU ELABORAREA PROIECTULUI TEHNIC DE EXECUTIE SI
- 1 LUNA PENTRU ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFICIARULUI.
IN DATA DE 30.08.2021 PRESTATORUL A TRANSMIS AMC. IN DATA DE 16.09.2021 AU FOST TRANSMISE PRESTATORULUI OBSERVATII LA AMC.
NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1DRUMURI DE MARE VITEZA IN FAZA
PROIECTARE (SF, PT)DRUM DE MARE VITEZA
DRUM DE MARE VITEZA
BAIA MARE - DEJ -
BISTRITA - VATRA
DORNEI - SUCEAVA
0+000 145+000 BAIA MARE - DEJ - BISTRITA LOT 1 145 ESTIMAT 2022 2024 ANUL 20246681.19 MIL. LEI
FARA TVA
PROCEDURA DE ACHIZITIE PENTRU LOTUL 1 A FOST ANULATA
DETALII STADIU PROCEDURA DE ATRIBUIRE IN LINK-UL DE MAI JOS.
2DRUMURI DE MARE VITEZA IN FAZA
PROIECTARE (SF, PT)DRUM DE MARE VITEZA
DRUM DE MARE VITEZA
BAIA MARE - DEJ -
BISTRITA - VATRA
DORNEI - SUCEAVA
145+000 228+000 SC EXPLAN SRL BISTRITA - VATRA DORNEI LOT 2 83 2021 2023 ANUL 2023
15.8 MIL LEI FARA
TVA (VALOARE
CONTRACT
ELABORARE S.F.)
IN DATA DE 10.03.2021, CNAIR A SEMNAT CONTRACTUL PENTRU ELABORARE STUDIU DE FEZABILITATE DRUM DE MARE VITEZA VITEZA BAIA MARE - SUCEAVA, LOT 2 BISTRITA - VATRA DORNEI CU OFERTANTUL SC EXPLAN SRL., CU O VALOARE DE 15.793.026,12 LEI
FARA TVA.
IN DATA DE 14.09.2021 A FOST INAINTATA DOCUMENTATIA ANALIZA MULTICRITERIALA 1. IN PREZENT ESTE IN ANALIZA (TERMEN 04.10.2021)
3DRUMURI DE MARE VITEZA IN FAZA
PROIECTARE (SF, PT)DRUM DE MARE VITEZA
DRUM DE MARE VITEZA
BAIA MARE - DEJ -
BISTRITA - VATRA
DORNEI - SUCEAVA
228+000 335+000
ASOCIEREA BEST CONSULTING &
DESIGN S.R.L. – INGENIERIA
ESPECIALIZADA OBRA CIVIL E
INDUSTRIAL S.A.
VATRA DORNEI-SUCEAVA LOT 3 107 2021 2023 ANUL 2023
14.48 MIL LEI
FARA TVA
(VALOARE
CONTRACT
ELABORARE S.F.)
IN DATA DE 10.03.2021, CNAIR A SEMNAT CONTRACTUL PENTRU ELABORARE STUDIU DE FEZABILITATE DRUM DE MARE VITEZA BAIA MARE - SUCEAVA, LOT 3 VATRA DORNEI – SUCEAVA CU ASOCIEREA BEST CONSULTING & DESIGN SRL – INGENIERIA ESPECIALIZADA
OBRA CIVIL E INDUSTRIAL, CU PRETUL DE 14.475.000,00 LEI FARA TVA.
NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRESDRUM EXPRES BRAILA -
GALATI0+000 11+088
ASOCIEREA SC SA & PE CONSTRUCT
SRL (LIDER DE ASOCIERE) -
SPEDITION UMB - TEHNOSTRADE
S.R.L.
BRAILA - GALATI LOT 1 11.08 0% 0%
ORDIN DE
INCEPERE
01.07.2021 -
ETAPA
PROIECTARE
MAI 2024 ANUL 2024371.42 MIL. LEI
FARA TVA
IN DATA DE 15.04.2021, CNAIR A SEMNAT CONTRACTUL PENTRU ""PROIECTAREA SI EXECUTIA DRUMULUI EXPRES BRAILA - GALATI” CU ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.
VALOAREA CONTRACTULUI ESTE DE 371.416.131,09 LEI FARA TVA.
SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE.
DURATA CONTRACTULUI ESTE DE 34 LUNI, DIN CARE 10 LUNI PERIOADA DE PROIECTARE SI 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR. PERIOADA DE GARANTIE ESTE DE 120 DE LUNI.
2 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES
DRUM EXPRES CRAIOVA
- PITESTI 0+000 17+700 TIRRENA SCAVI S.P.A. (ITALIA)TRONSON 1 - CRAIOVA - ROBANESTI
(KM 0+000 - KM 17+700)
SECTOR 1: 0+000 - 1+800
SECTOR 2: 1+800 - 10+000
SECTOR 3: 10+000 - 17+700
17.7 38.06% 28.20%
27.12.2018 -
PROIECTARE;
16.09.2019 -
EXECUTIE SECTOR
3 ;
13.07.2020 -
EXECUTIE SECTOR
1;
01.03.2021 -
EXECUTIE SECTOR
2 - km 5+245 - km
10+000
TRIM IV 2022 ANUL 2022358.18 MIL. LEI
FARA TVA
SECTOR 1: 0+000 - 1+850
IN DATA DE 03.07.2020 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE.
INCEPAND CU DATA DE 13.07.2020 A FOST EMIS ORDINUL DE INCEPERE EXECUTIE LUCRARI
SECTOR 2: 1+850 - 10+000
IN DATA DE 22.02.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE.
INCEPAND CU DATA DE 01.03.2021 A FOST EMIS ORDINUL DE INCEPERE EXECUTIE LUCRARI
SECTOR 3: 10+000 - 17+700 – IN EXECUTIE
IN DATA DE 22.05.2019 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE PENTRU SUPRAFETELE AFERENTE DOMENIUL PUBLIC. IN DATA DE 05.07.2019 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE.
INCEPAND CU DATA DE 16.09.2019 A FOST EMIS ORDINUL DE INCEPERE EXECUTIE LUCRARI
3 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES
DRUM EXPRES CRAIOVA
- PITESTI 17+700 36+200
ASOCIEREA SA & PE CONSTRUCT SRL -
SC SPEDITION UMB SRL - SC
TEHNOSTRADE SRL - SC CONSITRANS
SRL
TRONSON 2 - ROBANESTI - PIATRA
OLT (KM 17+700 - KM 57+550)
Lot 1 km 17+700 - km 36+200
LOT 1: KM 17+700 - KM
36+20018.5 88.86% 63.25
21.12.2018 -
ACTIVITATEA DE
PROIECTARE,
24.09.2019 -
EXECUTIE
(ETAPELE I, II SI
III), 21.11.2019 -
EXECUTIE (ETAPA
IV)
TRIM IV 2021 ANUL 2022661.45 MIL. LEI
FARA TVA
DRUMURI EXPRES PROIECTE IN EXECUTIE - OCTOMBRIE 2021
DRUMURI DE MARE VITEZĂ
DRUMURI EXPRES
DRUMURI DE MARE VITEZA IN FAZA PROIECTARE (SF, PT) - OCTOMBRIE 2021
4 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES
DRUM EXPRES CRAIOVA
- PITESTI 36+000 57+500
ASOCIEREA SA & PE CONSTRUCT SRL -
SC SPEDITION UMB SRL - SC
TEHNOSTRADE SRL - SC CONSITRANS
SRL
TRONSON 2 - PIATRA OLT - VALEA
MARE (KM 17+700 - 57+550)
Lot 2 - km 36+200 - km 57+550
LOT 2: KM 36+200 - KM
57+55021.35 86.29% 63.33%
21.12.2018 -
ACTIVITATEA DE
PROIECTARE,
24.09.2019 -
EXECUTIE
(ETAPELE I, II SI
III), 21.11.2019 -
EXECUTIE (ETAPA
IV)
TRIM IV 2021 ANUL 2022792.18 MIL. LEI
FARA TVA
5 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRESDRUM EXPRES CRAIOVA
- PITESTI89+300 121+115
ASOCIEREA SA & PE CONSTRUCT SRL -
SC SPEDITION UMB SRL - SC
TEHNOSTRADE SRL
TRONSON 4
COLONESTI - OARJA - PITESTITRONSON 4 31.82 0% 0% 2021 2024 ANUL 2024
617.08 MIL. LEI
FARA TVA
ANTREPRENORUL A CONSTITUIT GARANTIA DE BUNA EXECUTIE, IN CONFORMITATE CU PREVEDRILE CONTRACTUALE, ACEASTA FIIND APROBATA DE CATRE C.N.A.I.R. S.A. IN DATA DE 02.09.2021.
DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE:
• 12 LUNI PERIOADA DE PROIECTARE,
• 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,
• 120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.
INCEPAND CU DATA DE 15.11.2021 VA EMIS ORDIN DE INCEPERE.
6 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRESDRUM EXPRES CRAIOVA
- PITESTI57+550 89+300
ASOCIEREA SA & PE CONSTRUCT SRL -
SC SPEDITION UMB SRL - SC
TEHNOSTRADE SRL
TRONSON 3, VALEA MARE -
COLONESTITRONSON 3 31.75 0% 0% 18.01.2021 2024 ANUL 2024
670.71 MIL. LEI
FARA TVA
ANTREPRENORUL A CONSTITUIT GARANTIA DE BUNA EXECUTIE, IN CONFORMITATE CU PREVEDRILE CONTRACTUALE, ACEASTA FIIND APROBATA DE CATRE C.N.A.I.R. S.A. IN DATA DE 10.11.2020.
DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE:
• 12 LUNI PERIOADA DE PROIECTARE,
• 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,
• 120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.
INCEPAND CU DATA DE 18.01.2021 A FOST EMIS ORDIN DE INCEPERE.
PAC AVIZAT IN CADRUL CTE IN LUNA MARTIE 2021
7 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES DRUM DE LEGATURA A3 0+000 18+960 SC STRABAG SRL
LEGATURA CENTURA ORADEA
(GIRATIA SANTANDREI) -
AUTOSTRADA A3 (BIHARIA)
18.96 0% 0% 27.09.2021 2024 ANUL 2024545.9 MIL. LEI
FARA TVA
IN DATA DE 21.07.2021 A FOST SEMNAT CONTRACTUL DE PROIECTARE SI EXECUTIE CU STRABAG S.R.L.
DURATA CONTRACTULUI ESTE DE 30 DE LUNI, DIN CARE:
6 DE LUNI PERIOADA DE PROIECTARE,
24 DE LUNI PERIOADA DEEXECUTIE A LUCRARILOR.
NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1DRUMURI EXPRES IN PREGATIRE FAZA
PROIECTARE (SF, PT)DRUM EXPRES
DRUM EXPRES BACAU -
PIATRA NEAMT0+000 61+000
SEARCH CORPORATION & EGIS
ROMANIA
(VALOARE CONTRACT PROIECTARE:
8,923,930.03 LEI, FARA TVA)
BACAU - PIATRA NEAMT LOT 1 61 0% 0%
MARTIE 2020 -
ETAPA
PROIECTARE
SEPTEMBRIE 2021
- TERMEN
FINALIZARE
PROIECTARE;
PERIOADA
CONTRACTUALA
DE PRESTARE A
SERVICIILOR - 18
LUNI
APRILIE 2022 - TERMEN
FINALIZARE PROIECTARE
(CONFORM AA NR. 2 DIN
08.09.2021)
1123.86 MIL. LEI
FARA TVA
CONTRACT ELABORARE SF IN DERULARE.
IN DATA DE 14.07.2021 A FOAT AVIZATA AMC 1 IN CADRUL CTE CNAIR S.A.
DOCUMENTATIA AMC 2 ESTE IN ANALIZA LA JASPERS.
2DRUMURI EXPRES IN PREGATIRE FAZA
PROIECTARE (SF, PT)DRUM EXPRES
DRUM EXPRES BRAILA -
TULCEA (JIJILA -
CATALOI)
0+000 59+700
INGINERIA ESPECIALIZADA OBRA
CIVIL E INDUSTRIAL SA - CONTRACT
PROIECTARE (ELABORARE STUDIU
DE FEZABILITATE SI PROIECT TEHNIC)
SEMNAT IN LUNA MAI 2020.
(VALOARE CONTRACT PROIECTARE:
14.159.206,13 LEI, FARA TVA)
BRAILA - TULCEA LOT 1 59.7 0% 0%
IUNIE 2020 -
ETAPA
PROIECTARE
IUNIE 2022
FEBRUARIE 2023- TERMEN
FINALIZARE PROIECTARE
(CONFORM AA NR. 3)
1674.75 MIL. LEI
FARA TVA
CONTRACT ELBORARE S.F. IN DERULARE.
DOCUMENTATIA AMC ETAPA 1 REVIZIA 2 A FOST TRANSMISA CONSULTANTILOR JASPERS PENTRU OBSERVATII.
DOCUMENTATIA AMC ETAPA 1 REVIUITA A FOST RETRANSMISA CONSULTANTILOR JASPERS PENTRU OBSERVATII IN DATA DE 10.05.2021.
IN DATA DE 09.06.2021 FOST ORGANIZATA O NOUA SEDINTA CU EXPERTII JASPERS.
IN PREZENT PRESTATORUL IMPLEMENTEAZA OBSERVATIILE EMISE DE CATRE EXPERTII JASPERS IN CADRUL DOCUMENTATIEI AMC ETAPA 1.
PRESTATORUL ANALIZEAZA NOILE PROPUNERII DE AMENAJARE A DRUMULUI DE LEGATURA LA PUNCTUL DE TRECERE A FRONTIERE ISACCEA IN CONFORMITATE CU SOLICITARILE PRIMARIEI ISACCEA.
3DRUMURI EXPRES IN PREGATIRE FAZA
PROIECTARE (SF, PT)DRUM EXPRES
DRUM EXPRES BUZAU -
BRAILA0+000 98+000
INGINERIA ESPECIALIZADA OBRA
CIVIL E INDUSTRIAL SA - CONTRACT
ELABORARE SF SI PT IN DERULARE
(VALOARE CONTRACT PROIECTARE:
16.591.031,97 LEI, FARA TVA)
BUZAU - BRAILA LOT 1 98 0% 0%
03.04.2020 -
ETAPA
PROIECTARE
APRILIE 2022
OCTOMBRIE 2022- TERMEN
FINALIZARE PROIECTARE
(CONFORM AA NR. 2)
1805.55 MIL. LEI
FARA TVA
CONTRACT ELABORARE SF IN DERULARE.
AMC - ETAPA 1 SE AFLA IN ANALIZA CONSULTANTILOR JASPERS.
DOCUMENTATIA AMC 1 SE AFLA IN CURS DE REVIZUIRE CONFORM OBSERVATIILOR JASPERS.
DOCUMENTATIA AMC 1 REVIZUIT A FOST TRANSMISA CATRE CNAIR, CARE A EMIS NOI OBSERVATII CATRE PRESTATOR.
IN DATA DE 26.05.2021 A FOST ORGANIZATA O NOUA SEDINTA CU CONSULTANTII JASPERS.IN PREZENT PRESTATORUL IMPLEMENTEAZA OBSERVATIILE DE CATRE EXPERTII JASPERS IN CADRUL DOCUMENTATIEI AMC ETAPA 1.
4DRUMURI EXPRES IN PREGATIRE FAZA
PROIECTARE (SF, PT)DRUM EXPRES
DRUM EXPRES CRAIOVA
- TARGU JIU
ASOCIEREA EGIS ROMANIA S.A. –
SEARCH CORPORATION S.R.LCRAIOVA - TARGU JIU 108 0% 0%
ORDIN DE
INCEPERE
16.04.2021 -
ETAPA
PROIECTARE
APRILIE 202320.25 MIL LEI
FARA TVA
IN DATA DE 17.03.2021 CNAIR A SEMNAT CU OFERTANTUL DECLARAT CASTIGATOR - ASOCIEREA EGIS ROMANIA S.A. – SEARCH CORPORATION S.R.L.
VALOAREA CONTRACTULUI ESTE DE 20.247.133,77 LEI FARA TVA, SURSA DE FINANTARE FIIND DIN FONDURI EUROPENE NERAMBURSABILE.
IN DATA DE 16.04.2021 A FOST SEDINTA DE INCEPUT (ORDINUL DE INCEPERE)
TERMENUL DE PREDARE AMC 1 (16.07.2021) A FOST DEPASIT DIN CAUZA UNOR OBIECTIVE SEVESO DEPISTATE IN ZONA DE INTERES A DRUMULUI EXPRES.
IN DATA DE 03.09.2021 PRESTATORUL A TRANSMIS AMC 1. IN DATA DE 21.09.2021 AU FOST TRANSMISE PRESTATORULUI OBSERVATII LA AMC 1.
5DRUMURI EXPRES IN PREGATIRE FAZA
PROIECTARE (SF, PT)DRUM EXPRES
DRUM EXPRES FOCSANI -
BRAILA0+000 76+000
INGENIERIA ESPECIALIZADA OBRA
CIVIL E INDUSTRIAL S.A.
SEMNAT IN DATA DE 19.06.2020
(VALOARE CONTRACT PROIECTARE:
15.001.446,99 LEI, FARA TVA)
FOCSANI - BRAILA 76 0% 15%
ORDIN DE
INCEPERE
27.07.2020 -
ETAPA
PROIECTARE
IULIE 2022ANUL 2022 - FINALIZARE
ETAPA PROIECTARE
1400.22 MIL. LEI
FARA TVA
CONTRACT SEMNAT IN DATA DE 19.06.2020.
ORDINUL DE INCEPERE 27.07.2020
DURATA CONTRACTULUI ESTE DE 24 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI
ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU, ETAPA 1 (AMC1) FOST AVIZATA IN CTE CNAIR SA.
A FOST APROBATA TEMA PENTRU STUDII ARHEOLOGICE ETAPA1 SI STUDIUL ARHEOLOGIC ETAPA 1.
IN CURS DE ELABORARE ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU ETAPA 2 (AMC 2).
DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) - OCTOMBRIE 2021
6DRUMURI EXPRES IN PREGATIRE FAZA
PROIECTARE (SF, PT)DRUM EXPRES
DRUM EXPRES OVIDIU
(CONSTANTA) - TULCEA0+000 112+000
SEARCH CORPORATION & EGIS
ROMANIA- CONTRACT PROIECTARE
ELABORARE SF SI PROIECT TEHNIC
SEMNAT IN DATA DE 13.07. 2020
(VALOARE CONTRACT PROIECTARE:
17.845.626,28 LEI, FARA TVA)
CONSTANTA - TULCEA 112.5 0% 0%
ORDIN DE
INCEPERE
10.08.2020 -
ETAPA
PROIECTARE
Aug-22AUGUST 2022 - TERMEN
FINALIZARE PROIECTARE
2664.38 MIL. LEI
FARA TVA
CONTRACT IN DERULARE.
AMC ETAPA 1 ESTE IN CURS DE REVIZURIRE CONFORM OBSERVATIILOR JASPERS. PRESTATORUL ANALIZEAZA REALIZAREA UNOR DRUMURI DE LEGATURA CU MUN. TULCEA.
PRESTATORUL IMPREUNA CU CESTRIN ANALIZEAZA REALIZAREA DRUMURILOR EXPRES/DRUMURI DE LEGATURA LA DX8 IN CONFORMITATE CU DATELE/INFORMATIILE ACTUALIZATE TRANSMISE DE CATRE PRIMARIA TULCEA.
IN ANALIZA SOLICITAREA PRESTATORULUI DE PRELUNGIRE PERIOADA CONTRACTUALA.
7DRUMURI EXPRES IN PREGATIRE FAZA
PROIECTARE (SF, PT)DRUM EXPRES
DRUM EXPRES PASCANI -
SUCEAVA0+000 61+000
SEARCH CORPORATION SRL - EGIS
ROMANIA S.A - EGIS INTERNATIONAL
SAS.
CONTRACT PROIECTARE ELABORARE
SF SI PROIECT TEHNIC SEMNAT IN
DATA DE 07.09.2020 (VALOARE
CONTRACT DE PROIECTARE:
11,721,430.96 LEI FARA TVA)
PASCANI - SUCEAVA 61.86 0% 0% OCTOMBRIE 2020
OCTOMBRIE 2022
- FINALIZARE
ETAPA DE
PROIECTARE
1304.96 MIL. LEI
FARA TVA
CONTRACT IN DERULARE.
IN DATA DE 14.04.2021 A FOST AVIZATA IN CADRUL CTE-CNAIR SA DOCUMENTATIA AMC ETAPA 1. IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA 2. IN DATA DE 16.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 2. DOCUMENTATIA AMC ETAPA 2
ESTE IN ANALIZA LA BENEFICIAR.
DOCUMENTATIA AMC 2 A FOST AVIZATA IN CTE - CNAIR S.A. IN DATA DE 23.07.2021.
AU FOST OBTINUTE CERTIFICATELE DE URBANISM (SV, IS si BT)
IN PREZENT SE REALIZEAZA STUDII GEOTEHNICE.
8DRUMURI EXPRES IN PREGATIRE FAZA
PROIECTARE (SF, PT)DRUM EXPRES
DRUM EXPRES PLOIESTI -
GAESTI0+000 76+000
SEARCH CORPORATION & – MEGA
MUHENDISLIK MUSAVIRLIK A.S.
(MEGA ENGINEERING CONSULTING
INC.) - CONTRACT PROIECTARE
ELABORARE STUDIU DE
FEZABILITATE SI PROIECT TEHNIC DE
EXECUTIE SEMNAT IN DATA DE
25.08.2020 (VAL CTR PROIECTARE:
15.86 MIL LEI FARA TVA)
PLOIESTI - GAESTI 76 0% 0%
AUGUST 2020 –
DEMARARE
ETAPA DE
PROIECTARE
OCTOMBRIE 2022
- FINALIZARE
ETAPA DE
PROIECTARE
OCTOMBRIE 2022 -
TERMEN FINALIZARE
PROIECTARE
1671.37 MIL. LEI
FARA TVA
CONTRACT IN DERULARE.
PRESTATORUL A TRANSMIS DOCUMENTATIA ANALIZA MULTICRITERIALA DE TRASEU.
AU FOST EMISE OBSERVATII DIN PARTEA BENEFICIARULUI SI PRESTATORUL A TRANSMIS DOCUMENTATIA REVIZUITA.
IN DATA DE 09.04.2021 ANALIZA MULTICRITERIALA ETAPA 1 A FOST AVIZATA IN CADRUL C.T.E. CNAIR.
A FOST SUSPENDAT CONTRACTUL PENTRU O PERIOADA DE 3 LUNI INCEPAND CU DATA DE 18.05.2021.
IN DATA DE 18.08.2021 A FOST RELUATA ACTIVITATEA DE PROIECTARE.
9DRUMURI EXPRES IN PREGATIRE FAZA
PROIECTARE (SF, PT)DRUM EXPRES
DRUM EXPRES SUCEAVA
- SIRET0+000 40+000
SEARCH CORPORATION SRL - EGIS
ROMANIA S.A - EGIS INTERNATIONAL
SAS.
CONTRACT PROIECTARE ELABORARE
SF SI PROIECT TEHNIC SEMNAT IN
DATA DE 07.09.2020 (VALOARE
CONTRACT DE PROIECTARE:
10,092,839.13 LEI FARA TVA)
SUCEAVA- SIRET 56.17 0% 0% OCTOMBRIE 2020 OCTOMBRIE 2022882.9 MIL. LEI
FARA TVA
CONTRACT IN DERULARE.
DOCUMENTATIA ANALIZA MULTICRITERIALA DE TRASEU ESTE REVIZUITA CONFORM OBSERVATIILOR BENEFICIARULUI.
IN DATA DE 14.04.2021 A FOST AVIZATA IN CADRUL CTE-CNAIR SA DOCUMENTATIA AMC ETAPA 1. IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA 2. IN DATA DE 16.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 2. DOCUMENTATIA AMC ETAPA 2
ESTE IN ANALIZA LA BENEFICIAR.
DOCUMENTATIA AMC 2 A FOST AVIZATA IN CTE - CNAIR S.A. IN DATA DE 23.07.2021.
A FOST OBTINUT CERTIFICATUL DE URBANISM (SV)
IN PREZENT SE REALIZEAZA STUDII GEOTEHNICE.
10DRUMURI EXPRES IN PREGATIRE FAZA
PROIECTARE (SF, PT)DRUM EXPRES
DRUM EXPRES TISITA -
ALBITA0+000 160+000
SEARCH CORPORATION & EGIS
ROMANIA- CONTRACT PROIECTARE
ELABORARE STUDIU DE
FEZABILITATE SEMNAT IN DATA DE
09.07. 2020
(VALOARE CONTRACT PROIECTARE:
11.057.073,07 LEI FARA TVA)
TISITA - ALBITA 160 0% 0%
AUGUST 2020
DEMARARE
ETAPA DE
PROIECTARE
OCTOMBRIE 2022
- FINALIZARE
ETAPA DE
PROIECTARE
OCTOMBRIE 2022 -
TERMEN FINALIZARE ETAPA
DE PROIECTARE
3563.3 MIL. LEI
FARA TVA
CONTRACTUL IN DERULARE
A FOST TRANSMIS AMC ETAPA 1 SE AFLA IN CURS DE REVIZUIRE CONFORM OBSEVATIILOR BENEFICIARULUI.
PRESTATORUL ANALIZEAZA ETAPIZAREA SI FAZAREA OBIECTIVULUI DE INVESTITII CONFORM CERINTELOR CNAIR SI MTI. IN DATA DE 09.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 1. DOCUMENTATIA AMC ETAPA 1 ESTE IN ANALIZA LA BENEFICIAR.
DOCUMENTATIA AMC 1 REV 3 ETAPIZARE/FAZARE ESTE IN CURS DE REVIZUIRE IN CONFORMITATE CU OBSERVATIILE BENEFICIARULUI / MTI.
11DRUMURI EXPRES IN PREGATIRE FAZA
PROIECTARE (SF, PT)DRUM EXPRES
DRUM EXPRES OAR -
SATU MARE0+000 10+900
SEARCH CORPORATION SRL
SEMNAT IN DATA DE 10.07. 2020
(VALOARE CONTRACT PROIECTARE:
3.646.308,36 LEI FARA TVA)
SATU MARE - OAR (GRANITA
RO/HU)10.9 0% 3%
AUGUST 2020 -
DEMARARE
SERVICII DE
PROIECTARE FAZA
S.F. + P.A.C. +
P.T.E.
2022 -
FINALIZARE
SERVICII DE
PROIECTARE FAZA
S.F. + P.A.C. +
P.T.E.
ANUL 2022 - TERMEN
FINALIZARE FAZA DE
PROIECTARE
311.79 MIL. LEI
FARA TVA
IN DATA DE 10.07.2020 A FOST SEMNAT CONTRACTUL PROIECTARE SF+PAC/DTAC+PT
DURATA DE REALIZARE A CONTRACTULUI DE SERVICII ESTE DE 18 LUNI
IN DATA DE 10.08.2020 S-A DAT ORDINUL DE INCEPERE.
IN DATA DE 05.03.2021 A FOST AVIZATA IN CADRUL CTE CNAIR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU AMC1 + AMC2 (VARIANTA 1)
INVESTIGATIILE GEOITEHNICE SUNT REALIZATE IN PROCENT DE 70%.
IN DATA DE 17.05.2021 A FOST EMIS CERTIFICATUL DE URBANISM.
12DRUMURI EXPRES IN PREGATIRE FAZA
PROIECTARE (SF, PT)DRUM EXPRES A1 (PITESTI) - MIOVENI 0+000 10+000 SEARCH CORPORATION S.R.L. A1 (PITESTI) - MIOVENI 10 0% 0%
ORDIN DE
INCEPERE
09.12.2020 -
ETAPA DE
PROIECTARE
IULIE 2022 -
TERMEN
FINALIZARE
ETAPA DE
PROIECTARE
222.71 MIL. LEI
FARA TVA
CONTRACT IN DERULARE.
DOCUMENTATIA REVIZUITA AMC 1 A PRIMIT AVIZUL C.T.E. IN DATA DE 01.04.2021.
DOCUMENTATIA AMC ETAPA 2 A FOST AVIZATA IN CADRUL CTE-CNAIR S.A. IN DATA DE 24.06.2021.
PRESTATORUL A INAINTAT DOCUMENTATIA IN VEDEREA OBTINERII CERTIFICATULUI DE URBANISM. NU A FOST OBTINUT CERIFICATUL DE URBANISM (OPBSERVATII PRIMARIA MARACINENI SI INSTITUTUL POMICOL MARACINENI)
NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL
DN794+150 107+745 ASTALDI S.P.A.
ARAD - ORADEA, KM 4+150 – KM
107+745 103.55 98% 98% 03.02.2009 REZILIAT IN FOLOSINTA
266.31 MIL. LEI
FARA TVA
PROBLEME:
CONTRACTUL A FOST REZILIAT DE CATRE BENEFICIAR IN DATA DE 02.10.2020 DATORITA INTARZIERILOR SI NEEXECUTARII LUCRARILOR RAMASE DE EXECUTAT DE CATRE ANTREPRENOR.
1. NEEXECUTAREA LUCRARILOR PENTRU PODUL DE LA KM 41+635
2. INTARZIEREA FINALIZARII EXECUTIEI LUCRARILOR
DRUMURI NATIONALE IN REABILITARE / MODERNIZARE - OCTOMBRIE 2021
DRUMURI NAȚIONALE
2DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN 52 1+350 44+600
ASOCIEREA S.C. ALEXCOR TRADING
S.R.L. - IMPRESA DI COSTRUZIONI
ING. E. MANTOVANI S.P.A. – S.C.
PEGASUS ENGINEERING S.R.L.
ALEXANDRIA - TURNU MAGURELE 43.25
DATA INCEPERII
ACTIVITATII DE
PROIECTARE:
09.06.2020
126.323 MII LEI
FARA TVA -
VALOARE
PROIECTARE ȘI
EXECUȚIE PENTRU
AMBELE
SECTOARE
ORDINUL DE INCEPERE A EXECUTIEI LUCRARILOR SE VA DA DUPA OBTINEREA AUTORIZATIEI DE CONSTRUCTIEI
3DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN 52 49+194 52+649
ASOCIEREA S.C. ALEXCOR TRADING
S.R.L. - IMPRESA DI COSTRUZIONI
ING. E. MANTOVANI S.P.A. – S.C.
PEGASUS ENGINEERING S.R.L.
TURNU MAGURELE - PORT TURNU
MAGURELE3.455
DATA INCEPERII
ACTIVITATII DE
PROIECTARE:
09.06.2020
126.323 MII LEI
FARA TVA -
VALOARE
PROIECTARE ȘI
EXECUȚIE PENTRU
AMBELE
SECTOARE
ORDINUL DE INCEPERE A EXECUTIEI LUCRARILOR SE VA DA DUPA OBTINEREA AUTORIZATIEI DE CONSTRUCTIEI
4DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN7 251+475 254+315
S.C GEIGER TRANSILVANIA SRL –
SERVICII DE PROIECTARE SC CONSIS
PROIECT SRL IN CALITATE DE
SUBCONTRACTANT
REALIZARE LARGIRE VALEA OLTULUI
LA 4 BENZI DE CIRCULATIE INTRE KM
251+475 – KM 254+315
2.84 40% 25% 01.11.2019 SEPTEMBRIE 202122.141 MIL. LEI
FARA TVAA FOST OBTINUTA AC NR. 50 DIN DATA DE 04 SEPTEMBRIE 2020. ORDINUL ADMINITRATIV DE RELUARE A FOST DAT CU 21.09.2020.
5DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN5 7+573 19+220
ASOCIEREA EUROCOGEN - FILIALA
ANINOASA SRL & ALEANDRI SPA &
BEOZZO COSTRUZIONI SRL & SMART
BUILDING PROJET SRL
MODERNIZARE DN 5,
BUCURESTI – ADUNATII COPACENI
KM 7+573 - KM 19+220
DRUM MODERNIZAT -
LUCRARI FINALIZATE IN ANUL
2020
11.647 99.50% 93.80% 23.04.2015ESTIMAT
SEPTEMBRIE 2021
76.13 MIL. LEI
FARA TVAEXECUTIE LUCRARI
6DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN73 13+800 128+250
ASOCIEREA AZVI SA - STRACO GRUP
SRL - TRACTEBEL
MODERNIZARE: PITESTI -
CAMPULUNG - BRASOV
KM 13+800 - KM 42+850; KM
54+050 - KM 128+250
103.25 49.82% 51.00% 19.05.2014 DECEMBRIE 2023275.86 MIL. LEI
FARA TVA
A FOST RECEPTIONAT UN SECTOR DE 28,85 KM.
PENTRU RESTUL SECTORULUI CONTRACTUL ESTE IN CURS DE REZILIERE SI SE VA LANSA O PROCEDURA DE LICITATIE AVAND CA OBIECT ACTUALIZAREA PROIECTULUI PENTRU REST DE EXECUTAT.
DOCUMENTATIA DE ATRIBUIRE PENTRU SERVICII DE ACTUALIAZARE PROIECT FINALIZATA, PROCEDURA DE LICITATIE SUSPENDATA CA URMARE A UNOR CONTESTATII .
7DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN76 55+425 69+350
ASOCIEREA SC SYLC CON TRANS
SRL/HIDROSTROY ADIONESTI - VARFURILE LOT 3 13.93 97.50% 97.50% 15.03.2019
RECEPTIE LA
TERMINAREA
LUCRARILOR -
ESTIMAT
DECEMBRIE 2021
55.95 MIL. LEI
FARA TVARECEPTIE LA TERMINAREA LUCRARILOR - ESTIMAT DECEMBRIE 2021
8DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN56 47+000 84+020 MOCHLOS S.A. GALICEA MARE - CALAFAT LOT 2 33.83 100% 91.43% 03.09.2012 16.06.2021
81.94 MIL. LEI
FARA TVAPROCESUL VERBAL DE RECEPTIE LA TERMINAREA LUCRARILOR A FOST APROBAT DE DIRECTORUL GENERAL AL CNAIR IN DATA DE 16.06.2021.
9DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN76 69+350 102+660
ASOCIEREA SC DRUM ASFALT SRL –
VAHOSTAV SK A.S. – TRAMECO SA –
ILE VIOREL CONSTRUCT SRL.
VARFURILE - STEI LOT 4 33.31 84.68% 39.56% 29.06.2020
DECEMBRIE 2021 -
RECEPTIE LA
TERMINAREA
LUCRARILOR
DECEMBRIE 2026 -
RECEPTIE FINALA
ANUL 202174.78 MIL LEI
FARA TVA
CONTRACTUL PENTRU FINALIZAREA LUCRARILOR A FOST SEMNAT IN DATA DE 08.05.2020;
ORDINUL DE INCEPERE A LUCRARILOR A FOST EMIS IN DATA DE 29.06.2020;
PREDARE AMPLASAMENT - 02.07.2020.
10DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN71 0+000 109+905
LOT 1 - ASOCIEREA SC AQUA PARC
SRL - SC MAVGO HOLDING SRL -
HYDROSTROY AD - VDH AD
(VODSTROI 98 AD) - SC BDU MAXI
CONSTRUCT SRL
CONSTRUCTORUL A FOST NOTIFICAT
PENTRU REZILIERE
LOT 1 (SECTOR 1): BALDANA -
TARGOVISTE KM. 0+000 - KM
44+130 LARGIRE LA 4 BENZI
DE CIRCULATIE; LOT 2
(SECTOR 2): TARGOVISTE -
SINAIA KM. 51+041 - KM
109+905 - DRUM LA 2 BENZI)
102.99 0% 0%1567.03 MIL. LEI
FARA TVA
LOTUL 1 - IN DATA DE 14.01.2021 A FOST INAINTATA NOTIFICAREA DE REZILIERE.
LOTUL 2 - PROCEDURA RELUATA
PROCEDURA DE ACHIZITIE PUBLICA IN DERULARE
11DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN28B 0+000 76+758
ASOCIEREA SC AQUA PARC SRL - SC
MAVGO HOLDING SRL - VAHOSTAV -
SK A.S. - TRAMECO SA
MODERNIZARE DN28B, TARGU
FRUMOS – BOTOSANI, KM 0+000 –
KM 76+758
71.512 6% 10.10%
15.07.2020 -
ORDIN INCEPERE
PENTRU ETAPA
PROIECTARE
Aug-23 Aug-23267.31 MIL LEI
FARA TVA
CONTRACT PROIECTARE SI EXECUTIE IN DERULARE - SEMNAT IN DATA DE 20.05.2020.
AVIZAT PT CTE CNAIR 21.07.2021 AVIZAT PT CTE DRDP IASI - 09.06.2021 - AVIZAT DTAC DRDP IASI - 10.03.2021; AVIZAT DTAC CNAIR SA - 16.03.2021. AUTORIZATIE DE CONSTRUIRE NR. 21/12.05.2021 EMISA DE MTIC.
12DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN29D 2+800 48+146
ASOCIEREA SC AUTOTEHNOROM SRL
- SC OPR ASFALT SRL - OBRAS
PUBLICAS-Y REGADIOS SA - SC
EVALCONS TECH SRL
MODERNIZARE DN29D BOTOSANI -
STEFANESTI KM 2+800 – KM 18+500
SI KM 18+800 – KM 48+146
45.046 12% 2%
22.06.2020 -
EMITERE ORDIN
DE INCEPERE
PENTRU ETAPA
PROIECTARE
MARTIE 2023208.44 MIL LEI
FARA TVA
IN DATA DE 29.06.2020 A FOST DEPUSA APLICATIA DE FINANTARE PENTRU ANGAJAREA CHELTUIELILOR AFERENTE ACESTUI PROIECT, DIN FONDURI NERAMBURSABILE, ALOCALTE IN CADRUL POIM 2014 - 2020
CONTRACT PROIECTARE SI EXECUTIE IN DERULARE
IN DATA DE 08.01.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUCTIE
TERMEN DE PREDARE A PROIECTULUI TEHNIC DE EXECUTIE: 28.02.2021
PT - AVIZAT CNAIR SA NR. 5035/26.03.2021
13DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN7 30+950 52+350
LARGIRE LA 4 BENZI A DN7,
BALDANA-TITU, KM 30+950-KM
52+350
21.4
ESTIMAT
SEMNARE
CONTRACT IN
IPOTEZA FARA
CONTESTATIE:
MARTIE 2021
DECEMBRIE 2023 DECEMBRIE 2023210.63 MIL. LEI
FARA TVA
04.11.2020 A AVUT LOC DEPUNEREA OFERTELOR PENTRU PROCEDURA DE ATRIBUIRE A CONTRACTULUI "PROIECTARE TI EXECUTIE LARGIRE LA 4 BENZI A DN 7, BALDANA-TITU, KM 30+950 – KM 52+350”.
PANA LA TERMENUL LIMITA AU DEPUS OFERTE URMATORII AGENTI ECONOMICI:
1. ASOCIEREA CLAY WORK BUCHAREST - DIMAKS TURIZM INSAAT ENERJI AKARYAKIT NAK. VE TAS. GIDA TEM. OTOM. OTO. KIR.ITH. IHR. SAN.VE.TIC.LTD.STI. ISTANBUL;
2. ASOCIEREA COSEDIL SPA – SC BIT INVEST SRL - CHIRULLI ANDREA IMPRESA INDIVIDUALE – SC TOTAL ROAD SRL;
3. ASOCIEREA SC G&M ROAD BUILDING ENGINEERING SRL – SC KIRLIC GROUP SRL – SC BUILDING DESIGN 2000 TOP SRL – SC IRIMAT CONS S.R.L. - D'AGOSTINO ANGELO ANTONIO COSTRUZIONI GENERALI S.R.L. – SC CONCORDIA CON. STRADE S.R.L – SC SERCONSTRUCT
ROADS S.R.L.;
4. ASOCIEREA SC MAVGO HOLDING S.R.L. – SC BDU MAXI CONSTRUCT S.R.L.;
5. OZALTIN INSAAT TICARET VE SANAYI A.S.
VALOAREA ESTIMATA A CONTRACTULUI ESTE CUPRINSA IN INTERVALUL 243.801.103,00 - 289.093.324,00 LEI FARA TVA.
DURATA CONTRACTULUI ESTE DE 6 LUNI PERIOADA DE PROIECTARE TI 20 DE LUNI PENTRU EXECUTIA LUCRARILOR.
COMISIA DE EVALUARE VA ANALIZA OFERTELE IN CONFORMITATE CU PREVEDERILE DOCUMENTATIILOR DE ATRIBUIRE TI CU LEGISLATIA IN VIGOARE IN DOMENIUL ACHIZITIILOR PUBLICE.
ANALIZA SI EVALUAREA OFERTELOR CU STABILIREA OFERTANTULUI CASTIGATOR: 29.04.2021;
COMUNICAREA REZULTATULUI PROCEDURII: 29.04.2021;
TERMEN DEPUNERE CONTESTATII: 10.05.2021;
ESTIMAT SEMNARE CONTRACT, IN IPOTEZA FARA CONTESTATII: 25.05.2021
14DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN6 132+435 185+230
REABILITARE DN 6, ALEXANDRIA -
CRAIOVA, KM 90+190 - KM 222+182
LOT 2: KM 132+435 - KM 185+230
(RELICITARE)
48.009 2021 2024 ANUL 2024267.15 MIL. LEI
FARA TVA
CONTRACT REALIZARE EXPERTIZA TEHNICA SEMNAT IN DATA DE 06.06.2020
ORDINUL DE INCEPERE A FOST EMIS IN DATA DE 10.07.2020, CU O DURATA CONTRACTUALA DE 90 DE ZILE, TERMEN DE FINALIZARE 08.10.2020
CALENDAR PROCEDURA DE LICITATIE LOTUL 2, KM 132+435 - 185+230 - RELICITARE
DEPUNERE OFERTE: 29.06.2021
PROCEDURA IN CURS DE ANALIZA SI EVALUARE A OFERTELOR
15DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN66 106+220 106+965
ASOCIEREA S.C. FREYROM S.A. -
PROCONS GROUP S.R.L
REABILITARE DN66 PRIN
REAMENAJAREA SECTORULUI
CUPRINS INTRE KM 105+000 – KM
105+580 IN VEDEREA CONSTRUIRII
UNUI POD NOU PESTE JIU DE LA
MERI LA KM 105+250,
REAMENAJARE SECTOR KM 106+220
– KM 106+965
1.325 40.00% 10.75% 12.11.2020 12.07.2022 ANUL 202219.85 MIL. LEI
FARA TVA
CONTRACT EXECUTIE LUCRARI SEMNAT IN DATA DE 02.11.2020
DURATA DE REALIZARE A INVESTITIEI: 12 LUNI (EXCLUSIV PERIOADA DE TIMP FRIGUROS, DE REGULA, CUPRINSA IN PERIOADA 15.11- 15.03 ), CU O PERIOADA DE GARANTIE A LUCRARILOR ACORDATA DE EXECUTANT DE 96 LUNI (8 ANI).
APROBATA SITUATIA DE LUCRARI NR. 1 IN VALOARE DE 673.083,63 LEI FARA TVA. APROBATA SITUATIA DE LUCRARI NR. 2 IN VALOARE DE 991.685,77 LEI FARA TVA.
DOCUMENTATIA TEHNICA REPREZENTAND MODIFICARILE PREVAZUTE IN DISPOZITIILE DE SANTIER 1-7 A FOST AVIZATA IN CTE DRDP CRAIOVA CU AVIZ NR.545/01.07.2021 SI IN CTE CNAIR SA IN DATA DE 21.07.2021. DISPOZITIILE DE SANTIER 1-6 CONSUMA REZERVELE DE
IMPLEMENTARE, IN VALOARE DE 1.893.728,52 LEI FARA TVA. MODIFICARILE DIN DISPOZITIA DE SANTIER NR. 7 CONDUC LA O DEPASIRE CU 4.122.679,12 LEI FARA TVA A VALORII CONTRACTULUI , CEEA CE REPREZINTA 20.77 % DIN VALOAREA CONTRACTULUI. S-A
TRANSMIS CATRE CNAIR O ADRESA PENTRU COMUNICAREA SURSEI DE FINANTARE AFERENTA LUCRARILOR SUPLIMENTARE AVIZATE AFERENTE PODULUI PESTE JIU DE LA MERI. DIRECTIA ECONOMICA SI FINANCIARA A CNAIR A COMUNICAT EXISTENTA RESURSELOR
BUGETARE IN VEDEREA SEMNARII ACTULUI ADITIONAL LA CONTRACTUL DE LUCRARI. PROCEDURA PENTRU INCHEIEREA ACTULUI ADITIONAL A FOST SELECTATA DE ANAP IN VEDEREA CONTROLULUI EX-ANTE.
16DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN2L 60+165 76+277
MODERNIZARE DN 2L, SOVEJA -
LEPSA, KM 60+165 - KM 76+27716.112
PROIECTARE IN
DERULARE
ORDINUL DE
INCEPERE
PENTRU
PROIECTARE A
FOST EMIS IN
DATA DE
22.09.2020
DECEMBRIE 2023 DECEMBRIE 2023106.54 MIL. LEI
FARA TVA
CONTRACT DE PROIECTARE SI EXECUTIE LUCRARI SEMNAT IN DATA DE 24.07.2020.
VALOARE CONTRACT PROIECTARE + EXECUTIE LUCRARI: 126.778.219,70 LEI CU TVA, DIN CARE:
PROIECTARE: 3.655.098,42 LEI CU TVA
EXECUTIE LUCRARI: 123.123.121,28 LEI CU TVA
AVIZAT DTAC CTE DRDP IASI 16918/ 10.05.2021; AVIZAT DTAC CTE CNAIR SA - 08.06.2021
DURATA CONTRACTULUI ESTE: 30 LUNI PERIOADA DE PROIECTARE SI EXECUTIE A LUCRARILOR:
- 6 LUNI PROIECTARE;
- 24 LUNI EXECUTIE LUCRARI;
- 84 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.
PTE IN CURS DE REVIZUIRE.
17DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN7 256+675 258+950
PROIECTARE SI EXECUTIE
"REALIZARE BANDA A TREIA DN 7
VALEA OLTULUI INTRE KM 256+675
– KM 258+950”
2.2748.46 MIL. LEI
FARA TVA
18DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN69 0+000 10+000
TODINI COSTRUZIONI GENERALI
S.P.A.
DRUM DE LEGATURA INTRE DN69 SI
AUTOSTRADA A19,90
CTR SEMNAT IN
DATA DE
01.02.2021
01.03.2021 01.04.2023 ANUL 2023 189.57 MIL LEI
FARA TVA
CONTRACT SEMNAT IN DATA DE 01.02.2021, CU O PERIOADA CONTRACTUALA DE 2 ANI (6 LUNI PROIECTAREA ȘI 18 LUNI EXECUTIE ) ȘI ARE O GARANȚIE DE 84 DE LUNI. IN DATA DE 02.07.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 35 (NR MTI 26799 DIN
02.07.2021) - ETAPA I. AVIZ CTE CNAIR NR. 5075 DIN 30.06.2021 .
19DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN7 0+000 14+300
DRUM DE LEGATURA A1 - DN7
(TITU) (DJ 711A) - LARGIRE LA 4
BENZI DE CIRCULATIE
14.3 OCTOMBRIE 2019 Aug-2173.33 MIL. LEI
FARA TVA
STUDIUL DE FEZABILITATE IN VARIANTA DRAFT PREDAT DE CATRE PRESTATOR IN CURS DE ANALIZA.
S-AU EMIS OBSERVATII ASUPRA VARIANTEI DRAFT A STUDIUL DE FEZABILITATE SI SE ASTEAPTA VARIANTA FINALA.
IN DATA DE 29.04.2021 PRESTATORUL A TRANSMIS STUDIUL DE FEZABILITATE. STUDIUL DE FEZABILITATE SE AFLA IN ANALIZA LA BENEFICIAR. IN DATA DE 25.05.2021 AU FOST TRANSMISE OBSERVATIILE BENEFICIARULUI LA DOCUMENTATIA INAINTATA IN DATA DE
29.04.2021. PRESTATORUL IMPLEMENTEAZA OBSERVATIILE FORMULATE PENTRU SF.
20DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL
DRUM TRANSREGIO
GILAU - APAHIDA0+000 38+800 GILAU - APAHIDA 38.8
CONTRACT
SERVICII DE
PROIECTARE
DERULAT IN BAZA
UNUI PROTOCOL
DE CATRE UAT
CLUJ NAPOCA
2345.52 MIL.
FARA TVA
STUDIU DE FEZABILITATE IN ELABORARE
FINALIZARE SF - TRIM. IV 2021
21DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN24C 106+650 142+250
S.C. SEARCH CORPORATION S.R.L. -
ELABORARE SF / S.C. BEST
CONSULTING & DESIGN S.R.L.
BUCURESTI - REVIZUIRE S.F.
MANOLEASA - RADAUTI PRUT 35.6 33.63% 0%109.69 MIL. LEI
FARA TVA
SF REVIZUIT IN ANUL 2016 / HG NR. 460/28.06.2018 PENTRU APROBAREA INDICATORILOR TEHNICO-ECONOMICI
LIPSA FINANTARE LUCRARI
22DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL
POD PE DN13C PESTE
RAUL TARNAVA MARE
LA VANATORI
1+200 1+252POD PE DN 13C PESTE RAUL
TARNAVA MARE LA VANATORI0.0521
5.45 MIL. LEI
FARA TVACONTRACT SEMNAT IN LUNA OCTOMBRIE 2020.
23DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN1H 6+000 12+000 SC MECANO BAU TRADING SRL
REMEDIERE DEFECTIUNI PE DN1H
KM 6+000 - KM 12+0006 94.00% 61.16% 15.10.2020 15.11.2021 ANUL 2021
12.761 MIL. LEI
FARA TVAORDINUL DE INCEPERE A FOST EMIS INCEPAND CU DATA DE 15.10.2020. Estimare Receptie la Terminarea lucrarilor noiembrie 2021.
24DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN51 2+600 43+783 ZIMNICEA - ALEXANDRIA 41.183
0.1953 MIL. LEI
FARA T.V.A.DOCUMENTATIE INTOCMITA IN VEDEREA PROMOVARII SPRE LICITATIE.
25DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN2
PASAJ SUPERIOR PE DN2, PESTE CF
LA ROMAN, KM 332+9612
841.094 MIL. LEI
FARA TVA
26DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN57 152+990 200+745
152+990 - 200+745 (ORAVITA -
MORAVITA)47.755
1.638 MII LEI
FARA TVADOCUMENTATIE PREDATA LA DIRECTIA ACHIZITI
27DRUMURI NATIONALE IN REABILITARE/
MODERNIZAREDRUM NATIONAL DN21 104+160 106+900
PROIECTARE SI EXECUTIE PASAJ
SUPERIOR PE DN 21, KM105+5002.74 0% 0% 15.03.2021 01.09.2023 ANUL 2023
98.120 MIL LEI
FARA TVA
S-A EMIS ORDINUL DE INCEPERE IN DATA DE 15.03.2021.
DURATA DE EXECUTIE CONTRACT :
- 360 ZILE PERIOADA DE PROIECTARE
- 540 ZILE PERIOADA DE EXECUTIE.
STADIU: S-A EMIS AVIZUL PENTRU DECLARATIA DE PROIECTARE.
NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1VARIANTE OCOLITOARE PROIECTE IN
EXECUTIEVARIANTA OCOLITOARE CENTURA BUCURESTI
STRACO GRUP SRL - SC COMNORD
SRL - SPECIALIST CONSULTING SRL
PASAJ SUPRATERAN PE DJ 602
CENTURA BUCURESTI DOMNESTIDOMNESTI - DJ 602 0.536 43.62% 32.27%
15.01.2019 -
PENTRU
LUCRARILE
AUTORIZATE PRIN
AC 140/
20.12.2018
16.09.2019
PENTRU
LUCRARILE
AUTORIZATE PRIN
AC 69/28.08.2019
23.09.2020 -
PENTRU
LUCRARILE
AUTORIZATE PRIN
AC 54/23.09.2020
24 LUNI DE LA
EMITEREA
AUTORIZATIEI DE
CONSTRUIRE
(ESTIMAT LUNA
09.2022)
ANUL 202291.55 MIL. LEI
FARA TVA
CONTRACTUL DE PROIECTARE SI EXECUTIE PASAJ DOMNESTI A FOST SEMNAT IN DATA DE 10.05.2017
AUTORIZATIA DE CONSTRUIRE NR. 140/ 20.12.2018, NR. 69/ 28.08.2019 SI NR. 54/ 23.09.2020
LUCRARI IN EXECUȚIE: STRAT FUNDATIE DIN BALAST STABILIZAT - BRETEA INTOARCERE PRELUNGIREA GHENCEA HIDROIZOLATIE PE BALAST STABILIZAT - BRETEA INTOARCERE PRELUNGIREA GHENCEA STRAT DE MIXTURA DENSA AB31,5 - BRETEA PRELUNGIREA GHENCEA
HIDROIZOLATIE PE STRAT DE BAZA AB 31,5 - BRETEA PRELUNGIREA GHENCEA STRAT DE LEGATURA, BINDER BAD 22,4 - BRETEA PRELUNGIREA GHENCEA COFRARE ELEVATIE - ETAPA III CULEE C2 BETONARE ELEVATIE - ETAPA III - CULEE C2 ARMARE ELEVATIE - ETAPA III -
CULEE C2 ARMARE ELEVATIE - ETAPA III - CULEE C1 BETONARE ELEVATIE - ETAPA III - CULEE C1 LISE PREFABRICATE (PROCURARE SI MONTAJ) - ST3 TABLIER METALIC MONTAT - ST1 - GIRATIE COFRARE ELEVATIE - ETAPA III - CULEE C1 BETONARE ELEVATIE - ETAPA III -
CULEE C1 MONTARE BORDURI 20X25 CM - BRETEA INTOARCERE PRELUNGIREA GHENCEA UMPLUTURA GRANULARA - RAMPA PAMANT ARMAT COBORARE C3 PANOURI PREFABRICATE TERRE ARMEE - RAMPA PAMANT ARMAT COBORARE C3 EXCAVATI PT. TEREN
FUNDARE - RAMPA PAMANT ARMAT C7
2VARIANTE OCOLITOARE PROIECTE IN
EXECUTIEVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
BACAU0+000 30+842
SPEDITION UMB SRL –
TEHNOSTRADE SRLBACAU
OBIECT 1: 0+000 -20+299,
OBIECT 2: 0+000 - 3+177
OBIECT 3: 0+000 -7+366
30.842 100.00% 99.78%
23.01.2019 -
DATA DE
INCEPERE
PERIOADA DE
PROIECTARE
08.03.2019 -
DATA DE
INCEPERE A
LUCRARILOR IN
BAZA AC
040/15.07.20150
3.07.2019 - DATA
DE INCEPERE A
LUCRARILOR IN
BAZA AC
051/28.06.2019
IANUARIE 2022 ANUL 2020668.33 MIL. LEI
FARA TVA
DESCHIDERE TRAFIC
03.09.2020 - OBIECT 3;
02.12.2020 - OBIECT 1
VARIANTE OCOLITOARE PROIECTE IN EXECUTIE - OCTOMBRIE 2021
VARIANTE OCOLITOARE
3VARIANTE OCOLITOARE PROIECTE IN
EXECUTIEVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
BARLAD0+000 11+281
ASOCIEREA SC TEHNIC ASIST SRL – SC
TASS INFRA LOGISTIC SRLBARLAD 1 11.281 29.00% 18.98%
05.12.2018
(DATA DE
INCEPERE A
ACTIVITATII DE
PROIECTARE)
06.08.2020 -
DATA DE
INCEPERE A
LUCARILOR)
ESTIMAT IUNIE
2022
132.051 MIL. LEI
FARA TVA
CONTRACTUL A FOST SEMNAT IN DATA DE 24.10.2018. ORDINUL DE INCEPERE PENTRU PROIECTAREA LUCRARILOR A FOST EMIS.
A FOST AVIZAT PROIECTUL TEHNIC IN SEDINTA CTE DIN DATA DE 19.06.2020
AUTORIZATIE DE CONSTRUIRE A FOST EMISA.
ORDINUL DE INCEPERE A LUCRARILOR A FOST EMIS IN DATA DE 06.08.2020
AMPLASAMENTUL LUCRARILOR A FOST PREDAT CATRE ANTREPRENOR IN DATA DE 06.08.2020.
4VARIANTE OCOLITOARE PROIECTE IN
EXECUTIEVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
GALATI0+000 33+600
ASOCIEREA S.C. SA&PE CONSTRUCT
S.R.L. – S.C. SPEDITION UMB S.R.L. –
S.C. TEHNOSTRADE S.R.L.
GALATI 1 33.6 0% 0% IUNIE 2021 DECEMBRIE 2025 ANUL 2025705.28 MIL. LEI
FARA TVA
PRETUL PE KM ESTE DE CCA. 20.990.555 LEI FĂRĂ TVA, REPREZENTAND CCA. 4,327,949 EURO FARA TVA.
DURATA CONTRACTULUI ESTE DE 174 DE LUNI, DIN CARE:
• 12 LUNI PERIOADA DE PROIECTARE,
• 42 LUNI PERIOADA DE EXECUTIE A LUCRĂRILOR,
• 64 DE LUNI PERIOADĂ DE GARANȚIE A LUCRĂRILOR.
5VARIANTE OCOLITOARE PROIECTE IN
EXECUTIEVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
MIHAILESTI0+000 3+180 S.C. VIAROM CONSTRUCT S.R.L. MIHAILESTI RELICITARE 3.18
30.7% - PROGRES
IN CADRUL
CONTRACTULUI
REZILIAT;
80% IN CADRUL
NOULUI
CONTRACT
31.94% -
PROGRES IN
CADRUL
CONTRACTULUI
REZILIAT;
35.03 % IN
CADRUL NOULUI
CONTRACT
FEBRUARIE 2021 -
DEMARARE
LUCRARI RAMASE
DE EXECUTAT
FEBRUARIE 202236.9 MIL. LEI
FARA TVA
CONTRACT REZILIAT IN DATA DE 04.04.2019 DE CATRE CNAIR SA PENTRU NEINDEPLINIREA DE CATRE ANTREPRENOR A MAI MULTOR INSTIINTARI DE REMEDIERE.
EXPERTIZA TEHNICA REALIZATA - 2019
IN DATA DE 23.12.2020 CNAIR A SEMNAT CONTRACTUL AVAND CA OBIECT “CONSTRUCTIA VARIANTEI DE OCOLIRE MIHAILESTI - FINALIZARE LUCRARI”, CU OFERTANTUL DECLARAT CASTIGATOR S.C. VIAROM CONSTRUCT S.R.L.
VALOAREA CONTRACTULUI ESTE DE 36.862.651,20 LEI FARA TVA.
SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE.
TRASEUL ARE O LUNGIME DE 3,18 KM.
DURATA CONTRACTULUI ESTE DE 72 DE LUNI, DIN CARE:
12 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,
60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.
A FOST EMIS ORDINUL DE INCEPERE LUCRARI PENTRU DATA DE 15.02.2021.
6VARIANTE OCOLITOARE PROIECTE IN
EXECUTIEVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
SATU MARE0+000 19+540
ASOCIEREA ITINERA SPA COLLINI
LAVORI SPA - VIA DESIGN SRLSATU MARE 1 19.54 77.82% 63.03%
30.06.2017
(SERVICII DE
PROIECTARE)
28.06.2018
(EXECUTIE
LUCRARI)
ESTIMAT
DECEMBRIE 2021
304.791 MIL. LEI
FARA TVA
CONTRACTUL DE PROIECTARE SI EXECUTIA VARIANTEI DE OCOLIRE SATU MARE A FOST SEMNAT IN DATA DE16.11.2015
DATA DE INCEPERE A PERIOADEI DE PROIECTARE ESTE 30.06.2017.
DATA DE INCEPERE EXECUTIE LUCRARi ESTE 28.06.2019-ETAPA I.
DATA DE INCEPERE EXECUTIE LUCRARI ETAPA II ESTE 02.12.2020
7VARIANTE OCOLITOARE PROIECTE IN
EXECUTIEVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
TARGU JIU0+000 19+987
COLLINI LAVORI SPA - CONTRACT
REZILIAT
CONTRACT RELICITAT - ASOCIEREA
SECOL SOCIETA EDILE COSTRUZIONI
E LAVORI S.A.
TARGU JIU RELICITARE 19.987
40% PROGRES
INREGISTRAT IN
CADRUL
CONTRACTULUI
DE LUCRARI
REZILIAT;
14.50% IN
CADRUL NOULUI
CONTRACT
37.5% PROGRES
INREGISTRAT IN
CADRUL
CONTRACTULUI
DE LUCRARI
REZILIAT;
2.27% IN CADRUL
NOULUI
CONTRACT
14.10.2014 - CTR
REZILIAT
NOV. 2020 -
CONTRACT
RELICITAT
SEMNAT
CONTRACT
REZILIAT DE
CATRE
ANTREPRENOR IN
LUNA 05.2018.
CONFORM
CONTRACT
RELICITAT -
AUGUST 2022
207 MIL. LEI FARA
TVA
IN DATA DE 24.11.2020 A FOST SEMNAT CONTRACTUL NR 92/79265.
A FOST EMIS ORDINUL DE INCEPERE LUCRARI PENTRU DATA DE 15.02.2021.
IN DATA DE 18.02.2021 A FOST PREDAT AMPLASAMENTUL.
8VARIANTE OCOLITOARE PROIECTE IN
EXECUTIEVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
TECUCI0+000 6+945
ASOCIEREA S.C. MAVGO HOLDING
S.R.L. – S.C. ANTREPRIZA DE
CONSTRUCȚII DRUMURI ȘI
AUTOSTRĂZI S.R.L. (FOSTA S.C. AQUA
PARC S.R.L.) – S.C. BDU MAXI
CONSTRUCT S.R.L. – HYDROSTROY
AD
TECUCI (RELICITARE) RELICITARE 6.945
58% - PROGRES
FIZIC
INREGISTRAT LA
DATA REZILIERII
17% IN CADRUL
NOULUI
CONTRACT
29.63% -
PROGRES
INREGISTRAT IN
CADRUL
CONTRACTULUI
DE LUCRARI
REZILIAT
9.49% IN CADRUL
NOULUI
CONTRACT
CONTRACTUL
PENTRU
"CONSTRUCTIA
VARIANTEI DE
OCOLIRE TECUCI -
REST DE
EXECUTAT” A
FOST SEMNAT IN
16.04.2021. A
FOST EMIS
ORDINUL DE
INCEPE LUCRARI
IN 20.05.2021.IN
21.05.2021 A
AVUT LOC
PREDAREA
AMPLASAMENTUL
UI
CONTRACT
REZILIAT IN DATA
DE
20.05.2019.CONT
RACTUL PENTRU
"CONSTRUCTIA
VARIANTEI DE
OCOLIRE TECUCI -
REST DE
EXECUTAT” A
FOST SEMNAT IN
16.04.2021. A
FOST EMIS
ORDINUL DE
INCEPE LUCRARI
IN 20.05.2021.IN
21.05.2021 A
AVUT LOC
PREDAREA
AMPLASAMENTUL
UI
41.74 MIL. LEI
FARA TVA
VINERI, 16.04.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL PENTRU "CONSTRUCTIA VARIANTEI DE OCOLIRE TECUCI - REST DE EXECUTAT”, CU ASOCIEREA S.C. MAVGO HOLDING S.R.L. – S.C. ANTREPRIZA DE CONSTRUCTII DRUMURI SI AUTOSTRAZI S.R.L. (FOSTA S.C. AQUA
PARC S.R.L.) – S.C. BDU MAXI CONSTRUCT S.R.L. – HYDROSTROY AD.
VALOAREA CONTRACTULUI ESTE DE 41.735.534,38 LEI FARA TVA.
SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE.
VARIANTA DE OCOLIRE TECUCI ARE O LUNGIME DE 6,945 KM.
VARIANTA SE DESPRINDE DIN DN24, TRAVERSEAZĂ CU UN PASAJ SUPERIOR DN24 ȘI LINA CF MARASESTI - TECUCI LA KM 0+385,95, CONTINUA IN ALINIAMENT PANA LA INTERSECTIA LA NIVEL CU DJ252H LA KM 2+490, TRAVERSEAZA CU PASAJ SUPERIOR LINIA CF FAUREI -
TECUCI LA KM 6+416,29 SI SE FINALIZEAZA LA KM 6+945 (ECHIVALENT CU KM 6+801,29), LA INTERSECȚIA CU DN25.
PERIOADA CONTRACTUALA DE EXECUTIE A LUCRARILOR ESTE DE 12 DE LUNI, IAR PERIOADA DE GARANTIE ESTE DE 60 DE LUNI.
9VARIANTE OCOLITOARE PROIECTE IN
EXECUTIEVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
TIMISOARA SUD0+000 25+690 TIRRENA SCAVI S.P.A TIMISOARA - SECTOR SUD 25.69 38.68% 32.34%
29.01.2019 -
DATA DE
INCEPERE
PERIOADA DE
PROIECTARE
25.03.2020 -
ORDIN - INCEPERE
EXECUTIE
LUCRARI
ESTIMAT 2022 ANUL 2022272.43 MIL. LEI
FARA TVA
PROIECT TEHNIC FINALIZAT
AUTORIZATIE DE CONSTRUIRE EMISA IN LUNA MARTIE 2020.
EXECUTIE LUCRARI IN DERULARE.
10VARIANTE OCOLITOARE PROIECTE IN
EXECUTIEVARIANTA OCOLITOARE
VARIANTA
OCOLITOARE ZALAU
VO DN 1V0+000 5+535
ASOCIEREA SINOHYDRO
CORPORATION LIMITED – SC GOOD
PROOD S.R.L.
ETAPA 2 - 7 KM INTRE DN 1F KM
79+625 - DJ 191C1
5.535 KM (5
VIADUCTE, 2
PODURI, 2
INTERSECTII TIP
GIRATIE)
9% 16% 2020 2023 2023185.54 MIL. LEI
FARA TVA
ORDINUL DE INCEPERE A CONTRACTULUI A FOST COMUNICAT CA FIIND 25.09.2020 (PROIECTARE+EXECUTIE). PERIOADA DE PROIECTARE ESTE DE 6 LUNI (FINALIZARE 24.03.2021) SI 24 LUNI EXECUTIE LUCRARI (FINALIZARE 23.03.2023).
DECIZIA DE EXPROPRIERE NR. 1848 DIN 10.11.2020.
A FOST ACORDATA ANTREPRENORULUI POSESIA SANTIERULUI.
A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 17/26.03.2021.
A FOST EMISA HOTARAREA DE GUVERN NR.622 DIN 03.06.2021 PRIVIND SCOATEREA DEFINITIVA DIN FONDUL FORESTIER NATIONAL.
11VARIANTE OCOLITOARE PROIECTE IN
EXECUTIEVARIANTA OCOLITOARE
DRUM DE LEGATURA
DN5 - SOSEAUA DE
CENTURA - POD
PRIETENIEI
0+000 5+720 PORR CONSTRUCT S.R.L.
DRUM DE LEGATURA DN5 -
SOSEAUA DE CENTURA - POD
PRIETENIEI
5.72 66.10% 36.45% APRILIE 2020 ESTIMAT 2022 ESTIMAT 2022106.638 MIL. LEI
FARA TVA
IN DATA DE 19.11.2019 A FOST SEMNAT CONTRACTUL DE PROIECTARE SI EXECUTIE AFERENT ACESTUI OBIECTIV.
IN DATA DE 05.03.2020 A FOST SEMNAT CONTRACTUL DE SUPERVIZARE AFERENT LUCRARILOR.
IN DATA DE 15.04.2020 A FOST EMIS ORDINUL DE INCEPERE PENTRU PROIECTARE
IN DATA DE 21.10.2020 A FOST EMIS ORDINUL DE INCEPRE PENTRU EXECUTIA LUCRARILOR
NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1VARIANTE OCOLITOARE IN PREGATIRE
FAZA EXECUTIE LUCRARIVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
SIGHISOARA0+000 13+057
PROCEDURA DE LICITATIE ATRIBUIRE
CONTRACT PROIECTARE SI EXECUTIE
IN DERULARE
SIGHISOARA 13.057 0.00% 0.00% 14.06.2021ESTIMAT
23.11.2021ESTIMAT 2021
293.084 MIL LEI
FARA TVA14.06.2021 - DATA PUBLICARII ANUNTULUI, 31.08.2021 - DATA DE DEPUNERE A OFERTELOR, 23.11.2021 - DATA FINALIZARE PROCEDURA DE EVALUARE
2VARIANTE OCOLITOARE IN PREGATIRE
FAZA EXECUTIE LUCRARIVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
SFANTU GHEORGHE0+000 8+000 CONTRACT ELABORARE SF FINALIZAT SFANTU GHEORGHE 1 8 07.05.2018
2020 -
FINALIZARE
PROIECTARE,
ETAPA STUDIU DE
FEZABILITATE
41.47 MIL. LEI
FARA TVAPROCEDURA DE ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE - IN DERULARE, ETAPA EVALUARE OFERTE.
3VARIANTE OCOLITOARE IN PREGATIRE
FAZA EXECUTIE LUCRARIVARIANTA OCOLITOARE CENTURA BUCURESTI 35+600 55+465
LARGIRE LA 4 BENZI A CENTURII
RUTIERE A MUNICIPIULUI
BUCURESTI SUD INTRE A1 (KM
55+520) SI DN 5 (KM 40+000) - LOT
1 SI LOT 2
18,68
31,508LEI FARA
TVA - LOT 1
638,945 LEI FARA
TVA - LOT 2
DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL DE MAI JOS
NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1VARIANTE OCOLITOARE IN PREGATIRE
FAZA SF/PT/DTACVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
GIURGIU0+000 12+068
CONTRACT ELABORARE FAZE DE
PROIECTARE SF+PT+DE+DTAC+AT IN
DERULARE
GIURGIU 1
12.068 CONFORM
VARIANTEI DE
TRASEU
APROBATA
70% - SF
FINALIZAT SI
APROBAT PRIN
HG INDICATORI
TEHNICO -
ECONOMICI NR.
58/24.02.2021
57% 14.03.2018
2021 -
FINALIZARE
ETAPA DE
PROIECTARE.
DURATA DE
EXECUTIE A
LUCRARILOR : 36
DE LUNI DE LA
ORDINUL DE
INCEPERE, DUPA
FINALIZAREA
SERVICIILOR DE
PROIECTARE SI
OBTINEREA
AUTORIZATIEI DE
CONSTRUCTIE
VALOARE
PROIECT 1.6 MIL
LEI FARA TVA;
VALOARE
LUCRARI CF. SF -
VARIANTA 4
AVIZATA: TOTAL
GENERAL - 343.36
MIL LEI FARA TVA
CONTRACT PRESTARI SERVICII DE PROIECTARE FAZELE SF+PT+DE+DATC+AT SEMNAT IN DATA DE 14.03.2018.
ORDIN DE INCEPERE NR.3B/4773/26.03.2018 EMIS IN DATA DE 26.03.2018 PENTRU SERVICII DE PROIECTARE IN FAZA SF.
SF FINALIZAT SI APROBAT PRIN HG INDICATORI TEHNICO-ECONOMICI NR. 58/24.02.2021.
ORDIN DE INCEPERE PENTRU PT+DTAC SI AVIZE - NR. 3B/4773/26.03.2018 - INCEPAND CU 01.10.2020. PROIECTUL TEHNIC A FOST PREDAT IN 29.01.2021.
DOCUMENTATIA PENTRU PROMOVAREA HG DE EXPROPRIERI SI DOCUMENTATIA PT + DTAC AU FOST CONDIȚIONATE DE SUPRAPUNEREA OBIECTIVULUI CU UN OBIECTIV PRIVAT FINANTAT DIN FONDURI EUROPENE AFIR, FIIND NECESARE URMATOARELE:
* AVIZAREA IN CTE DRDP BUCURESTI A DOCUMENTATIEI PT+DTAC IN VARIANTA NOUA PROPUSA PENTRU CORELAREA OBIECTIVELOR, AVIZ OBTINUT IN DATA 04.06.2021;
* AVIZAREA IN CTE CNAIR A DOCUMENTATIEI PT+DTAC A DOCUMENTATIEI CU SOLUTIA MODIFICATA FATA DE CEA DIN SF, AVIZ OBTINUT CU NR. 5094/01.09.2021 TRANSMIS SI INREGISTRAT LA DRDP BUCURESTI CU NR.8/33194/16.09.2021;
* AVIZARE IN CTE CNAIR SIGURANTA CIRCULATIEI PENTRU PROIECT VO GIURGIU IMPREUNA CU PROIECTUL DE SEMNALIZARE SI MARCAJE SI CU PROIECTUL DE PARAPETE, DOCUMENT DE AVIZARE NR. 92/61651/27.07.2021, INREGISTRAT LA DRDP BUCURESTI CU NR.
8/31123/31.08.2021;
MAI SUNT DE ELABORAT :
* DETALII DE EXECUTIE 1 LUNA;
*PREGATIRE DOCUMENTATIE DE ATRIBUIRE PENTRU ACHIZITIA LUCRARI DE EXECUTIE: 2 LUNI;
* DOCUMENTATIA CADASTRALA PENTRU HG DE EXPROPRIERI DE UTILITATE PUBLICA;
MAI SUNT DE OBTINUT:
* AUTORIZATIA DE CONSTRUIRE SI HG DE EXPROPRIERI DE UTILITATE PUBLICA;
* AVIZ CTE DRDP BUCURESTI PENTRU FAZA DE;
IN DATA DE 25.06.2021 CA URMARE A SOLICITARII CNAIR - DEPARTAMENT OBTINERE FINANTARI PRIN ADRESA NR. 3B/ 2737/25.06.2021, DRDP BUCURESTI A INAINTAT DOCUMENTATIILE TEHNICE IN FAZELE SF - FINAL AVIZAT, PT + DTAC IN VARIANTA INAINTATA LA CTE
CNAIR, PENTRU A FI PUSE LA DISPOZITIA CONSILIULUI JUDETEAN GIURGIU PENTRU INCHEIEREA UNUI PARTENERIAT PENTRU IMPLEMENTAREA OBIECTIVULUI IN TEMEIUL OUG NR. 101/2020.
IN DATA DE 31.08.2021 S-A TRANSMIS LA DRDP BUCURESTI DOCUMENTUL DE AVIZARE EMIS DE COMISIA DE SIGURANTA CIRCULATIEI DIN CADRUL CNAIR CU NR. 92/61651/27.07.2021 CE A FOST INREGISTRAT CU NR. 8/31123/31.08.2021.
IN DATA DE 16.09.2021 S-A TRANSMIS LA DRDP BUCURESTI AVIZUL CTE CNAIR PENTRU FAZA PT+DTAC CU NR. 5094/01.09.2021.
2VARIANTE OCOLITOARE IN PREGATIRE
FAZA SF/PT/DTACVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
RAMNICU VALCEA0+000 21+837 SC SEARCH CORPORATION SRL RAMNICU VALCEA PROIECTARE 21.84 30% 0% 16.12.2019 2022
276.36 MIL. LEI
FARA TVA
CONTRACT DE SERVICII DE PROIECTARE ACTUALIZARE A STUDIULUI INITIAL INCLUSIV DOCUMENTATII PENTRU AVIZE,OBTINERE AVIZE SI ACORDURI, ELABORARE PROIECT TEHNIC INCLUSIV DTAC, DETALII DE EXECUTIE SI ASISTENTA TEHNICA PENTRU OBIECTIVUL VARIANTA
DE OCOLIRE RM. VALCEA NR. 148 /04.10.2019, CU ORDIN DE INCEPERE ACTIVITATI EMIS IN DATA DE 16.12.2019, IN DERULARE. PRESTATOR SC SEARCH CORPORATION SRL.
VALOAREA CONTRACT PROIECTARE: 3,832,075.75 LEI FARA TVA.
DOCUMENT DE AVIZARE CTE-CNAIR NR. 4915/09.04.2020 - ACTUALIZARE SF - ALTERNATIVE DE TRASEU.
CERTIFICATUL DE URBANISM NR. 12/10054/06.08.2020 EMIS DE C.J. VALCEA ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARIEI ORASULUI CALIMANESTI.
DOCUMENT DE AVIZARE CTE-CNAIR NR. 4992/19.10.2020 - ACTUALIZARE SF - ALTERNATIVE DE TRASEU (AMC ETAPA 4) - VARIANTE PENTRU RACORDAREA LA CENTURA CALIMANESTI.
C.J. VALCEA A EMIS UN NOU CERTIFICAT DE URBANISM, NR. 70/16141/23.11.2020, CARE SPECIFICA FAPTUL CA ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARULUI COMUNEI DAESTI.
DOCUMENT DE AVIZARE CTE-DRDP CRAIOVA NR. 3/20.01.2021 - STUDIUL ALTERNATIVELOR DE TRASEU IN ZONA LOCALITATII FEDELESOIU, COMUNA DAESTI - ETAPA 5. DOCUMENTATIA TEHNICA A FOST INAINTATA LA CJ VALCEA CARE A EMIS CERTIFICATUL DE URBANISM
NR. 05/19899/26.01.2021 CARE ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARULUI COMUNEI DAESTI. S-A EMIS
ORDIN DE SISTARE DIN DATA DE 29.01.2021. AU FOST INITIATE DEMERSURI IN VEDEREA ADRESARII INSTANTELOR JUDECATORESTI COMPETENTE PENTRU CHEMARE IN JUDECATA A C.J. VALCEA SI A REPREZENTANTULUI UAT DAESTI.
3VARIANTE OCOLITOARE IN PREGATIRE
FAZA SF/PT/DTACVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
REGHIN0+000 10+440 SC TPF INGINERIE SRL REGHIN 1 10.44 05.12.2019 2021
108.11 MIL. LEI
FARA TVA
CONTRACT PRESTARI SERVICII COMPLETARE STUDIU DE FEZABILITATE SEMNAT LA DATA DE 05.12.2019, IN DERULARE.
CONTRACT COMPLETARE SF IN DERULARE - FINALIZARE 2021
VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE LUCRARI - OCTOMBRIE 2021
VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC - OCTOMBRIE 2021
4VARIANTE OCOLITOARE IN PREGATIRE
FAZA SF/PT/DTACVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
TARGU MURES0+000 11+643 TARGU MURES
RELICITAREA LUCRARILOR
RAMASE DE EXECUTAT SE VA
REALIZA IN 2 ETAPE:
ETAPA 1: REVIZUIRE PROIECT
TEHNIC
ETAPA 2: LICITATIE LUCRARI
RAMASE DE EXECUTAT,
CORELATE CU PROIECTUL
TEHNIC REVIZUIT
11.643
34.26% -
PROGRES
INREGISTRAT IN
CADRUL
CONTRACTULUI
DE LUCRARI
REZILIAT
37.55% -
PROGRES
FINANCIAR
INREGISTRAT LA
DATA REZILIERII
09.10.2014
(ORDIN DE
INCEPERE
PENTRU
CONTRACTUL
REZILIAT)
ORDIN DE
INCEPERE A
LUCRARILOR -
PENTRU
CONTRACTUL
RELICITAT - VA FI
SPECIFICAT
ULTERIOR
SEMNARII
ACESTUIA
CONTRACT 1
INCETAT PE CALE
AMIABILA IN
29.12.2017
ANUL 2023134.80 MIL. LEI
FARA TVA
COPISA CONSTRUCTORA PIRENAICA SA - CONTRACT REZILIAT
LICITATIE ATRIBUIRE CONTRACT REST LUCRARI RAMASE DE EXECUTAT, CU TERMEN DEPUNERE OFERTE: 26.08.2020
PROCEDURA ANULATA ADMINISTRATIV PENTRU NEDEPUNERE DE OFERTE
DEMERSURILE IN VEDEREA ACTUALIZARII PROIECTULUI TEHNIC SUNT DEMARATE DE CATRE DRDP BRASOV.
IN DATA DE 23.02.2021, A FOST PUBLICAT IN SEAP ANUNTUL NR. CN1029446 CU PRIVIRE LA ACHIZITIA PUBLICA CARE VA AVEA CA SCOP ACTUALIZAREA DOCUMENTATIEI TEHNICE PT+DDE VARIANTA DE OCOLIRE TARGU MURES.
PROCEDURA DE LICITATIE IN DERULARE LA NIVELUL DRDP BRASOV
5VARIANTE OCOLITOARE IN PREGATIRE
FAZA SF/PT/DTACVARIANTA OCOLITOARE
ALTERNATIVA
TECHIRGHIOL0+000 28+833
SC CONSITRANS SRL - CONTRACT
PROIECTARE ELABORARE SF, PT SI
DTAC
TECHIRGHIOL 1 28.833 30% 0% FEBRUARIE 2020 DECEMBRIE 2021 DECEMBRIE 20215.372 MIL. LEI
FARA TVA
"CONTRACTUL PENTRU ELABORARE SF, PT SI DTAC A FOST SEMNAT IN DATA DE 26.07.2019 .
ORDINUL DE INCEPERE A FOST EMIS IN LUNA FEBRUARIE 2020.
STUDIU DE FEZABILITATE FINALIZAT, URMEAZA PARCURGEREA PROCEDURII PRIVIND APROBAREA INDICATORILOR TEHNICO-ECONOMICI (AVIZ CTE CNAIR, AVIZ MT, AVIZ CI SI HG). DUPA EMITEREA HG, TERMENUL CONTRACTUAL PENTRU EMITERE PT ESTE 3 LUNI.
AMC 1+2 A FOST AVIZAT IN CADRUL CTE CNAIR SA.
IN CURS DE FINALIZARE INVESTIGATIILE GEOTEHNICE DE TEREN."
6VARIANTE OCOLITOARE IN PREGATIRE
FAZA SF/PT/DTACVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
VASLUI0+000 14+940
CONTRACT REVIZUIRE SF IN
DERULAREVASLUI 1 14.94 2019 2021
142.8 MIL. LEI
FARA TVA
SF - 2006 (AVIZ MT 36/27/19.03.2007).
CONTRACT REVIZUIRE SF SI ELABORARE PT + DTAC SEMNAT IN LUNA MAI 2019 - IN DERULARE, CU TERMEN DECALAT FINALIZARE OCTOMBRIE 2021
DURATA REVIZUIRE SF – 8 LUNI AVIZ CTE DRDP IASI NR. 16891/19.04.2021 IN AVIZARE LA CTE CNAIR SA
DURATA ELABORARE PT – 6 LUNI
VALOARE CONTRACT PROIECTARE: 1.478.500 LEI
7VARIANTE OCOLITOARE IN PREGATIRE
FAZA SF/PT/DTACVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
HUSI
CONTRACT REVIZUIRE SF IN
DERULARE14.4
8VARIANTE OCOLITOARE IN PREGATIRE
FAZA SF/PT/DTACVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
PITESTI VEST0+000 20+000 TPF INGINERIE SRL PITESTI VEST 20 0% 0%
VALOARE SPF + SF
2.732 MIL LEI
FARA TVA
CONTRACT IN DERULARE.
IN DATA DE 26.04.2021 PRESTATORUL A TRANSMIS STUDIUL DE PREFEZABILITATE CONFORM GRAFICULUI ACTIVITATILOR. AU FOST FORMULATE OBSERVATII ASUPRA DOCUMENTATIE STUDIUL DE PREFEZABILITATE. PRESTATORUL A TRANSMIS SPF-UL REVIZUIT.
A FOST PREDAT STUDIUL DE TRAFIC REVIZUIT. SPF A FOST ANALIZAT IN CADRUL CTE-CNAIR S.A. AU FOST FORMULATE OBSERVATII DE CATRE CTE-CNAIR.
9VARIANTE OCOLITOARE IN PREGATIRE
FAZA SF/PT/DTACVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
DOROHOI0+000 13+900 SC NV CONSTRUCT SRL DOROHOI 13.9 0% 0% 429.22 MII LEI IN CURS DE FINALIZARE STUDIUL DE FEZABILITATE, DUPA APROBARE PUZ DOROHOI
10VARIANTE OCOLITOARE IN PREGATIRE
FAZA SF/PT/DTACVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
TIMISOARA VEST0+000 22+000 SEARCH CORPORATION SRL TIMISOARA 22 18.01.2021 18.04.2022
3.66 MIL. LEI
FARA TVA
CONTRACT IN DERULARE.
IN DATA DE 20.05.2021 FOST AVIZAT IN CTE CNAIR SA - ANALIZA MULTICRITERIALA ETAPA 1.
DOCUMENTATIA AMC ETAPA 2 A FOST PREDATA IN DATA DE 27.08.2021. AU FOST FORMULATE OBSERVATII DIN PARTEA BENEFICIARULUI IN DATA DE 16.09.2021.
NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1VARIANTE OCOLITOARE IN PREGATIRE
FAZA PROIECTAREVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
BISTRITA0+000 15+000 BISTRITA 1 15
2.33 MIL LEI FARA
TVA (VALOARE
ESTIMATA
CONTRACT S.F.)
PROCEDURA DE ACHIZITIE PUBLICA PENTRU CONTRACTUL DE SERVICII DE „ELABORARE STUDIU DE FEZABILITATE PENTRU VARIANTA DE OCOLIRE BISTRITA”, A FOST ANULATA.
OBIECTIVUL FACE PARTE DIN ,,AUTOSTRADA NORDULUI” – FIIND SPECIFICAT IN STUDIUL DE FEZABILITATE CA DRUMUL DE MARE VITEZA BAIA MARE-SUCEAVA: LOT 1 BAIA MARE-BISTRITA SI LOT 2 BISTRITA-VATRA DORNEI, VA INDEPLINI SI FUNCTIA DE VARIANTA DE
OCOLIRE PENTRU LOCALITATILE INTERSECTATE DE ACESTA.
2VARIANTE OCOLITOARE IN PREGATIRE
FAZA PROIECTAREVARIANTA OCOLITOARE
DRUM DE LEGATURA
DN6 - DRUM EXPRES
CRAIOVA-PITESTI
(TRONSONUL 1)
INITIERE PROCEDURA DE ACHIZITIE
ATRIBUIRE CONTRACT DE PRESTARI
SERVICII DE PROIECTARE
10
CNAIR SA A TRANSMIS CATRE MINISTERUL TRANSPORTURILOR SI INFRASTRUCTURII CEREREA DE FINANTARE PENTRU PROIECTUL: """"ELABORARE STUDIU DE FEZABILITATE, PROIECT TEHNIC DE EXECUTIE INCLUSIV PAC, DETALII DE EXECUTIE, ASIGURAREA ASISTENTEI
TEHNICE PE PARCURSUL EXECUTIEI DE LUCRARI SI IN PERIOADA DE GARANTIE A LUCRARILOR EXECUTATE PENTRU OBIECTIVUL DE INVESTITIE: DRUM DE LEGATURA PENTRU SPORIREA CAPACITATII DE TRAFIC INTRE DN6 (ZONA UZINEI FORD) SI DRUMUL EXPRES CRAIOVA –
PITESTI (TRONSONUL 1)"""".
PROCEDURA DE ACHIZITIE IN DERULARE CU O VALOARE ESTIMATA A CONTRACTULUI DE 1.500.000 LEI INCLUSIV TVA. TERMEN LIMITA DE DEPUNERE A OFERTELOR: 08.09.2021. CELE 2 OFERTE DEPUSE SUNT IN ANALIZA.
DURATA ESTIMATA A PRESTARII SERVICIILOR ESTE DE 89 LUNI (3 LUNI – ELABORARE SF INCLUSIV DOCUMENTATII PENTRU OBTINERE AVIZE/ACORDURI; 2 LUNI – ELABORARE PT INCLUSIV DTAC SI DE; 24 LUNI – ASISTENTA TEHNICA PE PARCURSUL EXECUTIEI LUCRARILOR;
60 LUNI – ASISTENTA TEHNICA IN PERIOADA DE GARANTIE A LUCRARILOR).
VARIANTE OCOLITOARE IN PREGATIRE FAZA PROIECTARE - OCTOMBRIE 2021
NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1VARIANTE OCOLITOARE IN
REABILITARE/MODERNIZAREVARIANTA OCOLITOARE CENTURA BUCURESTI 29+500 33+190 ITINERA SPA
LARGIRE LA 4 BENZI A CENTURII
RUTIERE A MUNICIPIULUI
BUCURESTI SUD INTRE A2 KM
23+600 SI A1 KM 55+520
AMENAJARE NOD RUTIER LOT
1: OLTENITA - DN 43.69 31.50% 35.53%
31.07.2019 -
DATA DE
INCEPERE
PERIOADA DE
PROIECTARE
ESTIMAT 2022 SEPTEMBRIE 2022169.5 MIL. LEI
FARA TVA
CONTRACTUL DE EXECUTIE LUCRARI A FOST SEMNAT IN DATA DE 20.06.2019/ AUTORIZATIE DE CONSTRUIRE VALABILA.
LUCRARI IN EXECUTIE:
DRUM - LUCRARI DE EXCAVATIE DN4 SI CB, LUCRARI DE UMPLUTURI, EXECUTIE STRAT DE FORMA, EXECUTIE FUNDATIE DIN BALAST,ASTERNERE STRAT DE BALSAT STABILIZAT.
PASAJ - TURNARE BETON EGALIZARE: 31 DE FUNDATII; TURNARE RADIERE: 31 BUC; EXECUTIE ELEVATII PILE: 27 BUC; EXECUTIE ELEVATII CULEE: 4 BUC; EXECUTIE RIGLE: 9 BUC, ARMARE SI COFRARE 2 BUC, CUZINETI SI ORPITORI SEISMICI SP1A, SP1B SI P2B, P4B, P1B,
COFRARE SI ARMARE RIGLE: P2B1, P3, P5B1, APROVIZIONARE APARATE DE REAZEM.
CONSOLIDARI - RAMPA A1: BETON DE EGALIZARE RAMPA A1; RADIERE BETONATE ZID TIP L – 7 BUC; ELEVATII BETONATE ZID TIP L – 6 BUC, EXCAVATIE SEGMENT 2 ZID TIP U, RADIER BETONAT SEGMENT 1 TIP U, ELEVATII BETONATE SEGMENT 1 TIP U; RAMPA A:
EXCAVATIE PRIMUL ZID TIP L, BETON DE EGALIZARE ZID TIP L – 7 BUC, RADIERE ZID TIP L, 7 SEGMENTE; ELEVATII ZID TIP L – 4 BUC.
RAMPA B: EXECUTATA IN PROPORTIE DE 90 %; MONTARE GEODREN, BETON DE PANTA PE ZIDUL TIP L; RAMPA B1: EXECUTATA IN PROPORTIE DE 75 %; RAMPA BUCURESTI: EXCAVATIE ZID DE SPRIJIN TIP L; BETON DE EGALIZARE; RADIERE BETONATE; ELEVATII BETONATE;
RAMPA OLTENITA: RADIERE BETONATE ZID DE SPRIJIN TIP L; BETON DE EGALIZARE; RADIERE BETONATE; ELEVATII BETONATE
RETELE DE UTILITATI - RETEA DE DISTRIBUTIE GAZE NATURALE – INTREGIRE CONDUCTA NOUA DN CB SI BRANSAMENTE NOI, S-A DEVIAT RETEAUA PE NOUL TRASEU PE DN4, KM 1+140 LA KM 1+580, SE PREGATESTE O NOUA CUPLARE PE DN4; RETEA DE TELECOMUNICATII
– FINALIZATA, TREBUIE INTOCMIT PV LA TERMINAREA LUCRARILOR; RETEA E-DISTRIBUTIE – S-AU DEVIAT TRASEELE JT ANTENA VODAFONE SI REMAT SI TRASEU MT 20 kV – PORCINE 1, SE MONTEAZA CABLURILE PE DN 4, PE TRASEELE DE MEDIE TENSIUNE.
RETEA DE CANALIZARE PLUVIALA - RETEA DN 4, REALIZAT APROXIMATIV 2600 M, 83,00%; RETEA CB, REALIZAT APROXIMATIV 1260 M, 32,12 %.
2VARIANTE OCOLITOARE IN
REABILITARE/MODERNIZAREVARIANTA OCOLITOARE CENTURA BUCURESTI 12+300 23+750 TIRRENA SCAVI S.P.A
MODERNIZAREA CENTURII RUTIERE
A MUNICIPIULUI BUCURESTI INTRE
A1 - DN7 SI DN2 - A2
SECTIUNEA DN 2 - A2 11.524 11.28% 17.77% 04.05.2020 ESTIMAT 2022 ANUL 2022235.75 MIL. LEI
FARA TVA
1. CONTRACTUL DE EXECUTIE LUCRARI A FOST SEMNAT IN DATA DE 02.03.2020/ AUTORIZATIE DE CONSTRUIRE VALABILA.
LUCRARI IN EXECUTIE: 3000 MP CURATARE AMPLASAMENT; 2250 MC DECAPARE PAMANT VEGETAL; 2400 MC SAPATURA CORP DRUM; 800 MC UMPLUTURI TERASAMENTE; 500 M RIGOLA DREPTUNGHIULARA; 600 MC STRAT DE FORMA DIN BALAST; 650 MC STRAT DE
FUNDATIE DIN BALAST; 25 MP COFRARE PILE; 3 TONE ARMATURA ELEVATII PASAJE; 10 MC BETONARE ELEVATII PASAJE; 500 M PILOTI DE INDESARE; ACTIVITATI GENERALE.
3VARIANTE OCOLITOARE IN
REABILITARE/MODERNIZAREVARIANTA OCOLITOARE CENTURA BUCURESTI 33+190 35+600
ASOCIEREA S.C. TRAMECO S.A. -
VAHOSTAV -SK, A.S. - CONSTRUCTII
ERBASU S.A. - GRAFIC TENDS S.R.L.
S.C. (LIDER DE ASOCIERE TRAMECO
S.A.)
LARGIRE LA 4 BENZI A CENTURII
RUTIERE A MUNICIPIULUI
BUCURESTI SUD INTRE A2 KM
23+600 SI A1 KM 55+520
AMENAJARE NOD RUTIER LOT
2: BERCENI - DJ 4012.41 33.57% 20.27% 06.05.2019 ESTIMAT 2022 IUNIE 2022
146 MIL. LEI FARA
TVA
CONTRACTUL DE PROIECTARE SI EXECUTIE PASAJ BERCENI A FOST SEMNAT IN DATA DE 19.03.2019.
ORDIN DE INCEPERE PROIECTARE: 06.05.2019
ORDIN DE INCEPERE EXECUTIE:
23.06.2020 - etapa 1; 10.08.2020 - etapa 2; 21.09.2020 - etapa 3; 06.06.2021 – etapa 4
AUTORIZATIE DE CONSTRUIRE:
AC nr. 27/12.06.2020 - etapa 1; AC 37/30.07.2020 - etapa 2; AC 52/10.09.2020 - etapa 3;
AC nr. 24/31.05.2021
FAZA PROIECTULUI: IN CURS DE EXECUTIE LUCRARI
4VARIANTE OCOLITOARE IN
REABILITARE/MODERNIZAREVARIANTA OCOLITOARE CENTURA BUCURESTI 55+465 64+160
ASOCIEREA S.C. DELTA A.C.M. 93 SRL
& AZVIRT LLC & S.C. MAXIDESIGN
S.R.L. - CONTRACT REZILIAT
MODERNIZAREA CENTURII RUTIERE
A MUNICIPIULUI BUCURESTI INTRE
A1 - DN 7 SI DN 2-A2:SECTIUNEA A1
(KM 55+465) - DN 7 (KM 64+160)
SECTIUNEA A1 KM 55+465 -
DN7 KM 64+1608.695
86.5% - PROGRES
FIZIC LA DATA
REZILIERII
77.73% -
PROGRES
FINANCIAR LA
DATA REZILIERII
2021 TRIM IV 2022106.6 MIL. LEI
FARA TVA
A FOST DEMARATA PROCEDURA DE ACHIZITIE PUBLICA PENTRU LUCRARI DE REMEDIERE SI FINALIZARE LUCRARI - REST DE EXECUTAT.
A FOST PUBLICAT ANUNTUL DE PARTICIPARE.
DETALII IN LINK-UL DE MAI JOS:
5VARIANTE OCOLITOARE IN
REABILITARE/MODERNIZAREVARIANTA OCOLITOARE CENTURA BUCURESTI SC STRABAG SRL
PROIECTARE SI EXECUTIE PASAJ
MOGOSOAIA PE CENTURA
BUCURESTI PESTE DN 1A
MOGOSOAIA/ DN 1A 0.8 97.00% 39.00%
04.12.2018 -
PROIECTARE;
02.04.2020 -
EXECUTIE
2021- CONFORM
ASUMARI
ANTREPRENOR
ANUL 2022 CONFORM
GRAFIC CONTRACT
32.26 MIL. LEI
FARA TVATRAFICUL A FOST DESCHIS IN DATA DE 30.09.2021
6VARIANTE OCOLITOARE IN
REABILITARE/MODERNIZAREVARIANTA OCOLITOARE CENTURA BUCURESTI
PENETRATIE PRELUNGIREA
GHENCEA – DOMNESTI SI
SUPRALARGIRE BULEVARDUL
GHENCEA INTRE STRADA BRASOV SI
TERMINAL TRAMVAI 41” CU
PROIECTUL “PASAJ SUPRATERAN PE
DJ 602, CENTURA BUCURESTI -
DOMNESTI
1.1
139.255 MII lei
FARA TVA -
VALOARE
PROIECTARE
CAIET DE SARCINI, APROBAT
REFERAT DE NECESITATE,
PAAP APROBAT 02.02.2021
PUBLICAT IN SEAP 05.03.2021
DESCHIDEREA OFERTELOR 08.04.2021
NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1VARIANTE OCOLITOARE - PROIECTE IN
COLABORARE CU AUTORITATILE LOCALEVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
ALESD0+000 16+840 ALESD 16.84
OBIECTIVUL A FOST TRANSFERAT CATRE CJ BIHOR IN VEDEREA REVIZUIRII DOCUMENTATIEI TEHNICE SI IMPLEMENTARII ACESTUIA IN BAZA OUG 101/2020.
DECEMBRIE 2020 - A FOST SEMNAT UN PARTENERIAT INTRE CNAIR SI CJ BIHOR IN ACEST SENS
IN DATA DE 20.05.2021 A FOST AVIZAT IN CADRUL CTE CNAIR SA STUDIUL DE FEZABILITATE.
IN DATA DE 21.05.2021 A FOST AVIZAT IN CADRUL CTE MTI STUDIUL DE FEZABILITATE
IUNIE 2021- URMEAZA AVIZAREA IN CADRUL CTE IM SI PROMOVAREA HG DE APROBARE A INDICATORILOR TEHNICO ECONOMICI
2VARIANTE OCOLITOARE - PROIECTE IN
COLABORARE CU AUTORITATILE LOCALEVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
IASI
19+690
(SELGROS)
26+460
(DN28)
ETAPA I – VARIANTA SUD OBIECT 3 –
VARIANTA TRAFIC GREU6.77
126.88 MIL. LEI
FARA TVA
(VALOARE
ESTIMATA)
PENTRU IMPLEMENTAREA ACESTUI OBIECTIV PRIMARIA MUNICIPIULUI IASI A INAINTAT O PROPUNERE DE SCHIMBARE A TRASEULUI, CA URMARE A IMPOSIBILITATII PASTRARII TRASEULUI PE BULEVARDUL POITIERS SI STRADA TREI FANTANI (KM 19+690 - KM 26+460).
PROPUNEREA A FOST ACCEPTATA DE CNAIR, URMAND A SE IDENTIFICA SURSA DE FINANTARE.
3VARIANTE OCOLITOARE - PROIECTE IN
COLABORARE CU AUTORITATILE LOCALEVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
MEDIAS0+000 8+500 MEDIAS 1 8.5 2022 2024
PENTRU IMPLEMENTAREA ACESTUI OBIECTIV A FOST SEMNAT UN PARTENERIAT DE IMPLEMENTARE INTRE CNAIR SA SI PRIMARIA MEDIAS IN BAZA PREVEDERILOR OUG 101/2020.
OBIECTIVUL SE IMPLEMENTEAZA DE CATRE UAT MEDIAS.
A FOST SEMNAT CONTRACTUL DE REVIZUIRE A STUDIULUI DE FEZABILITATE DE CATRE PRIMARIA MEDIAS IN LUNA IUNIE 2021.
A FOST EMIS ORDINUL DE INCEPERE IN DATA DE 10.06.2021 - TERMEN PENTRU EMITEREA RAPORTULUI DE INCEPUT- 31.07.2021
4VARIANTE OCOLITOARE - PROIECTE IN
COLABORARE CU AUTORITATILE LOCALEVARIANTA OCOLITOARE
VARIANTA OCOLITOARE
STEI0+000 27+230
COPISA CONSTRUCTORA PIRENAICA
SA - CONTRACT REZILIAT LICITATIE
ATRIBUIRE CONTRACT REST LUCRARI
RAMASE DE EXECUTAT, CU TERMEN
DEPUNERE OFERTE : 22.06.2020
STEI 1 27.23 0% 0%
CONTRACT
REZILIAT DE
CATRE
ANTREPRENOR
CONTRACT
REZILIAT DE
CATRE
ANTREPRENOR
CONTRACT REZILIAT DE
CATRE ANTREPRENOR
257.413 MIL. LEI
FARA TVA
OBIECTIVUL A FOST TRANSFERAT CATRE CJ BIHOR IN VEDEREA REVIZUIRII DOCUMENTATIEI TEHNICE SI IMPLEMENTARII ACESTUIA IN BAZA OUG 101/2020.
A FOST SEMNAT IN LUNA DECEMBRIE 2020, PARTENERIATUL INTRE CNAIR SI CJ BIHOR IN ACEST SENS.
CONTRACT REVIZUIRE STUDIU DE FEZABILITATE IN DERULARE - ESTIMAT FINALIZARE TRIM. III 2021
VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE LOCALE - OCTOMBRIE 2021
VARIANTE OCOLITOARE IN REABILITARE / MODERNIZARE - OCTOMBRIE 2021
NR.
CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)
PÂNĂ LA
(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)
STADIUL FIZIC
ACTUAL
STADIUL
FINANCIAR
ACTUAL
DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE
PROIECTOBSERVAȚII
1 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOAREVARIANTA OCOLITOARE
RADAUTI0+000 16+580
SPEDITION UMB - SC TEHNOSTRADE
SRLRADAUTI 1 16.58 08.10.2018 20.11.2020 ANUL 2020
97.44 MIL. LEI
FARA TVA
LUCRARI FINALIZATE - 20.11.2020
PENTRU ACEST PROIECT A FOST FINALIZAT PROCESUL DE ACCESARE A FINANTARII NERAMBURSABILE ALOCATE IN CADRUL POIM 2014-2020, FIIND EMISA NOTA DE APROBARE A FINANTARII ACESTUIA DIN FONDURI NERAMBURSABILE IN LUNA DEC. 2020.
CONTRACT DE FINANTARE A LUCRARILOR EXECUTATE IN CADRUL POIM 2014-2020 SEMNAT IN LUNA IANUARIE 2021
2 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOAREVARIANTA OCOLITOARE
SACUENI0+000 7+620
SC ANTREPRIZA DE REPARATII SI
LUCRARI ARL CLUJ SASACUENI 7.62 10.09.2019 12.08.2020 DECEMBRIE 2020
42.83 MIL. LEI
FARA TVA
LUCRARILE AU FOST FINALIZATE SI VARIANTA DE OCOLIRE SACUENI ESTE IN DATA IN CIRCULATIE INCEPAND CU 09.12.2020.
MOMENTAN SE AFLA IN PROCEDURA DE RECEPTIE LA TERMINAREA LUCRARILOR, LA DATA DE 15.09.2021 FIIND EMISA DECIZIA DIRECTORULUI GENERAL AL C.N.A.I.R.S.A. NR.1413/15.09.2021 PRIN CARE ESTE NUMITA COMISIA PENTRU EFECTUAREA R.T.L. S-A STABILIT
DATA LA CARE SE VA EFECTUA RECEPTIA LA TERMINAREA LUCRARILOR: 29.09.2021
3 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOAREVARIANTA OCOLITOARE
SUCEAVA0+000 7+285
ASOCIEREA S.C. AUTOTEHNOROM
S.R.L. (LIDER) – S.C. OPERATIONAL
AUTOLEASING S.R.L. – S.C. OPR
ASFALT S.R.L. – OBRAS PUBLICAS Y
REGADIOS S.A. – S.C.
FLORCONSTRUCT S.R.L. – S.C.
CALCARUL S.A.
SUCEAVA 1 7.285
DESCHISA
TRAFICULUI - IN
DATA DE 27 SEPT.
2019
77% 01.10.2018
OCTOMBRIE 2021
- RECEPTIE LA
TERMINAREA
LUCRARILOR
OCTOMBRIE 2028
- RECEPTIE FINALA
OCTOMBRIE 2021 -
FINALIZARE LUCRARI
AUXILIARE
63.85 MIL. LEI
FARA TVA
4 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOAREVARIANTA OCOLITOARE
CARACAL - RELICITARE0+000 10+345
ASOCIEREA SECOL S.A. - S.E.C.O.L
S.P.A.CARACAL 10.345 100% 97.05% 16.10.2014 RTL: 24.05.2018
41.69 MIL. LEI
FARA TVA
24.05.2018 - A FOST REALIZATA RTL
IN DATA DE 10.11.2020 A FOST REALIZATA RECEPTIA FINALA
5 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOAREVARIANTA OCOLITOARE
BRASOV0+000 7+292
ASOCIEREA CHIRULLI ANDREA
IMPRESA INDIVIDUALE - ALEANDRI
SPA - SMART BUILDING PROJECT-
PASQUALE ALO' SRL
TRONSON I, DN1 - DN 11 LOT 1 - RELICITARE 100% 98.56% 16.12.2014RTL: 28.11.2016;
RF:19.12.2019
59.56 MIL. LEI
FARA TVA
IN DATA DE 29.11.2016 A AVUT LOC RECEPTIA LA TERMINAREA LUCRARILOR. LA DATA PREZENTEI CONTRACTUL SE AFLA IN PERIOADA DE NOTIFICARE A DEFECTIUNILOR.
IN DATA DE 19.12.2019 A FOST APROBAT PROCESUL VERBAL DE RECEPTIE FINALA.
6 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOAREVARIANTA OCOLITOARE
BRASOV0+000 4+924
ASOCIEREA SC VIAROM CONSTRUCT
SA - SC BETA COPS SRL - SC
MAXIDESIGN SRL
TRONSON II, DN11 - DN13 LOT 3 4.924 100% 98.77% 07.08.2014
RECEPTIE LA
TERMINAREA
LUCRARILOR:
29.11.2019
64.42 MIL. LEI
FARA TVAPROCESUL VERBAL DE RECEPTIE LA TERMINAREA LUCRARILOR A FOST APROBAT DE DIRECTORUL GENERAL AL CNAIR IN DATA DE 29.11.2019.
VARIANTE OCOLITOARE IN FOLOSINTA - OCTOMBRIE 2021