NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PÂNĂ LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII 1 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA 30+550 59+100 ASOCIEREA TRAMECO SA – VAHOSTAV -SK A.S. – DRUMURI BIHOR SA – DRUM ASFALT SRL – EAST WATER DRILLINGS SRL SECTIUNEA 3C, SUBSECTIUNEA 3C2 CHIRIBIS - BIHARIA SUBSECTIUNEA 3C2: CHIRIBIS - BIHARIA 28.55 0.50% 0% 14.09.2020 - EMITERE ORDIN DE INCEPERE PENTRU ETAPA DE PROIECTARE (PROIECT TEHNIC) MARTIE 2022 (CONFORM CONTRACT) IUNIE 2022 (CONFORM PROGRAM) ANUL 2022 6 LUNI - ETAPA DE PROIECTARE; 18 LUNI - ETAPA DE EXECUTIE LUCRARI; 120 LUNI - PERIOADA DE GARANTIE 326.51 MIL. LEI FARA TVA CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 11.08. 2020. A FOST TRANSMISA CATRE ANTREPRENOR ADRESA CU ORDINUL DE INCEPERE PENTRU DATA DE 14.09.2020. A FOST ACORDAT DREPTUL DE ACCES IN SANTIER ANTREPRENORULUI. DURATA CONTRACTULUI ESTE DE 144 DE LUNI DIN CARE: 6 LUNI - ETAPA DE PROIECTARE; FINALIZARE PUNCT DE REFERINTA NR. 1 IN 09.11.2020. 18 LUNI - ETAPA DE EXECUTIE LUCRARI 120 LUNI - PERIOADA DE GARANTIE 2 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA 8+700 38+760 ASOCIEREA S.C. SPEDITION UMB S.R.L. – S.C. TEHNOSTRADE S.R.L. – S.C. ELECTROMONTAJ S.A SECTIUNEA 3A SI SECTIUNEA 3B, SUBSECTIUNEA 3A2: NADASELU - MIHAIESTI SI 3B1: MIHAESTI ZIMBOR SUBSECTIUNEA 3A2 NADASELU - MIHAIESTI KM 8+700 - 25+500+ 3B1, MIHAIESTI – ZIMBOR KM 0+000 - 13+260 30.06 0% 0% 25.01.2021 2023 ANUL 2023 1.390,614 MIL. LEI FARA TVA SEMNARE CONTRACT PROIECTARE SI EXECUTIE IN DATA DE 28.12.2020. PRETUL PE KM DE AUTOSTRADA ESTE DE CCA. 46,261,293.92 LEI FARA TVA, REPREZENTAND CCA. 9,383,629 EURO FARA TVA. DURATA CONTRACTULUI ESTE DE 96 DE LUNI, DIN CARE: • 12 LUNI PERIOADA DE PROIECTARE, • 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR, • 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR. AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3A2 IN LUNA APRILIE 2021. AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3B1 IN 01.07.2021 PROIECT TEHNIC DE EXECUTIE PENTRU 3A2 AVIZAT IN CTE - CNAIR IN DATA DE 20.08.2021 PROIECT TEHNIC IN CURS DE ELABORARE PENTRU 3B1 - TERMEN ESTIMAT AVIZARE PROIECT TEHNIC: DEC. 2021 3 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA 66+500 80+054 NUROL INSAAT VE TICARET S.A SECTIUNEA 3B, SUBSECTIUNEA 3B5 NUSFALAU - SUPLACU DE BARCAU SUBSECTIUNEA 3B5: NUSFALAU - SUPLACU DE BARCAU 13.55 4.34% 15.75% 01.02.2021 FEBRUARIE 2023 FEBRUARIE 2023 384.14 MIL. LEI FARA TVA CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN 30.09.2020; 6 LUNI PERIOADA DE PROIECTARE ; 18 LUNI PERIOADA DE EXECUTIE ; 120 LUNI PERIOADA DE GARANTIE LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 12 STRUCTURI (4 PASAJE SI 8 PODURI), RESPECTIV UN NOD RUTIER LA KM 67+500 FINALIZARE ETAPA PROIECTARE (PTE) - PROIECTUL TEHNIC DE EXECUTIE A FOST AVIZAT IN CADRUL CTE IN DATA DE 02.08.2021 4 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA 13+260 25+500 ASOCIEREA SC SA&PE CONSTRUCT SRL - SC SPEDITION UMB SRL - SC TEHNOSTRADE SRL SECTIUNEA 3B, SUBSECTIUNEA 3B2: ZIMBOR - POARTA SALAJULUI SUBSECTIUNEA 3B2: ZIMBOR - POARTA SALAJULUI 12.24 0% 0% 31.05.2021 - ORDIN DE INCEPERE 2023 ANUL 2023 680.40 MIL. LEI FARA TVA CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 01.07.2020; DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE: 12 LUNI PERIOADA DE PROIECTARE, 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR, 120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR A FOST CONSTITUITA GARANTIA DE BUNA EXECUTIE A LUCRARILOR, ORDINUL DE INCEPERE A LUCRARILOR EMIS PENTRU DATA DE 31.05.2021 5 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA 0+000 4+500 S.C. STRABAG S.R.L. SECTOR 1C: TG. MURES - OGRA LOT 1 - TARGU MURES - UNGHENI (4.5 KM) + DRUM DE LEGATURA (4.7 KM) 9.2 79.50% 63.87% ORDIN DE INCEPERE PENTRU EXECUTIE - 22 IULIE 2020 2022 (CONFORM CONTRACT) 2021 - CONFORM ESTIMARE ANTREPRENOR/ CNAIR SA ANUL 2022 192.06 MIL. LEI FARA TVA 1. CONTRACT DE EXECUTIE SEMNAT IN DATA DE 29.05.2020. 2. AUTORIZATIE DE CONSTRUIRE VALABILA PENTRU ACEST SECTOR. 3. DURATA DE REALIZARE A ACESTUI CONTRACT ESTE URMATOAREA: 18 LUNI - PERIOADA DE EXECUTIE A LUCRARILOR; 108 LUNI (9 ANI) - PERIOADA DE GARANTIE A LUCRARILOR; LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 3 PODURI SI PASAJE PE DRUMURI DE LEGATURA, 6 PODURI SI PASAJE PE AUTOSTRADA, PRECUM SI DOUA NODURI RUTIERE PENTRU CONECTAREA AUTOSTRAZII LA RETEAUA DE DRUMURI EXISTENTA. 6 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA DE CENTURA A MUNICIPIULUI BUCURESTI (A0) 47+600 52+070 ASOCIEREA S.C. SA&PE CONSTRUCT S.R.L. - S.C. SPEDITION UMB S.R.L. - S.C. TEHNOSTRADE S.R.L. SECTOR NORD LOT 4 4.47 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024 312.63 MIL. LEI FARA TVA IN DATA DE 17.05.2020, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL "PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 4 KM 47+600 - KM 52+070”, CU OFERTANTUL DECLARAT CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L. VALOAREA CONTRACTULUI: 312.633.554,09 LEI FARA TVA. LUNGIME: 4.47 KM SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE. DURATA CONTRACTULUI ESTE DE 150 LUNI, DIN CARE: 12 LUNI PERIOADA DE PROIECTARE, 18 LUNI PERIOADA DE EXECUTIE A LUCRARILOR 120 LUNI PERIOADA DE GARANTIE A LUCRARILOR 7 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA DE CENTURA A MUNICIPIULUI BUCURESTI (A0) 20+000 39+000 ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L. SECTOR NORD LOT 2 19 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024 831.92 MIL. LEI FARA TVA IN DATA DE 12.05.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL "PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 2 KM 20+000 - KM 39+000”, CU OFERTANTUL DECLARAT CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L. VALOAREA CONTRACTULUI: 831.920.653,34 LEI FARA TVA. LUNGIME: 19 KM SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE. DURATA CONTRACTULUI ESTE DE 154 LUNI, DIN CARE: 12 LUNI PERIOADA DE PROIECTARE, 22 LUNI PERIOADA DE EXECUȚIE A LUCRĂRILOR 120 LUNI PERIOADA DE GARANȚIE A LUCRĂRILOR A FOST EMIS ORDIN DE INCEPERE IN DATA DE 16.08.2021 AUTOSTRĂZI SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - OCTOMBRIE 2021 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI - OCTOMBRIE 2021
Transcript
Page 1: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA BRASOV -

TARGU MURES - CLUJ -

ORADEA

30+550 59+100

ASOCIEREA TRAMECO SA –

VAHOSTAV -SK A.S. – DRUMURI

BIHOR SA – DRUM ASFALT SRL –

EAST WATER DRILLINGS SRL

SECTIUNEA 3C, SUBSECTIUNEA 3C2

CHIRIBIS - BIHARIA

SUBSECTIUNEA 3C2: CHIRIBIS -

BIHARIA28.55 0.50% 0%

14.09.2020 -

EMITERE ORDIN

DE INCEPERE

PENTRU ETAPA

DE PROIECTARE

(PROIECT TEHNIC)

MARTIE 2022

(CONFORM

CONTRACT)

IUNIE 2022

(CONFORM

PROGRAM)

ANUL 2022 6 LUNI - ETAPA

DE PROIECTARE; 18 LUNI -

ETAPA DE EXECUTIE

LUCRARI; 120 LUNI -

PERIOADA DE GARANTIE

326.51 MIL. LEI

FARA TVA

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 11.08. 2020.

A FOST TRANSMISA CATRE ANTREPRENOR ADRESA CU ORDINUL DE INCEPERE PENTRU DATA DE 14.09.2020. A FOST ACORDAT DREPTUL DE ACCES IN SANTIER ANTREPRENORULUI.

DURATA CONTRACTULUI ESTE DE 144 DE LUNI DIN CARE:

6 LUNI - ETAPA DE PROIECTARE; FINALIZARE PUNCT DE REFERINTA NR. 1 IN 09.11.2020.

18 LUNI - ETAPA DE EXECUTIE LUCRARI

120 LUNI - PERIOADA DE GARANTIE

2AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA BRASOV -

TARGU MURES - CLUJ -

ORADEA

8+700 38+760

ASOCIEREA S.C. SPEDITION UMB

S.R.L. – S.C. TEHNOSTRADE S.R.L. –

S.C. ELECTROMONTAJ S.A

SECTIUNEA 3A SI SECTIUNEA 3B,

SUBSECTIUNEA 3A2: NADASELU -

MIHAIESTI SI 3B1: MIHAESTI ZIMBOR

SUBSECTIUNEA 3A2

NADASELU - MIHAIESTI KM

8+700 - 25+500+ 3B1,

MIHAIESTI – ZIMBOR KM

0+000 - 13+260

30.06 0% 0% 25.01.2021 2023 ANUL 20231.390,614 MIL.

LEI FARA TVA

SEMNARE CONTRACT PROIECTARE SI EXECUTIE IN DATA DE 28.12.2020. PRETUL PE KM DE AUTOSTRADA ESTE DE CCA. 46,261,293.92 LEI FARA TVA, REPREZENTAND CCA. 9,383,629 EURO FARA TVA.

DURATA CONTRACTULUI ESTE DE 96 DE LUNI, DIN CARE:

• 12 LUNI PERIOADA DE PROIECTARE,

• 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,

• 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.

AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3A2 IN LUNA APRILIE 2021.

AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3B1 IN 01.07.2021

PROIECT TEHNIC DE EXECUTIE PENTRU 3A2 AVIZAT IN CTE - CNAIR IN DATA DE 20.08.2021

PROIECT TEHNIC IN CURS DE ELABORARE PENTRU 3B1 - TERMEN ESTIMAT AVIZARE PROIECT TEHNIC: DEC. 2021

3AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA BRASOV -

TARGU MURES - CLUJ -

ORADEA

66+500 80+054 NUROL INSAAT VE TICARET S.ASECTIUNEA 3B, SUBSECTIUNEA 3B5

NUSFALAU - SUPLACU DE BARCAU

SUBSECTIUNEA 3B5:

NUSFALAU - SUPLACU DE

BARCAU

13.55 4.34% 15.75% 01.02.2021 FEBRUARIE 2023 FEBRUARIE 2023384.14 MIL. LEI

FARA TVA

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN 30.09.2020;

6 LUNI PERIOADA DE PROIECTARE

; 18 LUNI PERIOADA DE EXECUTIE

; 120 LUNI PERIOADA DE GARANTIE

LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 12 STRUCTURI (4 PASAJE SI 8 PODURI), RESPECTIV UN NOD RUTIER LA KM 67+500

FINALIZARE ETAPA PROIECTARE (PTE) - PROIECTUL TEHNIC DE EXECUTIE A FOST AVIZAT IN CADRUL CTE IN DATA DE 02.08.2021

4AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA BRASOV -

TARGU MURES - CLUJ -

ORADEA

13+260 25+500

ASOCIEREA SC SA&PE CONSTRUCT

SRL - SC SPEDITION UMB SRL - SC

TEHNOSTRADE SRL

SECTIUNEA 3B, SUBSECTIUNEA 3B2:

ZIMBOR - POARTA SALAJULUI

SUBSECTIUNEA 3B2: ZIMBOR -

POARTA SALAJULUI12.24 0% 0%

31.05.2021 -

ORDIN DE

INCEPERE

2023 ANUL 2023680.40 MIL. LEI

FARA TVA

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 01.07.2020;

DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE:

12 LUNI PERIOADA DE PROIECTARE,

24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,

120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR

A FOST CONSTITUITA GARANTIA DE BUNA EXECUTIE A LUCRARILOR, ORDINUL DE INCEPERE A LUCRARILOR EMIS PENTRU DATA DE 31.05.2021

5AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA BRASOV -

TARGU MURES - CLUJ -

ORADEA

0+000 4+500 S.C. STRABAG S.R.L. SECTOR 1C: TG. MURES - OGRA

LOT 1 - TARGU MURES -

UNGHENI (4.5 KM) + DRUM

DE LEGATURA (4.7 KM)

9.2 79.50% 63.87%

ORDIN DE

INCEPERE

PENTRU EXECUTIE

- 22 IULIE 2020

2022 (CONFORM

CONTRACT)

2021 -

CONFORM

ESTIMARE

ANTREPRENOR/

CNAIR SA

ANUL 2022192.06 MIL. LEI

FARA TVA

1. CONTRACT DE EXECUTIE SEMNAT IN DATA DE 29.05.2020.

2. AUTORIZATIE DE CONSTRUIRE VALABILA PENTRU ACEST SECTOR.

3. DURATA DE REALIZARE A ACESTUI CONTRACT ESTE URMATOAREA:

18 LUNI - PERIOADA DE EXECUTIE A LUCRARILOR;

108 LUNI (9 ANI) - PERIOADA DE GARANTIE A LUCRARILOR;

LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 3 PODURI SI PASAJE PE DRUMURI DE LEGATURA, 6 PODURI SI PASAJE PE AUTOSTRADA, PRECUM SI DOUA NODURI RUTIERE PENTRU CONECTAREA AUTOSTRAZII LA RETEAUA

DE DRUMURI EXISTENTA.

6AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA DE

CENTURA A

MUNICIPIULUI

BUCURESTI (A0)

47+600 52+070

ASOCIEREA S.C. SA&PE CONSTRUCT

S.R.L. - S.C. SPEDITION UMB S.R.L. -

S.C. TEHNOSTRADE S.R.L.

SECTOR NORD LOT 4 4.47 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024312.63 MIL. LEI

FARA TVA

IN DATA DE 17.05.2020, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL "PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 4 KM 47+600 - KM 52+070”, CU OFERTANTUL DECLARAT

CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.

VALOAREA CONTRACTULUI: 312.633.554,09 LEI FARA TVA.

LUNGIME: 4.47 KM

SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE.

DURATA CONTRACTULUI ESTE DE 150 LUNI, DIN CARE:

12 LUNI PERIOADA DE PROIECTARE,

18 LUNI PERIOADA DE EXECUTIE A LUCRARILOR

120 LUNI PERIOADA DE GARANTIE A LUCRARILOR

7AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA DE

CENTURA A

MUNICIPIULUI

BUCURESTI (A0)

20+000 39+000

ASOCIEREA SC SA & PE CONSTRUCT

SRL (LIDER DE ASOCIERE) -

SPEDITION UMB - TEHNOSTRADE

S.R.L.

SECTOR NORD LOT 2 19 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024831.92 MIL. LEI

FARA TVA

IN DATA DE 12.05.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL "PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 2 KM 20+000 - KM 39+000”, CU OFERTANTUL DECLARAT

CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.

VALOAREA CONTRACTULUI: 831.920.653,34 LEI FARA TVA.

LUNGIME: 19 KM

SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE.

DURATA CONTRACTULUI ESTE DE 154 LUNI, DIN CARE:

12 LUNI PERIOADA DE PROIECTARE,

22 LUNI PERIOADA DE EXECUȚIE A LUCRĂRILOR

120 LUNI PERIOADA DE GARANȚIE A LUCRĂRILOR

A FOST EMIS ORDIN DE INCEPERE IN DATA DE 16.08.2021

AUTOSTRĂZI

SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - OCTOMBRIE 2021

AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI - OCTOMBRIE 2021

Page 2: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

8AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA DE

CENTURA A

MUNICIPIULUI

BUCURESTI (A0)

69+000 85+300ALSIM ALARKO SANAYI TESISLERI VE

TICARET A.S.SECTOR SUD LOT 2: VIDRA - BRAGADIRU 16.3 27.43%

34.75% -

PROGRES

FINANCIAR

(INCLUSIV AVANS

LUCRARI SI

ACTUALIZARI

PRETURI)

10.04.2019 -

ORDIN DE

INCEPERE A

ACTIVITATII DE

PROIECTARE

18.08.2020 -

ORDIN INCEPERE

LUCRARI KM

69+000 - KM

70+700

FEBRUARIE 2023 FEBRUARIE 2023750.85 MIL. LEI

FARA TVA

ORDIN DE INCEPERE A LUCRARILOR 18.08.2020 ETAPA 1: KM 69+000 - KM 70+700

DECIZIA PENTRU EXPROPRIERI AFERENTA HG 675/2020 A FOST EMISA IN DATA DE 15.10.2020

A FOST ACORDAT AVANSUL PENTRU EXECUTIE LUCRARI (15% DIN VALOAREA LUCRARILOR)

ORDINUL DE INCEPERE PENTRU ETAPA 2, CONSTAND IN INTREG ALINIAMENTUL LOTULUI 2, A FOST EMIS IN DATA DE 29.10.2020, DATA DE INCEPERE FIIND 05.11.2020 (14,6 KM)

A FOST PUBLICAT IN MONITORIUL OFICIAL HG NR. 1139/30.12.2020 PRIVIND IMOBILELE AFLATE PE CULOARUL SUPLIMENTAR, INCLUSIV DECIZIA DE EXPROPRIERE NR. 378/17.02.2021.

IN DATA DE 12.03.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 11 PENTRU ETAPA III, EXPROPRIERI SUPLIMENTARE

9AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA DE

CENTURA A

MUNICIPIULUI

BUCURESTI (A0)

52+070 69+000ALSIM ALARKO SANAYI TESISLERI VE

TICARET A.S.

SECTOR NORD - KM 52+070 – KM

52+770; SECTOR SUD - KM 52+770 –

KM 69+000

LOT 1: GLINA - VIDRA 16.93 10.75%

19.73% -

PROGRES

FINANCIAR

(INCLUSIV AVANS

LUCRARI)

03.10.2019 -

DATA DE

INCEPERE A

ACTIVITATII DE

PROIECTARE

IUNIE 2023 ANUL 2023830.68 MIL. LEI

FARA TVA

A FOST EMISA AUTORIZATIA DE CONSTRUIRE NR. 66/25.11.2020

A FOST APROBAT PROIECTUL TEHNIC DE EXECUTIE IN DATA DE 11.02.2021.

ORDIN DE INCEPERE LUCRARI 01.03.2021

A FOST PUBLICAT IN MONITORIUL OFICIAL HG 861/2021 PRIVIND IMOBILELE AFLATE PE CULOARUL SUPLIMENTAR

10AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA DE

CENTURA A

MUNICIPIULUI

BUCURESTI (A0)

85+300 -

100+765

SUD

0+000 -

2+500

NORD

ASOCIEREA AKTOR TECHNICAL

SOCIETE ANONYME (AKTOR S.A.) -

S.C. EURO CONSTRUCT TRADING 98

S.R.L.

SECTOR SUD - KM 85+300 - KM

100+765; SECTOR NORD - KM 0+000

+ KM 2+500

LOT 3: BRAGADIRU - JOITA 17.965 0.00%

1,03% (PROGRES

FINANCIAR

INCLUSIV AVANS

PROIECTARE)

23.05.2019 -

DATA DE

INCEPERE A

ACTIVITATII DE

PROIECTARE

DECEMBRIE 2022 DECEMBRIE 2022853.42 MIL. LEI

FARA TVA

ANTREPRENORUL A FINALIZAT DECLARATIA DE PROIECTARE (INREGISTRAND INTARZIERI MAJORE IN ACTIVITATEA DE PROIECTARE), FIIND PENALIZAT CONFORM CONTRACTULUI PENTRU NEINDEPLINIREA PUCTULUI DE REFERINTA NR 1 (FINALIZAREA DECLARATIEI DE

PROIECTARE).

PAC A FOST ANALIZAT SI APROBAT IN CADRUL CTE CNAIR IN DATA DE 11.06.2021.

A FOST EMISA AUTORIZATIA DE CONSTRUIRE nr. 33/01.07.2021 - etapa I (km 86+700 - km 100+765, km 0+000 - km 2+500)

LA DATA PREZENTEI, BENEFICIARUL A EMIS OBSERVATII ASUPRA PTE - REVIZIA 2, URMAND CA ACESTA SA ELABOREZE O NOUA REVIZIE A PROIECTULUI TEHNIC

11AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA SEBES -

TURDA17+000 41+250

ASOCIEREA AKTOR TECHNICAL

SOCIETE ANONYME (AKTOR S.A.) -

S.C. EURO CONSTRUCT TRADING 98

S.R.L.

SANTIMBRU - AIUD LOT 2 24.25 89.00% 87.74% 02.12.2014

APRILIE 2022 -

CONFORM

GRAFIC DE

LUCRARI

ESTIMARE DESCHIDERE

TRAFIC - NOIEMBRIE 2021

549.33 MIL. LEI

FARA TVA

TERMENUL DE DESCHIDERE A TRAFICULUI ESTE ESTIMAT PENTRU FINALUL ANULUI 2021, RECEPTIA LA TERMINAREA LUCRARILOR FIIND ESTIMATA PENTRU APRILIE 2022.

CONTRACT PROIECTARE SI EXECUTIE CU INTARZIERI MAJORE INREGISTRATE, DATORATE SLABEI MOBILIZARI A CONSTRUCTORULUI DIN ANII ANTERIORI, DAR SI DIN PREZENT, DATORATA LIPSEI RESURSELOR FINANCIARE PROPRII PENTRU SUSTINEREA SANTIERULUI;

PE ROLUL INSTANTELOR, SE AFLA DOUA DOSARE PRIVIND CONTESTATII ALE UNOR EXECUTARI SILITE PENTRU IMOBILELE NECESARE EXECUTIEI LUCRARILOR. STADIU PROCESUAL: APEL.

IN DATA DE 18.06.2021, ANTREPRENORUL SI-A ASUMAT SOLUTIA FINALA IN VEDEREA STABILIZARII NECESARE IN ZONA KM 19+300, IN BAZA EXPERTIZEI TEHNICE REALIZATA DE ACESTA. CNAIR SA VA FACE O CONTRAEXPERTIZA, CARE SA VERIFICE CAUZELE ALUNECARII DE

TEREN (ESTE FINALIZATA DOCUMENTATIA, IN SAPTAMANA 04.10 - 08.10.2021 VOR FI TRANSMISE INVITATIILKE DE PARTICIPARE).

APLICARE MECANISM PREVAZUT DE OUG 7/ 2016 PENTRU PLATA CAD NR. 1 - IN DATA DE 28.06.2021, AU FOST APROBATE DE CATRE ORDONATORUL PRINCIPAL DE CREDITE DOCUMENTELE PREVAZUTE PRIN ORDINUL MT 205/ 2021 . IN DATA DE 30.06.2021, A FOST

EFECTUATA PLATA SUMEI PREVAZUTA PRIN DECIZIA CAD NR. 1 (ESTE INCLUSA IN PROGRESUL FINANCIAR.

12AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA SEBES -

TURDA0+000 17+000

ASOCIEREA IMPRESA PIZZAROTTI & C

SPA POMPONIO CONSTRUCTII SRLLANCRAM - SANTIMBRU LOT 1 17 98.00% 96.62% 02.12.2014

DESCHIDERE

TRAFIC -

03.12.2020

FINALIZARE

CONTRACT:

OCTOMBRIE 2021

DESCHIS TRAFIC:15,5 KM

AUTOSTRADA, INTEGRAL

NOD RUTIER SEBES,NOD

RUTIER ALBA SUD

DESCARCARE PRIN NOD

RUTIER ALBA NORD IN

DATA DE 30.07.2021.IN

DATA DE 03.12.2020, A

FOST DESCHIS TRAFICUL

DOAR PRIN 2 BRETELE NOD

SEBES SI SECT PANA LA NOD

ALBA NORD

541.73 MIL. LEI

FARA TVA

TERMENUL DE FINALIZARE A LUCRARILOR IN DATA DE 15.08.2021 A FOST COMUNICAT DE CATRE ANTREPRENOR (CARE DORESTE RECEPTIA LA TERMINAREA LUCRARILOR), DAR NU A FOST RESPECTAT. TERMENUL ESTIMAT DE CNAIR SA PENTRU RECEPTIA LA TERMINAREA

LUCRARILOR ESTE 30.10.2021.

IN DATA DE 03.12.2020 S-A DESCHIS TRAFICUL PE UN TRONSON DE 15.5 KM. IN DATA DE 30.07.2021, A FOST DESCHIS IN INTEGRALITATE TRAFICUL LA NODUL SEBES, CARE FACE LEGATURA INTRE AUTOSTRADA A10 SI A1.

DESCHIDEREA TRAFICULUI PE TOATA LUNGIMEA SECTORULUI DE AUTOSTRADA VA AVEA LOC DOAR DUPA FINALIZAREA LUCRARILOR SI PE LOTUL 2, DEOARECE DESCARCAREA TRAFICULUI ESTE POSIBILA DOAR PRIN NODUL ALBA IULIA NORD DE LA KM 15+500.

APLICAREA DE PENALITATI ANTREPRENORULUI PRIN EMITEREA UNEI FACTURI DE PENALITĂȚI PENTRU SUMA STABILITĂ DE CĂTRE INGINER PRIN MODUL DE SOLUȚIONARE A REVENDICĂRII BENEFICIARULUI PRIVIND EȘECUL ANTREPRENORULUI DE A RESPECTA

PREVEDERILE SUB-CLAUZEI 8.2 [DURATA DE EXECUȚIE] IN VALOARE DE 81.260.870,58 LEI

APLICAREA DE PENALITATI ANTREPRENORULUI PRIN EMITEREA UNEI FACTURI DE PENALITĂȚI PENTRU SUMA STABILITĂ DE CĂTRE INGINER PRIN MODUL DE SOLUȚIONARE A REVENDICĂRII BENEFICIARULUI PRIVIND ÎNTÂRZIERI ÎN REMITEREA PROGRAMULUI DE EXECUȚIE

PL ST002E, IN VALOARE DE 3.250.000.00 LEI

13AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA SIBIU -

PITESTI91+761 122+110 ASTALDI SPA (ITALIA) CURTEA DE ARGES - PITESTI SECTIUNEA 5 30.35 0% 3.31%

IUNIE 2020 -

EMITERE ORDIN

ETAPA DE

PROIECTARE,

AUTORIZATIA DE

CONSTRUIRE

NR.31/17.06.202

1

IN DATA DE

01.09.2021 S-A

EMIS ORDINUL DE

INCEPERE A

EXECUTIEI

LUCRARILOR

2025 IN CF CU

PREVEDERILE CTR

DURATA DE

REALIZARE A

ACESTUI CTR ESTE

DE 60 DE LUNI,

RESPECTIV: 12

LUNI PERIODA DE

PROIECTARE SI 48

DE LUNI PENTRU

EXECUTIA

LUCRARILOR.

PERIOADA DE

GARANTIE A

LUCRARILOR

OFERTATA DE

ASTALDI SPA ESTE

DE 120 DE LUNI

ANUL 20251710 MIL. LEI

FARA TVA

22.06.2020 – ORDIN DE INCEPERE FAZA PROIECTARE (12 LUNI)

CONTRACT DE SERVICII NR.92/58937/11.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 5 – CURTEA DE ARGES – PITESTI KM 92+600-KM 122+950"""" SEMNAT CU ASOCIAREA EGIS INTERNATIONAL S.A.S – SEARCH CORPORATION S.R.L.- ITALROM

INGINERIE INTERNATIONALA S.R.L.- METROUL S.A, A INLOCUIT SUPERVIZORUL DRDP BUCURESTI INCEPAND CU DATA DE 01.10.2020

IN DATA DE 30.12.2020 A FOST PUBLICATA HOTARAREA DE GUVERN NR.1134 PENTRU REALIZAREA EXPROPRIERILOR PENTRU SUPRAFETELE DE TEREN AFLATE PE AZA LOCALITATILOR BUDEASA, CURTEA DE ARGES, MALURENI SI MUNICIPIUL PITESTI, DIN JUDETUL ARGES.

17.02.2021 - S-A EMIS DECIZIA DE EXPROPRIERE NR. 377/2020 PENTRU IMOBILELE DE PE RAZA LOCALITATILOR BUDEASA, CURTEA DE ARGES, MALURENI SI MUN. PITESTI

PROCEDURA DE EXPROPRIERE INTERGAL FINALIZATA

IN DATA DE 16.06.2021 S-A OBTINUT AUTORIZATIA DE CONSTRUIRE

IN DATA DE 01.09.2021 S-A EMIS ORDINUL DE INCEPERE A LUCRARILOR

IN DATA DE 16.09.2021, A FOST AVIZAT IN CTE CNAIR PROIECTUL TEHNIC DE EXECUTIE.

14AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA SIBIU -

PITESTI0+000 13+170 PORR CONSTRUCT SRL LOT 1: KM 0+000 - KM 13+170

SECTIUNEA 1: SIBIU - BOITA

(KM 0+000 - KM 14+150), LOT

1

13.17 50.00% 48.41%

29.05.2019 -

EMITERE ORDIN

DE INCEPERE

ETAPA DE

PROIECTARE,

30.03.2020 -

EMITERE ORDIN

DE INCEPERE

ETAPA EXECUTIE

LUCRARI

28.05.2023 ANUL 2023612.65 MIL. LEI

FARA TVA

PROIECTUL TEHNIC A FOST FINALIZAT SI APROBAT DE CATRE CNAIR SA IN DATA DE 01.04.2020.

AUTORIZATIA DE CONSTRUIRE A FOST EMISA IN DATA DE 09.03.2020.

CONTRACT DE SERVICII NR. 92/61673/22.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 1 –SIBIU – BOITA KM 0+000-KM 14+150"" ASOCIEREA TPF INGINERIE S.R.L. - SEPTEMBRIE CONSULTING S.R.L. A INLOCUIT SUPERVIZORUL DRDP BUCURESTI

INCEPAND CU DATA DE 19.10.2020

Page 3: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

15AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIDRUM NATIONAL POD BRAILA

ASOCIEREA ASTALDI S.P. A - IHI

INFRASTRUCTURE SYSTEM CO. LTD.

POD SUSPENDAT PESTE DUNARE IN

ZONA BRAILA1

DRUM BRAILA-

JIJILA - 19,095

KM;

DRUM DE

LEGATURA CU

DN22 SMARDAN-

MACIN - 4,328

KM

48.50% 60.60% 21.12.2018

SECTIUNEA 2

DECEMBRIE 2021

TOTAL

CONTRACT:

ESTIMAT

DECEMBRIE 2022

DECEMBRIE 2021

SECTIUNEA 2 PODUL

SUSPENDAT

1.996 MLD. LEI

FARA TVACONTRACT IN DERULARE.

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA BRASOV -

TARGU MURES - CLUJ -

ORADEA

30+550 59+100

ASOCIEREA TRAMECO SA –

VAHOSTAV -SK A.S. – DRUMURI

BIHOR SA – DRUM ASFALT SRL –

EAST WATER DRILLINGS SRL

SECTIUNEA 3C, SUBSECTIUNEA 3C2

CHIRIBIS - BIHARIA

SUBSECTIUNEA 3C2: CHIRIBIS -

BIHARIA28.55 0.50% 0%

14.09.2020 -

EMITERE ORDIN

DE INCEPERE

PENTRU ETAPA

DE PROIECTARE

(PROIECT TEHNIC)

MARTIE 2022

(CONFORM

CONTRACT)

IUNIE 2022

(CONFORM

PROGRAM)

ANUL 2022 6 LUNI - ETAPA

DE PROIECTARE; 18 LUNI -

ETAPA DE EXECUTIE

LUCRARI; 120 LUNI -

PERIOADA DE GARANTIE

326.51 MIL. LEI

FARA TVA

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 11.08. 2020.

A FOST TRANSMISA CATRE ANTREPRENOR ADRESA CU ORDINUL DE INCEPERE PENTRU DATA DE 14.09.2020. A FOST ACORDAT DREPTUL DE ACCES IN SANTIER ANTREPRENORULUI.

DURATA CONTRACTULUI ESTE DE 144 DE LUNI DIN CARE:

6 LUNI - ETAPA DE PROIECTARE; FINALIZARE PUNCT DE REFERINTA NR. 1 IN 09.11.2020.

18 LUNI - ETAPA DE EXECUTIE LUCRARI

120 LUNI - PERIOADA DE GARANTIE

2AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA BRASOV -

TARGU MURES - CLUJ -

ORADEA

8+700 38+760

ASOCIEREA S.C. SPEDITION UMB

S.R.L. – S.C. TEHNOSTRADE S.R.L. –

S.C. ELECTROMONTAJ S.A

SECTIUNEA 3A SI SECTIUNEA 3B,

SUBSECTIUNEA 3A2: NADASELU -

MIHAIESTI SI 3B1: MIHAESTI ZIMBOR

SUBSECTIUNEA 3A2

NADASELU - MIHAIESTI KM

8+700 - 25+500+ 3B1,

MIHAIESTI – ZIMBOR KM

0+000 - 13+260

30.06 0% 0% 25.01.2021 2023 ANUL 20231.390,614 MIL.

LEI FARA TVA

SEMNARE CONTRACT PROIECTARE SI EXECUTIE IN DATA DE 28.12.2020. PRETUL PE KM DE AUTOSTRADA ESTE DE CCA. 46,261,293.92 LEI FARA TVA, REPREZENTAND CCA. 9,383,629 EURO FARA TVA.

DURATA CONTRACTULUI ESTE DE 96 DE LUNI, DIN CARE:

• 12 LUNI PERIOADA DE PROIECTARE,

• 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,

• 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.

AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3A2 IN LUNA APRILIE 2021.

AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3B1 IN 01.07.2021

PROIECT TEHNIC DE EXECUTIE PENTRU 3A2 AVIZAT IN CTE - CNAIR IN DATA DE 20.08.2021

PROIECT TEHNIC IN CURS DE ELABORARE PENTRU 3B1 - TERMEN ESTIMAT AVIZARE PROIECT TEHNIC: DEC. 2021

3AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA BRASOV -

TARGU MURES - CLUJ -

ORADEA

66+500 80+054 NUROL INSAAT VE TICARET S.ASECTIUNEA 3B, SUBSECTIUNEA 3B5

NUSFALAU - SUPLACU DE BARCAU

SUBSECTIUNEA 3B5:

NUSFALAU - SUPLACU DE

BARCAU

13.55 4.34% 15.75% 01.02.2021 FEBRUARIE 2023 FEBRUARIE 2023384.14 MIL. LEI

FARA TVA

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN 30.09.2020;

6 LUNI PERIOADA DE PROIECTARE

; 18 LUNI PERIOADA DE EXECUTIE

; 120 LUNI PERIOADA DE GARANTIE

LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 12 STRUCTURI (4 PASAJE SI 8 PODURI), RESPECTIV UN NOD RUTIER LA KM 67+500

FINALIZARE ETAPA PROIECTARE (PTE) - PROIECTUL TEHNIC DE EXECUTIE A FOST AVIZAT IN CADRUL CTE IN DATA DE 02.08.2021

4AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA BRASOV -

TARGU MURES - CLUJ -

ORADEA

13+260 25+500

ASOCIEREA SC SA&PE CONSTRUCT

SRL - SC SPEDITION UMB SRL - SC

TEHNOSTRADE SRL

SECTIUNEA 3B, SUBSECTIUNEA 3B2:

ZIMBOR - POARTA SALAJULUI

SUBSECTIUNEA 3B2: ZIMBOR -

POARTA SALAJULUI12.24 0% 0%

31.05.2021 -

ORDIN DE

INCEPERE

2023 ANUL 2023680.40 MIL. LEI

FARA TVA

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 01.07.2020;

DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE:

12 LUNI PERIOADA DE PROIECTARE,

24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,

120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR

A FOST CONSTITUITA GARANTIA DE BUNA EXECUTIE A LUCRARILOR, ORDINUL DE INCEPERE A LUCRARILOR EMIS PENTRU DATA DE 31.05.2021

5AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA BRASOV -

TARGU MURES - CLUJ -

ORADEA

0+000 4+500 S.C. STRABAG S.R.L. SECTOR 1C: TG. MURES - OGRA

LOT 1 - TARGU MURES -

UNGHENI (4.5 KM) + DRUM

DE LEGATURA (4.7 KM)

9.2 79.50% 63.87%

ORDIN DE

INCEPERE

PENTRU EXECUTIE

- 22 IULIE 2020

2022 (CONFORM

CONTRACT)

2021 -

CONFORM

ESTIMARE

ANTREPRENOR/

CNAIR SA

ANUL 2022192.06 MIL. LEI

FARA TVA

1. CONTRACT DE EXECUTIE SEMNAT IN DATA DE 29.05.2020.

2. AUTORIZATIE DE CONSTRUIRE VALABILA PENTRU ACEST SECTOR.

3. DURATA DE REALIZARE A ACESTUI CONTRACT ESTE URMATOAREA:

18 LUNI - PERIOADA DE EXECUTIE A LUCRARILOR;

108 LUNI (9 ANI) - PERIOADA DE GARANTIE A LUCRARILOR;

LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 3 PODURI SI PASAJE PE DRUMURI DE LEGATURA, 6 PODURI SI PASAJE PE AUTOSTRADA, PRECUM SI DOUA NODURI RUTIERE PENTRU CONECTAREA AUTOSTRAZII LA RETEAUA

DE DRUMURI EXISTENTA.

6AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA DE

CENTURA A

MUNICIPIULUI

BUCURESTI (A0)

47+600 52+070

ASOCIEREA S.C. SA&PE CONSTRUCT

S.R.L. - S.C. SPEDITION UMB S.R.L. -

S.C. TEHNOSTRADE S.R.L.

SECTOR NORD LOT 4 4.47 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024312.63 MIL. LEI

FARA TVA

IN DATA DE 17.05.2020, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL "PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 4 KM 47+600 - KM 52+070”, CU OFERTANTUL DECLARAT

CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.

VALOAREA CONTRACTULUI: 312.633.554,09 LEI FARA TVA.

LUNGIME: 4.47 KM

SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE.

DURATA CONTRACTULUI ESTE DE 150 LUNI, DIN CARE:

12 LUNI PERIOADA DE PROIECTARE,

18 LUNI PERIOADA DE EXECUTIE A LUCRARILOR

120 LUNI PERIOADA DE GARANTIE A LUCRARILOR

7AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA DE

CENTURA A

MUNICIPIULUI

BUCURESTI (A0)

20+000 39+000

ASOCIEREA SC SA & PE CONSTRUCT

SRL (LIDER DE ASOCIERE) -

SPEDITION UMB - TEHNOSTRADE

S.R.L.

SECTOR NORD LOT 2 19 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024831.92 MIL. LEI

FARA TVA

IN DATA DE 12.05.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL "PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 2 KM 20+000 - KM 39+000”, CU OFERTANTUL DECLARAT

CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.

VALOAREA CONTRACTULUI: 831.920.653,34 LEI FARA TVA.

LUNGIME: 19 KM

SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE.

DURATA CONTRACTULUI ESTE DE 154 LUNI, DIN CARE:

12 LUNI PERIOADA DE PROIECTARE,

22 LUNI PERIOADA DE EXECUȚIE A LUCRĂRILOR

120 LUNI PERIOADA DE GARANȚIE A LUCRĂRILOR

A FOST EMIS ORDIN DE INCEPERE IN DATA DE 16.08.2021

AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI - OCTOMBRIE 2021

Page 4: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

8AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA DE

CENTURA A

MUNICIPIULUI

BUCURESTI (A0)

69+000 85+300ALSIM ALARKO SANAYI TESISLERI VE

TICARET A.S.SECTOR SUD LOT 2: VIDRA - BRAGADIRU 16.3 27.43%

34.75% -

PROGRES

FINANCIAR

(INCLUSIV AVANS

LUCRARI SI

ACTUALIZARI

PRETURI)

10.04.2019 -

ORDIN DE

INCEPERE A

ACTIVITATII DE

PROIECTARE

18.08.2020 -

ORDIN INCEPERE

LUCRARI KM

69+000 - KM

70+700

FEBRUARIE 2023 FEBRUARIE 2023750.85 MIL. LEI

FARA TVA

ORDIN DE INCEPERE A LUCRARILOR 18.08.2020 ETAPA 1: KM 69+000 - KM 70+700

DECIZIA PENTRU EXPROPRIERI AFERENTA HG 675/2020 A FOST EMISA IN DATA DE 15.10.2020

A FOST ACORDAT AVANSUL PENTRU EXECUTIE LUCRARI (15% DIN VALOAREA LUCRARILOR)

ORDINUL DE INCEPERE PENTRU ETAPA 2, CONSTAND IN INTREG ALINIAMENTUL LOTULUI 2, A FOST EMIS IN DATA DE 29.10.2020, DATA DE INCEPERE FIIND 05.11.2020 (14,6 KM)

A FOST PUBLICAT IN MONITORIUL OFICIAL HG NR. 1139/30.12.2020 PRIVIND IMOBILELE AFLATE PE CULOARUL SUPLIMENTAR, INCLUSIV DECIZIA DE EXPROPRIERE NR. 378/17.02.2021.

IN DATA DE 12.03.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 11 PENTRU ETAPA III, EXPROPRIERI SUPLIMENTARE

9AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA DE

CENTURA A

MUNICIPIULUI

BUCURESTI (A0)

52+070 69+000ALSIM ALARKO SANAYI TESISLERI VE

TICARET A.S.

SECTOR NORD - KM 52+070 – KM

52+770; SECTOR SUD - KM 52+770 –

KM 69+000

LOT 1: GLINA - VIDRA 16.93 10.75%

19.73% -

PROGRES

FINANCIAR

(INCLUSIV AVANS

LUCRARI)

03.10.2019 -

DATA DE

INCEPERE A

ACTIVITATII DE

PROIECTARE

IUNIE 2023 ANUL 2023830.68 MIL. LEI

FARA TVA

A FOST EMISA AUTORIZATIA DE CONSTRUIRE NR. 66/25.11.2020

A FOST APROBAT PROIECTUL TEHNIC DE EXECUTIE IN DATA DE 11.02.2021.

ORDIN DE INCEPERE LUCRARI 01.03.2021

A FOST PUBLICAT IN MONITORIUL OFICIAL HG 861/2021 PRIVIND IMOBILELE AFLATE PE CULOARUL SUPLIMENTAR

10AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA DE

CENTURA A

MUNICIPIULUI

BUCURESTI (A0)

85+300 -

100+765

SUD

0+000 -

2+500

NORD

ASOCIEREA AKTOR TECHNICAL

SOCIETE ANONYME (AKTOR S.A.) -

S.C. EURO CONSTRUCT TRADING 98

S.R.L.

SECTOR SUD - KM 85+300 - KM

100+765; SECTOR NORD - KM 0+000

+ KM 2+500

LOT 3: BRAGADIRU - JOITA 17.965 0.00%

1,03% (PROGRES

FINANCIAR

INCLUSIV AVANS

PROIECTARE)

23.05.2019 -

DATA DE

INCEPERE A

ACTIVITATII DE

PROIECTARE

DECEMBRIE 2022 DECEMBRIE 2022853.42 MIL. LEI

FARA TVA

ANTREPRENORUL A FINALIZAT DECLARATIA DE PROIECTARE (INREGISTRAND INTARZIERI MAJORE IN ACTIVITATEA DE PROIECTARE), FIIND PENALIZAT CONFORM CONTRACTULUI PENTRU NEINDEPLINIREA PUCTULUI DE REFERINTA NR 1 (FINALIZAREA DECLARATIEI DE

PROIECTARE).

PAC A FOST ANALIZAT SI APROBAT IN CADRUL CTE CNAIR IN DATA DE 11.06.2021.

A FOST EMISA AUTORIZATIA DE CONSTRUIRE nr. 33/01.07.2021 - etapa I (km 86+700 - km 100+765, km 0+000 - km 2+500)

LA DATA PREZENTEI, BENEFICIARUL A EMIS OBSERVATII ASUPRA PTE - REVIZIA 2, URMAND CA ACESTA SA ELABOREZE O NOUA REVIZIE A PROIECTULUI TEHNIC

11AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA SEBES -

TURDA17+000 41+250

ASOCIEREA AKTOR TECHNICAL

SOCIETE ANONYME (AKTOR S.A.) -

S.C. EURO CONSTRUCT TRADING 98

S.R.L.

SANTIMBRU - AIUD LOT 2 24.25 89.00% 87.74% 02.12.2014

APRILIE 2022 -

CONFORM

GRAFIC DE

LUCRARI

ESTIMARE DESCHIDERE

TRAFIC - NOIEMBRIE 2021

549.33 MIL. LEI

FARA TVA

TERMENUL DE DESCHIDERE A TRAFICULUI ESTE ESTIMAT PENTRU FINALUL ANULUI 2021, RECEPTIA LA TERMINAREA LUCRARILOR FIIND ESTIMATA PENTRU APRILIE 2022.

CONTRACT PROIECTARE SI EXECUTIE CU INTARZIERI MAJORE INREGISTRATE, DATORATE SLABEI MOBILIZARI A CONSTRUCTORULUI DIN ANII ANTERIORI, DAR SI DIN PREZENT, DATORATA LIPSEI RESURSELOR FINANCIARE PROPRII PENTRU SUSTINEREA SANTIERULUI;

PE ROLUL INSTANTELOR, SE AFLA DOUA DOSARE PRIVIND CONTESTATII ALE UNOR EXECUTARI SILITE PENTRU IMOBILELE NECESARE EXECUTIEI LUCRARILOR. STADIU PROCESUAL: APEL.

IN DATA DE 18.06.2021, ANTREPRENORUL SI-A ASUMAT SOLUTIA FINALA IN VEDEREA STABILIZARII NECESARE IN ZONA KM 19+300, IN BAZA EXPERTIZEI TEHNICE REALIZATA DE ACESTA. CNAIR SA VA FACE O CONTRAEXPERTIZA, CARE SA VERIFICE CAUZELE ALUNECARII DE

TEREN (ESTE FINALIZATA DOCUMENTATIA, IN SAPTAMANA 04.10 - 08.10.2021 VOR FI TRANSMISE INVITATIILKE DE PARTICIPARE).

APLICARE MECANISM PREVAZUT DE OUG 7/ 2016 PENTRU PLATA CAD NR. 1 - IN DATA DE 28.06.2021, AU FOST APROBATE DE CATRE ORDONATORUL PRINCIPAL DE CREDITE DOCUMENTELE PREVAZUTE PRIN ORDINUL MT 205/ 2021 . IN DATA DE 30.06.2021, A FOST

EFECTUATA PLATA SUMEI PREVAZUTA PRIN DECIZIA CAD NR. 1 (ESTE INCLUSA IN PROGRESUL FINANCIAR.

12AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA SEBES -

TURDA0+000 17+000

ASOCIEREA IMPRESA PIZZAROTTI & C

SPA POMPONIO CONSTRUCTII SRLLANCRAM - SANTIMBRU LOT 1 17 98.00% 96.62% 02.12.2014

DESCHIDERE

TRAFIC -

03.12.2020

FINALIZARE

CONTRACT:

OCTOMBRIE 2021

DESCHIS TRAFIC:15,5 KM

AUTOSTRADA, INTEGRAL

NOD RUTIER SEBES,NOD

RUTIER ALBA SUD

DESCARCARE PRIN NOD

RUTIER ALBA NORD IN

DATA DE 30.07.2021.IN

DATA DE 03.12.2020, A

FOST DESCHIS TRAFICUL

DOAR PRIN 2 BRETELE NOD

SEBES SI SECT PANA LA NOD

ALBA NORD

541.73 MIL. LEI

FARA TVA

TERMENUL DE FINALIZARE A LUCRARILOR IN DATA DE 15.08.2021 A FOST COMUNICAT DE CATRE ANTREPRENOR (CARE DORESTE RECEPTIA LA TERMINAREA LUCRARILOR), DAR NU A FOST RESPECTAT. TERMENUL ESTIMAT DE CNAIR SA PENTRU RECEPTIA LA TERMINAREA

LUCRARILOR ESTE 30.10.2021.

IN DATA DE 03.12.2020 S-A DESCHIS TRAFICUL PE UN TRONSON DE 15.5 KM. IN DATA DE 30.07.2021, A FOST DESCHIS IN INTEGRALITATE TRAFICUL LA NODUL SEBES, CARE FACE LEGATURA INTRE AUTOSTRADA A10 SI A1.

DESCHIDEREA TRAFICULUI PE TOATA LUNGIMEA SECTORULUI DE AUTOSTRADA VA AVEA LOC DOAR DUPA FINALIZAREA LUCRARILOR SI PE LOTUL 2, DEOARECE DESCARCAREA TRAFICULUI ESTE POSIBILA DOAR PRIN NODUL ALBA IULIA NORD DE LA KM 15+500.

APLICAREA DE PENALITATI ANTREPRENORULUI PRIN EMITEREA UNEI FACTURI DE PENALITĂȚI PENTRU SUMA STABILITĂ DE CĂTRE INGINER PRIN MODUL DE SOLUȚIONARE A REVENDICĂRII BENEFICIARULUI PRIVIND EȘECUL ANTREPRENORULUI DE A RESPECTA

PREVEDERILE SUB-CLAUZEI 8.2 [DURATA DE EXECUȚIE] IN VALOARE DE 81.260.870,58 LEI

APLICAREA DE PENALITATI ANTREPRENORULUI PRIN EMITEREA UNEI FACTURI DE PENALITĂȚI PENTRU SUMA STABILITĂ DE CĂTRE INGINER PRIN MODUL DE SOLUȚIONARE A REVENDICĂRII BENEFICIARULUI PRIVIND ÎNTÂRZIERI ÎN REMITEREA PROGRAMULUI DE EXECUȚIE

PL ST002E, IN VALOARE DE 3.250.000.00 LEI

13AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA SIBIU -

PITESTI91+761 122+110 ASTALDI SPA (ITALIA) CURTEA DE ARGES - PITESTI SECTIUNEA 5 30.35 0% 3.31%

IUNIE 2020 -

EMITERE ORDIN

ETAPA DE

PROIECTARE,

AUTORIZATIA DE

CONSTRUIRE

NR.31/17.06.202

1

IN DATA DE

01.09.2021 S-A

EMIS ORDINUL DE

INCEPERE A

EXECUTIEI

LUCRARILOR

2025 IN CF CU

PREVEDERILE CTR

DURATA DE

REALIZARE A

ACESTUI CTR ESTE

DE 60 DE LUNI,

RESPECTIV: 12

LUNI PERIODA DE

PROIECTARE SI 48

DE LUNI PENTRU

EXECUTIA

LUCRARILOR.

PERIOADA DE

GARANTIE A

LUCRARILOR

OFERTATA DE

ASTALDI SPA ESTE

DE 120 DE LUNI

ANUL 20251710 MIL. LEI

FARA TVA

22.06.2020 – ORDIN DE INCEPERE FAZA PROIECTARE (12 LUNI)

CONTRACT DE SERVICII NR.92/58937/11.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 5 – CURTEA DE ARGES – PITESTI KM 92+600-KM 122+950"""" SEMNAT CU ASOCIAREA EGIS INTERNATIONAL S.A.S – SEARCH CORPORATION S.R.L.- ITALROM

INGINERIE INTERNATIONALA S.R.L.- METROUL S.A, A INLOCUIT SUPERVIZORUL DRDP BUCURESTI INCEPAND CU DATA DE 01.10.2020

IN DATA DE 30.12.2020 A FOST PUBLICATA HOTARAREA DE GUVERN NR.1134 PENTRU REALIZAREA EXPROPRIERILOR PENTRU SUPRAFETELE DE TEREN AFLATE PE AZA LOCALITATILOR BUDEASA, CURTEA DE ARGES, MALURENI SI MUNICIPIUL PITESTI, DIN JUDETUL ARGES.

17.02.2021 - S-A EMIS DECIZIA DE EXPROPRIERE NR. 377/2020 PENTRU IMOBILELE DE PE RAZA LOCALITATILOR BUDEASA, CURTEA DE ARGES, MALURENI SI MUN. PITESTI

PROCEDURA DE EXPROPRIERE INTERGAL FINALIZATA

IN DATA DE 16.06.2021 S-A OBTINUT AUTORIZATIA DE CONSTRUIRE

IN DATA DE 01.09.2021 S-A EMIS ORDINUL DE INCEPERE A LUCRARILOR

IN DATA DE 16.09.2021, A FOST AVIZAT IN CTE CNAIR PROIECTUL TEHNIC DE EXECUTIE.

14AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIAUTOSTRADA

AUTOSTRADA SIBIU -

PITESTI0+000 13+170 PORR CONSTRUCT SRL LOT 1: KM 0+000 - KM 13+170

SECTIUNEA 1: SIBIU - BOITA

(KM 0+000 - KM 14+150), LOT

1

13.17 50.00% 48.41%

29.05.2019 -

EMITERE ORDIN

DE INCEPERE

ETAPA DE

PROIECTARE,

30.03.2020 -

EMITERE ORDIN

DE INCEPERE

ETAPA EXECUTIE

LUCRARI

28.05.2023 ANUL 2023612.65 MIL. LEI

FARA TVA

PROIECTUL TEHNIC A FOST FINALIZAT SI APROBAT DE CATRE CNAIR SA IN DATA DE 01.04.2020.

AUTORIZATIA DE CONSTRUIRE A FOST EMISA IN DATA DE 09.03.2020.

CONTRACT DE SERVICII NR. 92/61673/22.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 1 –SIBIU – BOITA KM 0+000-KM 14+150"" ASOCIEREA TPF INGINERIE S.R.L. - SEPTEMBRIE CONSULTING S.R.L. A INLOCUIT SUPERVIZORUL DRDP BUCURESTI

INCEPAND CU DATA DE 19.10.2020

15AUTOSTRAZI IN EXECUTIE / PROIECTARE SI

EXECUTIE LUCRARIDRUM NATIONAL POD BRAILA

ASOCIEREA ASTALDI S.P. A - IHI

INFRASTRUCTURE SYSTEM CO. LTD.

POD SUSPENDAT PESTE DUNARE IN

ZONA BRAILA1

DRUM BRAILA-

JIJILA - 19,095

KM;

DRUM DE

LEGATURA CU

DN22 SMARDAN-

MACIN - 4,328

KM

48.50% 60.60% 21.12.2018

SECTIUNEA 2

DECEMBRIE 2021

TOTAL

CONTRACT:

ESTIMAT

DECEMBRIE 2022

DECEMBRIE 2021

SECTIUNEA 2 PODUL

SUSPENDAT

1.996 MLD. LEI

FARA TVACONTRACT IN DERULARE.

Page 5: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA

AUTOSTRADA BRASOV -

BACAU 0+000 165+000

SEARCH CORPORATION&

PRIMACONS GRUP SRL - CONTRACT

PROIECTARE ELABORARE STUDIU DE

FEZABILITATE SI PROIECT TEHNIC

(VALOARE CONTRACT PROIECTARE:

20.093.359,86 LEI FARA TVA)

BRASOV - BACAU LOT 1 165 0% 0%

22.05.2020 -

DATA SEMNARII

CONTRACTULUI

DE PRESTARI

SERVICII DE

PROIECTARE

(STUDIU DE

FEZABILITATE SI

ELABORARE

PROIECT TEHNIC)

10.07.2020 -

ORDIN INCEPERE

ETAPA DE

PROIECTARE

2023 -

FINALIZARE

PROIECTARE

(SF+PT)

ANUL 2023 - FINALIZARE

PROIECTARE (SF+PT)

8858.21 MIL. LEI

FARA TVA

DURATA CONTRACTULUI ESTE DE 30 LUNI.

ORDINUL DE INCEPERE: 10.07.2020

PRESTATORUL A ELABORAT ANALIZA MULTICRITERIALA PRIVIND ALEGEREA ALTERNATIVELOR DE TRASEU, ETAPA 1.

A FOST AVIZAT IN CTE CNAIR SA - ANALIZA MULTICRITERIALA ETAPA 1.

AU FOST FINALIZATE STUDIILE DE TEREN AFERENT PROIECTULUI PRELIMINAR (STUDII TOPOGRAFICE SI GEOTEHNICE).

A FOST INAINTATA ANALIZA MULTICRITERIALA NR. 2, IN ANALIZA JASPERS

2AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA A1 SI A3 SEARCH CORPORATION SRL

ELABORARE STUDIU DE

FEZABILITATE SI PROIECT TEHNIC DE

EXECUTIE PENTRU 6 NODURI

RUTIERE PE A1 SI A3 IN ZONA DE

VEST A ROMANIEI

A1(KM 326+155) - DJ

704(CUGHIR),A1(KM

362+813) - DC

129(SANTUHALM),A1(KM

485+030 - DJ

609E(RECAS),A1(KM 450+210)

- DJ 609(BETTHAUSEN),A1(KM

528+509) - DJ

682G(CRUCENI),A3(KM

39+940) - DN1P(SPINUS)

0% 0% 22.04.2021 22.06.2022

CONTRACT SEMNAT IN DATA DE 17.03.2021

ORDINUL DE INCEPERE A ACTIVITATII DE PROIECTARE A FOST EMIS IN DATA DE 22.04.2021

DURATA CONTRACTULUI ESTE DE 14 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI, DIN CARE:

-6 LUNI PENTRU ELABORAREA STUDIULUI DE FEZABILITATE,

- 4 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA LUCRARILOR DE CONSTRUIRE,

- 3 LUNI PENTRU ELABORAREA PROIECTULUI TEHNIC DE EXECUTIE SI

- 1 LUNI PENTRU ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFICIARULUI.

A AVUT LOC SEDINTA DE INCEPUT IN DATA DE 22.04.2021. A FOST APROBAT RAPORTUL DE PROGRES NR.3

3AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA

AUTOSTRADA TARGU

NEAMT - IASI -

UNGHENI

0+000 100+140 SC CONSITRANS S.R.L.TARGU NEAMT - IASI (LETCANI) -

UNGHENI100.14

2021 - SERVICII

DE PROIECTARE

FAZA S.F. + P.A.C.

+ P.T.E. SECTIUNE

TARGU NEAMT -

IASI-UNGHENI

2023 -

FINALIZARE

PROIECTARE

ANUL 2025 - PERIOADA

ESTIMATA DESCHIDERE

TRAFIC PENTRU PRIMELE

SECTIUNI

58.83 MIL. LEI

FARA TVA

(VALOARE

CONTRACT

COMPLETARE/RE

VIZUIRE/ACTUALI

ZARE S.F. SI

ELABORARE P.A.C.

+ P.A.D. + P.T.E)

IN DATA DE 08.04.2021 A FOST SEMNAT CONTRACTUL DE SERVICII „COMPLETARE/ REVIZUIRE/ ACTUALIZARE STUDIU DE FEZABILITATE SI ELABORARE P.A.C., P.A.D. SI P.T.E. PENTRU OBIECTIVUL „AUTOSTRADA TARGU-NEAMT – IASI – UNGHENI” CU SC CONSITRANS S.R.L.

PRETUL CONTRACTULUI ESTE DE 58.830.448,35 LEI FARA TVA

IN DATA DE 07.05.2021 A AVUT LOC SEDINTA DE INCEPUT

IN DATA DE 15.09.2021 A FOST INAINTATA DOCUMENTATIA ANALIZA MULTICRITERIALA ETAPA 1, IN PREZENT ACEASTA ESTE IN ANALIZA (TERMEN 05.10.2021)

DURATA DE REALIZARE A SERVICIILOR DE PROIECTARE ESTE DUPA CUM URMEAZA:

12 LUNI PENTRU REALIZAREA STUDIULUI DE FEZABILITATE;

5 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA EXECUTARII LUCRARILOR DE CONSTRUIRE (PAC) SI OBTINEREA AUTORIZATIEI DE CONSTRUIRE;

5 LUNI PENTRU REALIZAREA PROIECTULUI TEHNIC DE EXECUTIE (PTE)

4AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA

AUTOSTRADA SIBIU -

BRASOV 0+000 68+050

CONSITRANS

(VALOARE CONTRACT PROIECTARE:

16.313.855,49 FARA TVA)

SIBIU - FAGARAS LOT 1 68.05 22.00%

ORDIN DE

INCEPERE

11.05.2015

TRIM III 2021/

FINALIZARE

PROIECTARE FAZA

REVIZUIRE

STUDIU DE

FEZABILITATE

FINALIZARE PROIECTARE

(EMITERE ACORD DE

MEDIU) - TRIM. III 2021

5170 MIL. LEI

FARA TVACONTRACT REVIZUIRE STUDIU DE FEZABILITATE IN DERULARE - STUDIUL DE FEZABILITATE A FOST AVIZAT IN CADRUL CTE, PROCEDURA DE MEDIU IN DERULARE

5AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA

AUTOSTRADA SIBIU -

BRASOV 0+000 48+410

ASOCIEREA SEARCH CORPORATION

S.R.L. - PROTELCO S.A. - LIKE

CONSULTING S.R.L. – MEGA

MUHENDISLIK MUSAVIRLIK A.S.

(MEGA ENGINEERING CONSULTING

INC.)

FAGARAS - BRASOV LOT 2 48.41 0% 0% 2021 202318.17 MIL LEI

FARA TVA

IN DATA DE 23.08.2021, CNAIR A SEMNAT CONTRACTUL PENTRU „COMPLETARE STUDIU DE FEZABILITATE ȘI PROIECT TEHNIC PENTRU ""AUTOSTRADA BRAȘOV - FĂGĂRAȘ”, CU OFERTANTUL DECLARAT CÂȘTIGĂTOR ASOCIEREA SEARCH CORPORATION S.R.L. - PROTELCO

S.A. - LIKE CONSULTING S.R.L. – MEGA MUHENDISLIK MUSAVIRLIK A.S. (MEGA ENGINEERING CONSULTING INC.).

VALOAREA CONTRACTULUI ESTE DE 18.174.952,71 LEI FĂRĂ TVA.

SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE.

CONTRACTUL DE SERVICII ESTE STRUCTURAT ASTFEL:

• ETAPA I: 25 LUNI

STUDIU DE FEZABILITATE: 22 LUNI

PROIECT PENTRU AUTORIZAREA EXECUTĂRII LUCRĂRILOR DE CONSTRUIRE (P.A.C.) ȘI

ASISTENȚĂ TEHNICĂ ACORDATĂ BENEFICIARULUI PENTRU SUSŢINEREA APLICAŢIEI DE FINANŢARE: 3 LUNI

• ETAPA II: 6 LUNI

PROIECT TEHNIC (P.T.): 3 LUNI

ASISTENȚĂ TEHNICĂ ACORDATĂ BENEFICIARULUI PENTRU PROCEDURA DE ATRIBUIRE A EXECUŢIEI LUCRĂRILOR: 2 LUNI

RAPORT FINANCIAR FINAL: 1 LUNĂ.

• ETAPA III: 36 LUNI

ASISTENȚĂ TEHNICĂ ACORDATĂ BENEFICIARULUI PE DURATA EXECUŢIEI LUCRĂRILOR, CU CONDIŢIA DEMARĂRII LUCRĂRILOR NU MAI TÂRZIU DE 3 ANI DE LA APROBAREA PROIECTULUI TEHNIC.

6AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA

AUTOSTRADA TARGU

MURES - TARGU NEAMT 0+000 211+000

PROIECTANT: INGENIERIA

ESPECIALIZADA OBRA CIVIL E

INDUSTRIAL SA

TARGU MURES - TARGU NEAMT LOT 1 211 52% 11% 28.05.2019

25.07.2021

(CONFORM ACT

ADITIONAL LA

CTR DE PRESTARI

SERVICII)

ANUL 2021 - FINALIZARE

PROIECTARE

2025 - PERIOADA ESTIMATA

PENTRU DESCHIDEREA

PRIMELOR SECTIUNI

17.58 MIL. LEI

FARA TVA

IN DATA DE 28.05.2019 A FOST SEMNAT CONTRACTUL DE SERVICII 92/36788 AFERENT „COMPLETARE STUDIU DE FEZABILITATE PENTRU AUTOSTRADA TARGU MURES – TARGU NEAMT”.

TERMEN INITIAL DE FINALIZARE A REVIZUIRII STUDIULUI DE FEZABILITATE - 25.01.2021.

CONTRACT DE REVIZUIRE SF IN DERULARE

IN DATA DE 31.07.2020 A FOST SEMNAT ADITIONALUL NR. 1, PRIN CARE SE PRELUNGESTE TERMENUL DE FINALIZARE AL SERVICIILOR DE PROIECTARE CU 6 LUNI.

TERMEN DE FINALIZARE CONFORM ACT ADITIONAL - 25.07.2021

EMITEREA DECIZIEI ETAPEI DE INCADRARE INITIALE ANPM IN DATA DE 18.09.2020.

IN DATA DE 31.09.2020 A AVUT LOC SEDINTA PENTRU AVIZAREA IN CTE / CNAIR A TRASEULUI CORECTAT CONFORM CONSTRANGERILOR IDENTIFICATE. PENTRU FINALIZAREA AVIZARII CTE A FOST SOLICITATA COMPLETAREA DOCUMENTATIEI.

IN DATA DE 05.11.2020 A FOST AVIZAT TRASEUL FINAL IN COMISIA CTE CNAIR.

IN DATA DE 27.01.2021 A FOST APROBAT STUDIU TOPOGRAFIC. MASURATORI TOPOGRAFICE CU TEHNOLOGIA LIDAR

IN DATA DE 25.03.2021 A FOST APROBAT STUDIUL GEOTEHNIC AFERENT TRONSON: DITRAU - TARGU NEAMT, SECTOR 4 KM 95+600 – KM 118+800.

AU FOST FINALIZATE INVESTIGATIILE IN SITU PE JUD. MURES SI JUD. HARGHITA SI AU FOST AVIZATE STUDIILE ARHEOLOGICE ETAPA 2 JUD. HARGHITA SI JUD. MURES

- IN DATA DE 16.04.2021 A FOST INAINTATA O VARIANTA PRELIMINARA A STUDIULUI DE FEZABILITATE

AU FOST FINALIZATE INVESTIGATIILE IN SITU PE JUD. NEAMT SI JUD. IASI SI AU FOST AVIZATE STUDIILE ARHEOLOGICE ETAPA 2 JUD. NEAMT SI JUD. IASI

A FOST EMISA DECIZIA ETAPEI DE INCADRARE CU NR. 90 DIN 22.06.2021

AU FOST FINALIZATE INVESTIGATIILE GEOTEHNICE IN TEREN.

IN DATA DE 09.08.2021 A FOST INAINTAT STUDIUL DE FEZABILITATE PENTRU AUTOSTRADA TARGU MURES-TARGU NEAMT_REV1. IN DATA DE 30.07.2021 AU FOST EMISE OBSERVATII

IN PREZENT DOCUMENTATIA ESTE REVIZUITA DE CATRE PRESTATOR

AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) - OCTOMBRIE 2021

Page 6: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

7AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA

AUTOSTRADA

TIMISOARA - MORAVITA0+000 60+000

SEARCH CORPORATION & EGIS

ROMANIA- CONTRACT PROIECTARE

ELABORARE SF SEMNAT IN DATA DE

4 MARTIE 2020

(VALOARE CONTRACT PROIECTARE:

8.727.474,68 FARA TVA)

TIMISOARA – MORAVITA LOT 1 6004.03.2020 -

ELABORARE SF

MAI 2022 -

TERMEN

FINALIZARE

PROIECTARE;

PERIOADA

CONTRACTUALA

DE PRESTARE A

SERVICIILOR - 24

LUNI

MAI 2022 - TERMEN

FINALIZARE PROIECTARE

141.6 MIL. LEI

FARA TVA

ETAPA DE PROIECTARE (ELABORARE STUDIU DE FEZABILITATE) IN DERULARE.

S-A AVIZAT IN CTE-CNAIR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU, ETAPA 1

A FOST TRANSMISA DOCUMENTATIA AMC ETAPA 2 REVIZIA 3.

DOCUMENTATIA AMC 2 REVIZIA 3 SE AFLA LA JASPERS PENTRU OBSERVATII.

8AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA

AUTOSTRADA BACAU -

PASCANI0+000 77+394

INGINERIA ESPECIALIZADA OBRA

CIVIL E INDUSTRIAL SA - CONTRACT

ELABORARE SF SI PT IN DERULARE

(VALOARE CONTRACT PROIECTARE:

16.950.944,23 FARA TVA)

BACAU - PASCANI LOT 1 77.283 0% 23%

ORDIN DE

INCEPERE

01.03.2019 -

ETAPA

PROIECTARE

2021ANUL 2021 - FINALIZARE

ETAPA PROIECTARE

1750.27 MIL. LEI

FARA TVA

ACTIVITATE DE PROIECTARE IN DERULARE/ FINALIZARE ANALIZA MULTICRITERIALA, AVIZARE IN CTE/ STABILIRE PROFIL DE AUTOSTRADA

AU FOST INAINTATE OBSERVATII PENTRU STUDIU DE FEZABILITATE,

A FOST EFECTUATA EVALUAREA DE IMPACT ASUPRA SIGURANTEI RUTIERE.

IN DATA DE 19.07.2021 A FOST INAINTAT STUDIUL DE FEZABILITATE REVIZUIT, AU FOST EMISE OBSERVATII

AU FOST EMISE OBSERVATII ASUPRA STUDIULUI DE FEZABLITATE REV 3 IN DATA DE 09.08.2021. OBSERVATIILE CU PRIVIRE LA STUDIUL GEOTEHNIC AU FOST EMISE IN DATA DE 13.08.2021.

IN DATA DE 02.08.2021 A FOST INAINTAT PROIECTUL TEHNIC, IN FORMAT ELECTRONIC.

ASUPRA PROIECTULUI TEHNIC BENEFICIARUL A EMIS OBSERVATII IN DATA DE 23.08.2021.

9AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA

AUTOSTRADA BUZAU -

FOCSANI0+000 82+440

CONSITRANS - CONTRACT

ELABORARE SF SI PT

(VALOARE CONTRACT PROIECTARE:

13.933.291,10 LEI, FARA TVA)

BUZAU - FOCSANI 82.44 23.75%

ORDIN DE

INCEPERE

12.11.2018 -

ETAPA

PROIECTARE

2021 FINALIZARE 20211270.62 MIL. LEI

FARA TVA

CONTRACT PROIECTARE IN DERULARE - ETAPA ELABORARE STUDIU DE FEZABILITATE ANALIZA MULTICRITERIALA ETAPA 1 SI ETAPA 2.

A FOST AVIZAT IN CADRUL CTE CNAIR STUDIUL SI RAPORTUL ALTERNATIVELOR DE TRASEU (AMC 1 SI AMC 2)

INVESTIGATIILE GEOTEHNICE AU FOST REALIZATE IN PROPORTIE DE 100%. IN CURS DE ELABORARE TESTELE DE LABORATOR.

A FOST AVIZAT IN CADRUL COMISIEI TEHNICE PENTRU SIGURANTA CIRCULATIEI NODURILE RUTIERE SI DOTARILE AUTOSTRAZII.

A FOST INAINTAT IN DATA DE 21.09.2021 STUDIUL DE FEZABILITATE FINAL.

PRESTATORUL A PREDAT IN DATA DE 17.09.2021 STUDIUL GEOTEHNIC FINAL - AU FOST EMISE OBSERVATII

A FOST INAINTAT PROIECTULUI TEHNIC - AU FOST EMISE OBSERVATII

10AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA

AUTOSTRADA FOCSANI -

BACAU0+000 96+052

CONSITRANS - CONTRACT

ELABORARE SF SI PT

(VALOARE CONTRACT PROIECTARE:

20.123.408,52 LEI, FARA TVA)

FOCSANI - BACAU 96.052 0% 0.37%

ORDIN DE

INCEPERE

10.01.2019 -

ETAPA

PROIECTARE

2021ANUL 2021 - FINALIZARE

ETAPA PROIECTARE

1927.35 MIL. LEI

FARA TVA

ETAPA DE PROIECTARE (ELABORARE STUDIU DE FEZABILITATE) IN DERULARE.

S-A AVIZAT IN CADRUL CTE CNAIR SA - STUDIUL SI RAPORTUL ALTERNATIVELOR DE TRASEU (ANALIZA MULTICRITERIALA ETAPA 1 SI ANALIZA MULTICRITERIALA ETAPA 2).

AU INCEPUT INVESTIGATIILE ARHEOLOGICE.

STUDIILE GEOTEHNICE IN CURS DE REALIZARE-PROCENTUL DE REALIZARE ESTE DE 61%.

STUDIUL ARHEOLOGIC ETAPA NR. 2 A FOST TRANSMIS LA MINISTERELE DE CULTURA DE PE RAZA JUDETELOR VRANCEA SI BACAU IN VEDEREA OBTINERII AVIZELOR.

IN DATA DE 09.03.2021 AU FOST ANALIZATE IN CADRUL COMISIEI TEHNICE PENTRU SIGURANTA CIRCULATIEI NODURILE RUTIERE SI DOTARILE AUTOSTRAZII

IN DATA DE 05.05.2021 A FOST INAINTAT STUDIUL DE FEZABILITATE SUB FORMA DRAFT- AU FOST EMISE OBSERVATII

11AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA

AUTOSTRADA SIBIU -

PITESTI44+800 68+000

SECTIUNEA 6, CONEXIUNE DN 73C

CU AUTOSTRADA SIBIU - PITESTI

(NOD TIGVENI) SI MODERNIZARE DN

73C (KM 44+800 – KM 68+000)

SECTIUNEA 6 23.2 0% 0% 2022 2023ANUL 2023 - FINALIZARE

PROIECTARE

VALORI

ESTIMATE: 2.099

MIL. LEI FARA TVA

- TIGVENI -

CURTEA DE

ARGES

3.926 MIL. LEI

FARA TVA -

AUTOSTRADA

SIBIU - PITESTI

DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL DE MAI JOS

12AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA

AUTOSTRADA PLOIESTI -

BRASOVSC CONSITRANS S.R.L.

PLOIESTI - BRASOV (FARA SECTOR

RASNOV - CRISTIAN)97.3 0% 0%

2021 -

DEMARARE

SERVICII DE

PROIECTARE FAZA

S.F. + P.A.C. +

P.T.E.

2023 -

FINALIZARE

SERVICII DE

PROIECTARE FAZA

S.F. + P.A.C. +

P.T.E.

1000.8 MIL. LEI

FARA TVA

CONTRACT IN DERULARE.

S-AU EFECTUAT VIZITE IN TEREN CU REPREZENTANTI DIN PARTEA BENEFICIARULUI SI DIN PARTEA PRESTATORULUI PENTRU IDENTIFICAREA EVENTUALELOR CONSTRANGERI.

A FOST APROBAT DE CATRE BENEFICIAR RAPORTUL DE PROGRES NR. 5.

13AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA POD PESTE PRUT LA

UNGHENI

S.C. EXPERT PROIECT 2002 S.R.L. POD PESTE PRUT LA UNGHENI 1 80% 45%

2016 -

DEMARARE

PROIECTARE POD

UNGHENI; 2020 -

DEMARARE

PROIECTARE

SECTIUNEA IASI -

UNGHENI

2021 -

FINALIZARE

PROIECTARE FAZA

SF, DEMARARE

SERVICII DE

PROIECTARE SI

EXECUTIE POD

UNGHENI

ANUL 2024 - DESCHIDERE

TRAFIC POD PESTE PRUT LA

UNGHENI

0.8 MIL. LEI FARA

TVA

2.POD UNGHENI - STUDIU DE FEZABILITATE FINALIZAT CU EXCEPTIA ACORDULUI DE MEDIU ;

PROCEDURA DE MEDIU IN DERULARE

OBTINERE DEROGARE DE LA ART ART. 23 ALIN. (2) SI ALE ART. 27 ALIN. (1) DIN ORDONANTA DE URGENTA A GUVERNULUI

NR. 57/2007 PRIVIND REGIMUL ARIILOR NATURALE PROTEJATE, PRIN OUG NR. 105/2020, SEMNARE MEMORANDUM IN VEDERE PROMOVARII ACORDULUI BILATERAL ROMANIA-MOLDOVA NECESAR OBTINERII ACORDULUI DE MEDIU.

ESTE IN PREGATIRE LA MTIC ACORDUL BILATEARAL ROMANIA-MOLDOVA.

IN DATA DE 24.08.2020 A FOST EMISA DECIZIA ETAPEI DE EVALUARE INITIALA DE CATRE A.N.P.M. IASI.

IN DATA DE 24.08.2020 A FOST EMISA DECIZIA ETAPEI DE INCADRARE INITIALA NR. 133/2020 ANMP .

PENTRU CONTINUAREA PROCEDURII DE OBTINERE A ACORDULUI DE MEDIU S-A TRANSMIS MEMORIUL DE PREZENTARE CATRE APM IASI.

IN DATA DE 22.02.2021 A FOST EMISA DECIZIA ETAPEI DE INCADRARE NR. 15 DE CATRE APM IASI.

14AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA A4 16+700 16+700 SEARCH CORPORATION SRL

ELABORARE STUDIU DE

FEZABILITATE SI PROIECT TEHNIC DE

EXECUTIE PENTRU NOD RUTIER

CUMPANA A4 (KM 16+700)-DN 39E

0% 0% 26.10.2020 NOIEMBRIE 2021

NOIEMBRIE 2021 -

FINALIZAR E PROIECT

TEHNIC

674,39 MIL LEI

FARA TVA

CONTRACT SEMNAT IN DATA DE 23.09.2020.

ORDINUL DE INCEPERE A ACTIVITATII DE PROIECTARE A FOST EMIS IN DATA DE 26.10.2020

DURATA CONTRACTULUI ESTE DE 8 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI, DIN CARE:

-3 LUNI PENTRU ELABORAREA STUDIULUI DE FEZABILITATE,

- 2 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA LUCRARILOR DE CONSTRUIRE,

- 1 LUNI PENTRU ELABORAREA PROIECTULUI TEHNIC DE EXECUTIE SI

- 1 LUNI PENTRU ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFICIARULUI.

A AVUT LOC SEDINTA DE INCEPUT IN DATA DE 26.10.2020.

S-A EMIS ORDINUL ADMINISTRATIV NR. 1 - APROBARE EXPERTI NON CHEIE.

CTR SUSPENDAT, ACTIVITATEA FIIND RELUATA INCEPAND CU DATA DE 16.04.2021

A FOST AVIZATA IN CADRUL CTE CNAIR IN DATA DE 20.05.2021 ANALIZA MULTICRITERIALA ETAPA 1.

AU FOST FINALIZATE STUDIILE GEOTEHNICE, TERMENUL ESTIMAT DE PREDARE A STUDIULUI DE FEZABILITATE ESTE 31 AUGUST 2021 SI ELABORARE PROIECT TEHNIC - NOIEMBRIE 2021

15AUTOSTRAZI IN PREGATIRE FAZA

PROIECTARE (SF, PT)AUTOSTRADA A1 , A2 si A3 SEARCH CORPORATION SRL

ELABORARE STUDIU DE

FEZABILITATE SI PROIECT TEHNIC DE

EXECUTIE PENTRU 3 NODURI

RUTIERE PE A1, A2, A3 IN ZONA DE

SUD EST A ROMANIEI

NOD RUTIER AUTOSTRADA A1

KM 73+100 CU DJ702F LA

IONESTI;

NOD RUTIER AUTOSTRADA A2

KM 90+100 CU DJ 306 SI

DN3A LA DRAGOS VODA;

NOD RUTIER AUTOSTRADA A3

KM 36+700 CU DJ 101C LA

GRUIU (SECTOR BUCUREȘTI –

PLOIESTI);

0% 0% 24.06.2021 24.04.2020

CONTRACT SEMNAT IN DATA DE 20.05.2021

ORDINUL DE INCEPERE A ACTIVITATII DE PROIECTARE A FOST EMIS IN DATA DE 24.06.2021

DURATA CONTRACTULUI ESTE DE 10 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI, DIN CARE:

- 4 LUNI PENTRU ELABORAREA STUDIULUI DE FEZABILITATE,

- 3 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA LUCRARILOR DE CONSTRUIRE,

- 2 LUNI PENTRU ELABORAREA PROIECTULUI TEHNIC DE EXECUTIE SI

- 1 LUNA PENTRU ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFICIARULUI.

IN DATA DE 30.08.2021 PRESTATORUL A TRANSMIS AMC. IN DATA DE 16.09.2021 AU FOST TRANSMISE PRESTATORULUI OBSERVATII LA AMC.

Page 7: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1DRUMURI DE MARE VITEZA IN FAZA

PROIECTARE (SF, PT)DRUM DE MARE VITEZA

DRUM DE MARE VITEZA

BAIA MARE - DEJ -

BISTRITA - VATRA

DORNEI - SUCEAVA

0+000 145+000 BAIA MARE - DEJ - BISTRITA LOT 1 145 ESTIMAT 2022 2024 ANUL 20246681.19 MIL. LEI

FARA TVA

PROCEDURA DE ACHIZITIE PENTRU LOTUL 1 A FOST ANULATA

DETALII STADIU PROCEDURA DE ATRIBUIRE IN LINK-UL DE MAI JOS.

2DRUMURI DE MARE VITEZA IN FAZA

PROIECTARE (SF, PT)DRUM DE MARE VITEZA

DRUM DE MARE VITEZA

BAIA MARE - DEJ -

BISTRITA - VATRA

DORNEI - SUCEAVA

145+000 228+000 SC EXPLAN SRL BISTRITA - VATRA DORNEI LOT 2 83 2021 2023 ANUL 2023

15.8 MIL LEI FARA

TVA (VALOARE

CONTRACT

ELABORARE S.F.)

IN DATA DE 10.03.2021, CNAIR A SEMNAT CONTRACTUL PENTRU ELABORARE STUDIU DE FEZABILITATE DRUM DE MARE VITEZA VITEZA BAIA MARE - SUCEAVA, LOT 2 BISTRITA - VATRA DORNEI CU OFERTANTUL SC EXPLAN SRL., CU O VALOARE DE 15.793.026,12 LEI

FARA TVA.

IN DATA DE 14.09.2021 A FOST INAINTATA DOCUMENTATIA ANALIZA MULTICRITERIALA 1. IN PREZENT ESTE IN ANALIZA (TERMEN 04.10.2021)

3DRUMURI DE MARE VITEZA IN FAZA

PROIECTARE (SF, PT)DRUM DE MARE VITEZA

DRUM DE MARE VITEZA

BAIA MARE - DEJ -

BISTRITA - VATRA

DORNEI - SUCEAVA

228+000 335+000

ASOCIEREA BEST CONSULTING &

DESIGN S.R.L. – INGENIERIA

ESPECIALIZADA OBRA CIVIL E

INDUSTRIAL S.A.

VATRA DORNEI-SUCEAVA LOT 3 107 2021 2023 ANUL 2023

14.48 MIL LEI

FARA TVA

(VALOARE

CONTRACT

ELABORARE S.F.)

IN DATA DE 10.03.2021, CNAIR A SEMNAT CONTRACTUL PENTRU ELABORARE STUDIU DE FEZABILITATE DRUM DE MARE VITEZA BAIA MARE - SUCEAVA, LOT 3 VATRA DORNEI – SUCEAVA CU ASOCIEREA BEST CONSULTING & DESIGN SRL – INGENIERIA ESPECIALIZADA

OBRA CIVIL E INDUSTRIAL, CU PRETUL DE 14.475.000,00 LEI FARA TVA.

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRESDRUM EXPRES BRAILA -

GALATI0+000 11+088

ASOCIEREA SC SA & PE CONSTRUCT

SRL (LIDER DE ASOCIERE) -

SPEDITION UMB - TEHNOSTRADE

S.R.L.

BRAILA - GALATI LOT 1 11.08 0% 0%

ORDIN DE

INCEPERE

01.07.2021 -

ETAPA

PROIECTARE

MAI 2024 ANUL 2024371.42 MIL. LEI

FARA TVA

IN DATA DE 15.04.2021, CNAIR A SEMNAT CONTRACTUL PENTRU ""PROIECTAREA SI EXECUTIA DRUMULUI EXPRES BRAILA - GALATI” CU ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.

VALOAREA CONTRACTULUI ESTE DE 371.416.131,09 LEI FARA TVA.

SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE.

DURATA CONTRACTULUI ESTE DE 34 LUNI, DIN CARE 10 LUNI PERIOADA DE PROIECTARE SI 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR. PERIOADA DE GARANTIE ESTE DE 120 DE LUNI.

2 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES

DRUM EXPRES CRAIOVA

- PITESTI 0+000 17+700 TIRRENA SCAVI S.P.A. (ITALIA)TRONSON 1 - CRAIOVA - ROBANESTI

(KM 0+000 - KM 17+700)

SECTOR 1: 0+000 - 1+800

SECTOR 2: 1+800 - 10+000

SECTOR 3: 10+000 - 17+700

17.7 38.06% 28.20%

27.12.2018 -

PROIECTARE;

16.09.2019 -

EXECUTIE SECTOR

3 ;

13.07.2020 -

EXECUTIE SECTOR

1;

01.03.2021 -

EXECUTIE SECTOR

2 - km 5+245 - km

10+000

TRIM IV 2022 ANUL 2022358.18 MIL. LEI

FARA TVA

SECTOR 1: 0+000 - 1+850

IN DATA DE 03.07.2020 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE.

INCEPAND CU DATA DE 13.07.2020 A FOST EMIS ORDINUL DE INCEPERE EXECUTIE LUCRARI

SECTOR 2: 1+850 - 10+000

IN DATA DE 22.02.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE.

INCEPAND CU DATA DE 01.03.2021 A FOST EMIS ORDINUL DE INCEPERE EXECUTIE LUCRARI

SECTOR 3: 10+000 - 17+700 – IN EXECUTIE

IN DATA DE 22.05.2019 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE PENTRU SUPRAFETELE AFERENTE DOMENIUL PUBLIC. IN DATA DE 05.07.2019 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE.

INCEPAND CU DATA DE 16.09.2019 A FOST EMIS ORDINUL DE INCEPERE EXECUTIE LUCRARI

3 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES

DRUM EXPRES CRAIOVA

- PITESTI 17+700 36+200

ASOCIEREA SA & PE CONSTRUCT SRL -

SC SPEDITION UMB SRL - SC

TEHNOSTRADE SRL - SC CONSITRANS

SRL

TRONSON 2 - ROBANESTI - PIATRA

OLT (KM 17+700 - KM 57+550)

Lot 1 km 17+700 - km 36+200

LOT 1: KM 17+700 - KM

36+20018.5 88.86% 63.25

21.12.2018 -

ACTIVITATEA DE

PROIECTARE,

24.09.2019 -

EXECUTIE

(ETAPELE I, II SI

III), 21.11.2019 -

EXECUTIE (ETAPA

IV)

TRIM IV 2021 ANUL 2022661.45 MIL. LEI

FARA TVA

DRUMURI EXPRES PROIECTE IN EXECUTIE - OCTOMBRIE 2021

DRUMURI DE MARE VITEZĂ

DRUMURI EXPRES

DRUMURI DE MARE VITEZA IN FAZA PROIECTARE (SF, PT) - OCTOMBRIE 2021

Page 8: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

4 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES

DRUM EXPRES CRAIOVA

- PITESTI 36+000 57+500

ASOCIEREA SA & PE CONSTRUCT SRL -

SC SPEDITION UMB SRL - SC

TEHNOSTRADE SRL - SC CONSITRANS

SRL

TRONSON 2 - PIATRA OLT - VALEA

MARE (KM 17+700 - 57+550)

Lot 2 - km 36+200 - km 57+550

LOT 2: KM 36+200 - KM

57+55021.35 86.29% 63.33%

21.12.2018 -

ACTIVITATEA DE

PROIECTARE,

24.09.2019 -

EXECUTIE

(ETAPELE I, II SI

III), 21.11.2019 -

EXECUTIE (ETAPA

IV)

TRIM IV 2021 ANUL 2022792.18 MIL. LEI

FARA TVA

5 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRESDRUM EXPRES CRAIOVA

- PITESTI89+300 121+115

ASOCIEREA SA & PE CONSTRUCT SRL -

SC SPEDITION UMB SRL - SC

TEHNOSTRADE SRL

TRONSON 4

COLONESTI - OARJA - PITESTITRONSON 4 31.82 0% 0% 2021 2024 ANUL 2024

617.08 MIL. LEI

FARA TVA

ANTREPRENORUL A CONSTITUIT GARANTIA DE BUNA EXECUTIE, IN CONFORMITATE CU PREVEDRILE CONTRACTUALE, ACEASTA FIIND APROBATA DE CATRE C.N.A.I.R. S.A. IN DATA DE 02.09.2021.

DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE:

• 12 LUNI PERIOADA DE PROIECTARE,

• 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,

• 120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.

INCEPAND CU DATA DE 15.11.2021 VA EMIS ORDIN DE INCEPERE.

6 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRESDRUM EXPRES CRAIOVA

- PITESTI57+550 89+300

ASOCIEREA SA & PE CONSTRUCT SRL -

SC SPEDITION UMB SRL - SC

TEHNOSTRADE SRL

TRONSON 3, VALEA MARE -

COLONESTITRONSON 3 31.75 0% 0% 18.01.2021 2024 ANUL 2024

670.71 MIL. LEI

FARA TVA

ANTREPRENORUL A CONSTITUIT GARANTIA DE BUNA EXECUTIE, IN CONFORMITATE CU PREVEDRILE CONTRACTUALE, ACEASTA FIIND APROBATA DE CATRE C.N.A.I.R. S.A. IN DATA DE 10.11.2020.

DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE:

• 12 LUNI PERIOADA DE PROIECTARE,

• 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,

• 120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.

INCEPAND CU DATA DE 18.01.2021 A FOST EMIS ORDIN DE INCEPERE.

PAC AVIZAT IN CADRUL CTE IN LUNA MARTIE 2021

7 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES DRUM DE LEGATURA A3 0+000 18+960 SC STRABAG SRL

LEGATURA CENTURA ORADEA

(GIRATIA SANTANDREI) -

AUTOSTRADA A3 (BIHARIA)

18.96 0% 0% 27.09.2021 2024 ANUL 2024545.9 MIL. LEI

FARA TVA

IN DATA DE 21.07.2021 A FOST SEMNAT CONTRACTUL DE PROIECTARE SI EXECUTIE CU STRABAG S.R.L.

DURATA CONTRACTULUI ESTE DE 30 DE LUNI, DIN CARE:

6 DE LUNI PERIOADA DE PROIECTARE,

24 DE LUNI PERIOADA DEEXECUTIE A LUCRARILOR.

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1DRUMURI EXPRES IN PREGATIRE FAZA

PROIECTARE (SF, PT)DRUM EXPRES

DRUM EXPRES BACAU -

PIATRA NEAMT0+000 61+000

SEARCH CORPORATION & EGIS

ROMANIA

(VALOARE CONTRACT PROIECTARE:

8,923,930.03 LEI, FARA TVA)

BACAU - PIATRA NEAMT LOT 1 61 0% 0%

MARTIE 2020 -

ETAPA

PROIECTARE

SEPTEMBRIE 2021

- TERMEN

FINALIZARE

PROIECTARE;

PERIOADA

CONTRACTUALA

DE PRESTARE A

SERVICIILOR - 18

LUNI

APRILIE 2022 - TERMEN

FINALIZARE PROIECTARE

(CONFORM AA NR. 2 DIN

08.09.2021)

1123.86 MIL. LEI

FARA TVA

CONTRACT ELABORARE SF IN DERULARE.

IN DATA DE 14.07.2021 A FOAT AVIZATA AMC 1 IN CADRUL CTE CNAIR S.A.

DOCUMENTATIA AMC 2 ESTE IN ANALIZA LA JASPERS.

2DRUMURI EXPRES IN PREGATIRE FAZA

PROIECTARE (SF, PT)DRUM EXPRES

DRUM EXPRES BRAILA -

TULCEA (JIJILA -

CATALOI)

0+000 59+700

INGINERIA ESPECIALIZADA OBRA

CIVIL E INDUSTRIAL SA - CONTRACT

PROIECTARE (ELABORARE STUDIU

DE FEZABILITATE SI PROIECT TEHNIC)

SEMNAT IN LUNA MAI 2020.

(VALOARE CONTRACT PROIECTARE:

14.159.206,13 LEI, FARA TVA)

BRAILA - TULCEA LOT 1 59.7 0% 0%

IUNIE 2020 -

ETAPA

PROIECTARE

IUNIE 2022

FEBRUARIE 2023- TERMEN

FINALIZARE PROIECTARE

(CONFORM AA NR. 3)

1674.75 MIL. LEI

FARA TVA

CONTRACT ELBORARE S.F. IN DERULARE.

DOCUMENTATIA AMC ETAPA 1 REVIZIA 2 A FOST TRANSMISA CONSULTANTILOR JASPERS PENTRU OBSERVATII.

DOCUMENTATIA AMC ETAPA 1 REVIUITA A FOST RETRANSMISA CONSULTANTILOR JASPERS PENTRU OBSERVATII IN DATA DE 10.05.2021.

IN DATA DE 09.06.2021 FOST ORGANIZATA O NOUA SEDINTA CU EXPERTII JASPERS.

IN PREZENT PRESTATORUL IMPLEMENTEAZA OBSERVATIILE EMISE DE CATRE EXPERTII JASPERS IN CADRUL DOCUMENTATIEI AMC ETAPA 1.

PRESTATORUL ANALIZEAZA NOILE PROPUNERII DE AMENAJARE A DRUMULUI DE LEGATURA LA PUNCTUL DE TRECERE A FRONTIERE ISACCEA IN CONFORMITATE CU SOLICITARILE PRIMARIEI ISACCEA.

3DRUMURI EXPRES IN PREGATIRE FAZA

PROIECTARE (SF, PT)DRUM EXPRES

DRUM EXPRES BUZAU -

BRAILA0+000 98+000

INGINERIA ESPECIALIZADA OBRA

CIVIL E INDUSTRIAL SA - CONTRACT

ELABORARE SF SI PT IN DERULARE

(VALOARE CONTRACT PROIECTARE:

16.591.031,97 LEI, FARA TVA)

BUZAU - BRAILA LOT 1 98 0% 0%

03.04.2020 -

ETAPA

PROIECTARE

APRILIE 2022

OCTOMBRIE 2022- TERMEN

FINALIZARE PROIECTARE

(CONFORM AA NR. 2)

1805.55 MIL. LEI

FARA TVA

CONTRACT ELABORARE SF IN DERULARE.

AMC - ETAPA 1 SE AFLA IN ANALIZA CONSULTANTILOR JASPERS.

DOCUMENTATIA AMC 1 SE AFLA IN CURS DE REVIZUIRE CONFORM OBSERVATIILOR JASPERS.

DOCUMENTATIA AMC 1 REVIZUIT A FOST TRANSMISA CATRE CNAIR, CARE A EMIS NOI OBSERVATII CATRE PRESTATOR.

IN DATA DE 26.05.2021 A FOST ORGANIZATA O NOUA SEDINTA CU CONSULTANTII JASPERS.IN PREZENT PRESTATORUL IMPLEMENTEAZA OBSERVATIILE DE CATRE EXPERTII JASPERS IN CADRUL DOCUMENTATIEI AMC ETAPA 1.

4DRUMURI EXPRES IN PREGATIRE FAZA

PROIECTARE (SF, PT)DRUM EXPRES

DRUM EXPRES CRAIOVA

- TARGU JIU

ASOCIEREA EGIS ROMANIA S.A. –

SEARCH CORPORATION S.R.LCRAIOVA - TARGU JIU 108 0% 0%

ORDIN DE

INCEPERE

16.04.2021 -

ETAPA

PROIECTARE

APRILIE 202320.25 MIL LEI

FARA TVA

IN DATA DE 17.03.2021 CNAIR A SEMNAT CU OFERTANTUL DECLARAT CASTIGATOR - ASOCIEREA EGIS ROMANIA S.A. – SEARCH CORPORATION S.R.L.

VALOAREA CONTRACTULUI ESTE DE 20.247.133,77 LEI FARA TVA, SURSA DE FINANTARE FIIND DIN FONDURI EUROPENE NERAMBURSABILE.

IN DATA DE 16.04.2021 A FOST SEDINTA DE INCEPUT (ORDINUL DE INCEPERE)

TERMENUL DE PREDARE AMC 1 (16.07.2021) A FOST DEPASIT DIN CAUZA UNOR OBIECTIVE SEVESO DEPISTATE IN ZONA DE INTERES A DRUMULUI EXPRES.

IN DATA DE 03.09.2021 PRESTATORUL A TRANSMIS AMC 1. IN DATA DE 21.09.2021 AU FOST TRANSMISE PRESTATORULUI OBSERVATII LA AMC 1.

5DRUMURI EXPRES IN PREGATIRE FAZA

PROIECTARE (SF, PT)DRUM EXPRES

DRUM EXPRES FOCSANI -

BRAILA0+000 76+000

INGENIERIA ESPECIALIZADA OBRA

CIVIL E INDUSTRIAL S.A.

SEMNAT IN DATA DE 19.06.2020

(VALOARE CONTRACT PROIECTARE:

15.001.446,99 LEI, FARA TVA)

FOCSANI - BRAILA 76 0% 15%

ORDIN DE

INCEPERE

27.07.2020 -

ETAPA

PROIECTARE

IULIE 2022ANUL 2022 - FINALIZARE

ETAPA PROIECTARE

1400.22 MIL. LEI

FARA TVA

CONTRACT SEMNAT IN DATA DE 19.06.2020.

ORDINUL DE INCEPERE 27.07.2020

DURATA CONTRACTULUI ESTE DE 24 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI

ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU, ETAPA 1 (AMC1) FOST AVIZATA IN CTE CNAIR SA.

A FOST APROBATA TEMA PENTRU STUDII ARHEOLOGICE ETAPA1 SI STUDIUL ARHEOLOGIC ETAPA 1.

IN CURS DE ELABORARE ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU ETAPA 2 (AMC 2).

DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) - OCTOMBRIE 2021

Page 9: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

6DRUMURI EXPRES IN PREGATIRE FAZA

PROIECTARE (SF, PT)DRUM EXPRES

DRUM EXPRES OVIDIU

(CONSTANTA) - TULCEA0+000 112+000

SEARCH CORPORATION & EGIS

ROMANIA- CONTRACT PROIECTARE

ELABORARE SF SI PROIECT TEHNIC

SEMNAT IN DATA DE 13.07. 2020

(VALOARE CONTRACT PROIECTARE:

17.845.626,28 LEI, FARA TVA)

CONSTANTA - TULCEA 112.5 0% 0%

ORDIN DE

INCEPERE

10.08.2020 -

ETAPA

PROIECTARE

Aug-22AUGUST 2022 - TERMEN

FINALIZARE PROIECTARE

2664.38 MIL. LEI

FARA TVA

CONTRACT IN DERULARE.

AMC ETAPA 1 ESTE IN CURS DE REVIZURIRE CONFORM OBSERVATIILOR JASPERS. PRESTATORUL ANALIZEAZA REALIZAREA UNOR DRUMURI DE LEGATURA CU MUN. TULCEA.

PRESTATORUL IMPREUNA CU CESTRIN ANALIZEAZA REALIZAREA DRUMURILOR EXPRES/DRUMURI DE LEGATURA LA DX8 IN CONFORMITATE CU DATELE/INFORMATIILE ACTUALIZATE TRANSMISE DE CATRE PRIMARIA TULCEA.

IN ANALIZA SOLICITAREA PRESTATORULUI DE PRELUNGIRE PERIOADA CONTRACTUALA.

7DRUMURI EXPRES IN PREGATIRE FAZA

PROIECTARE (SF, PT)DRUM EXPRES

DRUM EXPRES PASCANI -

SUCEAVA0+000 61+000

SEARCH CORPORATION SRL - EGIS

ROMANIA S.A - EGIS INTERNATIONAL

SAS.

CONTRACT PROIECTARE ELABORARE

SF SI PROIECT TEHNIC SEMNAT IN

DATA DE 07.09.2020 (VALOARE

CONTRACT DE PROIECTARE:

11,721,430.96 LEI FARA TVA)

PASCANI - SUCEAVA 61.86 0% 0% OCTOMBRIE 2020

OCTOMBRIE 2022

- FINALIZARE

ETAPA DE

PROIECTARE

1304.96 MIL. LEI

FARA TVA

CONTRACT IN DERULARE.

IN DATA DE 14.04.2021 A FOST AVIZATA IN CADRUL CTE-CNAIR SA DOCUMENTATIA AMC ETAPA 1. IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA 2. IN DATA DE 16.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 2. DOCUMENTATIA AMC ETAPA 2

ESTE IN ANALIZA LA BENEFICIAR.

DOCUMENTATIA AMC 2 A FOST AVIZATA IN CTE - CNAIR S.A. IN DATA DE 23.07.2021.

AU FOST OBTINUTE CERTIFICATELE DE URBANISM (SV, IS si BT)

IN PREZENT SE REALIZEAZA STUDII GEOTEHNICE.

8DRUMURI EXPRES IN PREGATIRE FAZA

PROIECTARE (SF, PT)DRUM EXPRES

DRUM EXPRES PLOIESTI -

GAESTI0+000 76+000

SEARCH CORPORATION & – MEGA

MUHENDISLIK MUSAVIRLIK A.S.

(MEGA ENGINEERING CONSULTING

INC.) - CONTRACT PROIECTARE

ELABORARE STUDIU DE

FEZABILITATE SI PROIECT TEHNIC DE

EXECUTIE SEMNAT IN DATA DE

25.08.2020 (VAL CTR PROIECTARE:

15.86 MIL LEI FARA TVA)

PLOIESTI - GAESTI 76 0% 0%

AUGUST 2020 –

DEMARARE

ETAPA DE

PROIECTARE

OCTOMBRIE 2022

- FINALIZARE

ETAPA DE

PROIECTARE

OCTOMBRIE 2022 -

TERMEN FINALIZARE

PROIECTARE

1671.37 MIL. LEI

FARA TVA

CONTRACT IN DERULARE.

PRESTATORUL A TRANSMIS DOCUMENTATIA ANALIZA MULTICRITERIALA DE TRASEU.

AU FOST EMISE OBSERVATII DIN PARTEA BENEFICIARULUI SI PRESTATORUL A TRANSMIS DOCUMENTATIA REVIZUITA.

IN DATA DE 09.04.2021 ANALIZA MULTICRITERIALA ETAPA 1 A FOST AVIZATA IN CADRUL C.T.E. CNAIR.

A FOST SUSPENDAT CONTRACTUL PENTRU O PERIOADA DE 3 LUNI INCEPAND CU DATA DE 18.05.2021.

IN DATA DE 18.08.2021 A FOST RELUATA ACTIVITATEA DE PROIECTARE.

9DRUMURI EXPRES IN PREGATIRE FAZA

PROIECTARE (SF, PT)DRUM EXPRES

DRUM EXPRES SUCEAVA

- SIRET0+000 40+000

SEARCH CORPORATION SRL - EGIS

ROMANIA S.A - EGIS INTERNATIONAL

SAS.

CONTRACT PROIECTARE ELABORARE

SF SI PROIECT TEHNIC SEMNAT IN

DATA DE 07.09.2020 (VALOARE

CONTRACT DE PROIECTARE:

10,092,839.13 LEI FARA TVA)

SUCEAVA- SIRET 56.17 0% 0% OCTOMBRIE 2020 OCTOMBRIE 2022882.9 MIL. LEI

FARA TVA

CONTRACT IN DERULARE.

DOCUMENTATIA ANALIZA MULTICRITERIALA DE TRASEU ESTE REVIZUITA CONFORM OBSERVATIILOR BENEFICIARULUI.

IN DATA DE 14.04.2021 A FOST AVIZATA IN CADRUL CTE-CNAIR SA DOCUMENTATIA AMC ETAPA 1. IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA 2. IN DATA DE 16.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 2. DOCUMENTATIA AMC ETAPA 2

ESTE IN ANALIZA LA BENEFICIAR.

DOCUMENTATIA AMC 2 A FOST AVIZATA IN CTE - CNAIR S.A. IN DATA DE 23.07.2021.

A FOST OBTINUT CERTIFICATUL DE URBANISM (SV)

IN PREZENT SE REALIZEAZA STUDII GEOTEHNICE.

10DRUMURI EXPRES IN PREGATIRE FAZA

PROIECTARE (SF, PT)DRUM EXPRES

DRUM EXPRES TISITA -

ALBITA0+000 160+000

SEARCH CORPORATION & EGIS

ROMANIA- CONTRACT PROIECTARE

ELABORARE STUDIU DE

FEZABILITATE SEMNAT IN DATA DE

09.07. 2020

(VALOARE CONTRACT PROIECTARE:

11.057.073,07 LEI FARA TVA)

TISITA - ALBITA 160 0% 0%

AUGUST 2020

DEMARARE

ETAPA DE

PROIECTARE

OCTOMBRIE 2022

- FINALIZARE

ETAPA DE

PROIECTARE

OCTOMBRIE 2022 -

TERMEN FINALIZARE ETAPA

DE PROIECTARE

3563.3 MIL. LEI

FARA TVA

CONTRACTUL IN DERULARE

A FOST TRANSMIS AMC ETAPA 1 SE AFLA IN CURS DE REVIZUIRE CONFORM OBSEVATIILOR BENEFICIARULUI.

PRESTATORUL ANALIZEAZA ETAPIZAREA SI FAZAREA OBIECTIVULUI DE INVESTITII CONFORM CERINTELOR CNAIR SI MTI. IN DATA DE 09.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 1. DOCUMENTATIA AMC ETAPA 1 ESTE IN ANALIZA LA BENEFICIAR.

DOCUMENTATIA AMC 1 REV 3 ETAPIZARE/FAZARE ESTE IN CURS DE REVIZUIRE IN CONFORMITATE CU OBSERVATIILE BENEFICIARULUI / MTI.

11DRUMURI EXPRES IN PREGATIRE FAZA

PROIECTARE (SF, PT)DRUM EXPRES

DRUM EXPRES OAR -

SATU MARE0+000 10+900

SEARCH CORPORATION SRL

SEMNAT IN DATA DE 10.07. 2020

(VALOARE CONTRACT PROIECTARE:

3.646.308,36 LEI FARA TVA)

SATU MARE - OAR (GRANITA

RO/HU)10.9 0% 3%

AUGUST 2020 -

DEMARARE

SERVICII DE

PROIECTARE FAZA

S.F. + P.A.C. +

P.T.E.

2022 -

FINALIZARE

SERVICII DE

PROIECTARE FAZA

S.F. + P.A.C. +

P.T.E.

ANUL 2022 - TERMEN

FINALIZARE FAZA DE

PROIECTARE

311.79 MIL. LEI

FARA TVA

IN DATA DE 10.07.2020 A FOST SEMNAT CONTRACTUL PROIECTARE SF+PAC/DTAC+PT

DURATA DE REALIZARE A CONTRACTULUI DE SERVICII ESTE DE 18 LUNI

IN DATA DE 10.08.2020 S-A DAT ORDINUL DE INCEPERE.

IN DATA DE 05.03.2021 A FOST AVIZATA IN CADRUL CTE CNAIR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU AMC1 + AMC2 (VARIANTA 1)

INVESTIGATIILE GEOITEHNICE SUNT REALIZATE IN PROCENT DE 70%.

IN DATA DE 17.05.2021 A FOST EMIS CERTIFICATUL DE URBANISM.

12DRUMURI EXPRES IN PREGATIRE FAZA

PROIECTARE (SF, PT)DRUM EXPRES A1 (PITESTI) - MIOVENI 0+000 10+000 SEARCH CORPORATION S.R.L. A1 (PITESTI) - MIOVENI 10 0% 0%

ORDIN DE

INCEPERE

09.12.2020 -

ETAPA DE

PROIECTARE

IULIE 2022 -

TERMEN

FINALIZARE

ETAPA DE

PROIECTARE

222.71 MIL. LEI

FARA TVA

CONTRACT IN DERULARE.

DOCUMENTATIA REVIZUITA AMC 1 A PRIMIT AVIZUL C.T.E. IN DATA DE 01.04.2021.

DOCUMENTATIA AMC ETAPA 2 A FOST AVIZATA IN CADRUL CTE-CNAIR S.A. IN DATA DE 24.06.2021.

PRESTATORUL A INAINTAT DOCUMENTATIA IN VEDEREA OBTINERII CERTIFICATULUI DE URBANISM. NU A FOST OBTINUT CERIFICATUL DE URBANISM (OPBSERVATII PRIMARIA MARACINENI SI INSTITUTUL POMICOL MARACINENI)

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL

DN794+150 107+745 ASTALDI S.P.A.

ARAD - ORADEA, KM 4+150 – KM

107+745 103.55 98% 98% 03.02.2009 REZILIAT IN FOLOSINTA

266.31 MIL. LEI

FARA TVA

PROBLEME:

CONTRACTUL A FOST REZILIAT DE CATRE BENEFICIAR IN DATA DE 02.10.2020 DATORITA INTARZIERILOR SI NEEXECUTARII LUCRARILOR RAMASE DE EXECUTAT DE CATRE ANTREPRENOR.

1. NEEXECUTAREA LUCRARILOR PENTRU PODUL DE LA KM 41+635

2. INTARZIEREA FINALIZARII EXECUTIEI LUCRARILOR

DRUMURI NATIONALE IN REABILITARE / MODERNIZARE - OCTOMBRIE 2021

DRUMURI NAȚIONALE

Page 10: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

2DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN 52 1+350 44+600

ASOCIEREA S.C. ALEXCOR TRADING

S.R.L. - IMPRESA DI COSTRUZIONI

ING. E. MANTOVANI S.P.A. – S.C.

PEGASUS ENGINEERING S.R.L.

ALEXANDRIA - TURNU MAGURELE 43.25

DATA INCEPERII

ACTIVITATII DE

PROIECTARE:

09.06.2020

126.323 MII LEI

FARA TVA -

VALOARE

PROIECTARE ȘI

EXECUȚIE PENTRU

AMBELE

SECTOARE

ORDINUL DE INCEPERE A EXECUTIEI LUCRARILOR SE VA DA DUPA OBTINEREA AUTORIZATIEI DE CONSTRUCTIEI

3DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN 52 49+194 52+649

ASOCIEREA S.C. ALEXCOR TRADING

S.R.L. - IMPRESA DI COSTRUZIONI

ING. E. MANTOVANI S.P.A. – S.C.

PEGASUS ENGINEERING S.R.L.

TURNU MAGURELE - PORT TURNU

MAGURELE3.455

DATA INCEPERII

ACTIVITATII DE

PROIECTARE:

09.06.2020

126.323 MII LEI

FARA TVA -

VALOARE

PROIECTARE ȘI

EXECUȚIE PENTRU

AMBELE

SECTOARE

ORDINUL DE INCEPERE A EXECUTIEI LUCRARILOR SE VA DA DUPA OBTINEREA AUTORIZATIEI DE CONSTRUCTIEI

4DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN7 251+475 254+315

S.C GEIGER TRANSILVANIA SRL –

SERVICII DE PROIECTARE SC CONSIS

PROIECT SRL IN CALITATE DE

SUBCONTRACTANT

REALIZARE LARGIRE VALEA OLTULUI

LA 4 BENZI DE CIRCULATIE INTRE KM

251+475 – KM 254+315

2.84 40% 25% 01.11.2019 SEPTEMBRIE 202122.141 MIL. LEI

FARA TVAA FOST OBTINUTA AC NR. 50 DIN DATA DE 04 SEPTEMBRIE 2020. ORDINUL ADMINITRATIV DE RELUARE A FOST DAT CU 21.09.2020.

5DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN5 7+573 19+220

ASOCIEREA EUROCOGEN - FILIALA

ANINOASA SRL & ALEANDRI SPA &

BEOZZO COSTRUZIONI SRL & SMART

BUILDING PROJET SRL

MODERNIZARE DN 5,

BUCURESTI – ADUNATII COPACENI

KM 7+573 - KM 19+220

DRUM MODERNIZAT -

LUCRARI FINALIZATE IN ANUL

2020

11.647 99.50% 93.80% 23.04.2015ESTIMAT

SEPTEMBRIE 2021

76.13 MIL. LEI

FARA TVAEXECUTIE LUCRARI

6DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN73 13+800 128+250

ASOCIEREA AZVI SA - STRACO GRUP

SRL - TRACTEBEL

MODERNIZARE: PITESTI -

CAMPULUNG - BRASOV

KM 13+800 - KM 42+850; KM

54+050 - KM 128+250

103.25 49.82% 51.00% 19.05.2014 DECEMBRIE 2023275.86 MIL. LEI

FARA TVA

A FOST RECEPTIONAT UN SECTOR DE 28,85 KM.

PENTRU RESTUL SECTORULUI CONTRACTUL ESTE IN CURS DE REZILIERE SI SE VA LANSA O PROCEDURA DE LICITATIE AVAND CA OBIECT ACTUALIZAREA PROIECTULUI PENTRU REST DE EXECUTAT.

DOCUMENTATIA DE ATRIBUIRE PENTRU SERVICII DE ACTUALIAZARE PROIECT FINALIZATA, PROCEDURA DE LICITATIE SUSPENDATA CA URMARE A UNOR CONTESTATII .

7DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN76 55+425 69+350

ASOCIEREA SC SYLC CON TRANS

SRL/HIDROSTROY ADIONESTI - VARFURILE LOT 3 13.93 97.50% 97.50% 15.03.2019

RECEPTIE LA

TERMINAREA

LUCRARILOR -

ESTIMAT

DECEMBRIE 2021

55.95 MIL. LEI

FARA TVARECEPTIE LA TERMINAREA LUCRARILOR - ESTIMAT DECEMBRIE 2021

8DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN56 47+000 84+020 MOCHLOS S.A. GALICEA MARE - CALAFAT LOT 2 33.83 100% 91.43% 03.09.2012 16.06.2021

81.94 MIL. LEI

FARA TVAPROCESUL VERBAL DE RECEPTIE LA TERMINAREA LUCRARILOR A FOST APROBAT DE DIRECTORUL GENERAL AL CNAIR IN DATA DE 16.06.2021.

9DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN76 69+350 102+660

ASOCIEREA SC DRUM ASFALT SRL –

VAHOSTAV SK A.S. – TRAMECO SA –

ILE VIOREL CONSTRUCT SRL.

VARFURILE - STEI LOT 4 33.31 84.68% 39.56% 29.06.2020

DECEMBRIE 2021 -

RECEPTIE LA

TERMINAREA

LUCRARILOR

DECEMBRIE 2026 -

RECEPTIE FINALA

ANUL 202174.78 MIL LEI

FARA TVA

CONTRACTUL PENTRU FINALIZAREA LUCRARILOR A FOST SEMNAT IN DATA DE 08.05.2020;

ORDINUL DE INCEPERE A LUCRARILOR A FOST EMIS IN DATA DE 29.06.2020;

PREDARE AMPLASAMENT - 02.07.2020.

10DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN71 0+000 109+905

LOT 1 - ASOCIEREA SC AQUA PARC

SRL - SC MAVGO HOLDING SRL -

HYDROSTROY AD - VDH AD

(VODSTROI 98 AD) - SC BDU MAXI

CONSTRUCT SRL

CONSTRUCTORUL A FOST NOTIFICAT

PENTRU REZILIERE

LOT 1 (SECTOR 1): BALDANA -

TARGOVISTE KM. 0+000 - KM

44+130 LARGIRE LA 4 BENZI

DE CIRCULATIE; LOT 2

(SECTOR 2): TARGOVISTE -

SINAIA KM. 51+041 - KM

109+905 - DRUM LA 2 BENZI)

102.99 0% 0%1567.03 MIL. LEI

FARA TVA

LOTUL 1 - IN DATA DE 14.01.2021 A FOST INAINTATA NOTIFICAREA DE REZILIERE.

LOTUL 2 - PROCEDURA RELUATA

PROCEDURA DE ACHIZITIE PUBLICA IN DERULARE

11DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN28B 0+000 76+758

ASOCIEREA SC AQUA PARC SRL - SC

MAVGO HOLDING SRL - VAHOSTAV -

SK A.S. - TRAMECO SA

MODERNIZARE DN28B, TARGU

FRUMOS – BOTOSANI, KM 0+000 –

KM 76+758

71.512 6% 10.10%

15.07.2020 -

ORDIN INCEPERE

PENTRU ETAPA

PROIECTARE

Aug-23 Aug-23267.31 MIL LEI

FARA TVA

CONTRACT PROIECTARE SI EXECUTIE IN DERULARE - SEMNAT IN DATA DE 20.05.2020.

AVIZAT PT CTE CNAIR 21.07.2021 AVIZAT PT CTE DRDP IASI - 09.06.2021 - AVIZAT DTAC DRDP IASI - 10.03.2021; AVIZAT DTAC CNAIR SA - 16.03.2021. AUTORIZATIE DE CONSTRUIRE NR. 21/12.05.2021 EMISA DE MTIC.

12DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN29D 2+800 48+146

ASOCIEREA SC AUTOTEHNOROM SRL

- SC OPR ASFALT SRL - OBRAS

PUBLICAS-Y REGADIOS SA - SC

EVALCONS TECH SRL

MODERNIZARE DN29D BOTOSANI -

STEFANESTI KM 2+800 – KM 18+500

SI KM 18+800 – KM 48+146

45.046 12% 2%

22.06.2020 -

EMITERE ORDIN

DE INCEPERE

PENTRU ETAPA

PROIECTARE

MARTIE 2023208.44 MIL LEI

FARA TVA

IN DATA DE 29.06.2020 A FOST DEPUSA APLICATIA DE FINANTARE PENTRU ANGAJAREA CHELTUIELILOR AFERENTE ACESTUI PROIECT, DIN FONDURI NERAMBURSABILE, ALOCALTE IN CADRUL POIM 2014 - 2020

CONTRACT PROIECTARE SI EXECUTIE IN DERULARE

IN DATA DE 08.01.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUCTIE

TERMEN DE PREDARE A PROIECTULUI TEHNIC DE EXECUTIE: 28.02.2021

PT - AVIZAT CNAIR SA NR. 5035/26.03.2021

Page 11: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

13DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN7 30+950 52+350

LARGIRE LA 4 BENZI A DN7,

BALDANA-TITU, KM 30+950-KM

52+350

21.4

ESTIMAT

SEMNARE

CONTRACT IN

IPOTEZA FARA

CONTESTATIE:

MARTIE 2021

DECEMBRIE 2023 DECEMBRIE 2023210.63 MIL. LEI

FARA TVA

04.11.2020 A AVUT LOC DEPUNEREA OFERTELOR PENTRU PROCEDURA DE ATRIBUIRE A CONTRACTULUI "PROIECTARE TI EXECUTIE LARGIRE LA 4 BENZI A DN 7, BALDANA-TITU, KM 30+950 – KM 52+350”.

PANA LA TERMENUL LIMITA AU DEPUS OFERTE URMATORII AGENTI ECONOMICI:

1. ASOCIEREA CLAY WORK BUCHAREST - DIMAKS TURIZM INSAAT ENERJI AKARYAKIT NAK. VE TAS. GIDA TEM. OTOM. OTO. KIR.ITH. IHR. SAN.VE.TIC.LTD.STI. ISTANBUL;

2. ASOCIEREA COSEDIL SPA – SC BIT INVEST SRL - CHIRULLI ANDREA IMPRESA INDIVIDUALE – SC TOTAL ROAD SRL;

3. ASOCIEREA SC G&M ROAD BUILDING ENGINEERING SRL – SC KIRLIC GROUP SRL – SC BUILDING DESIGN 2000 TOP SRL – SC IRIMAT CONS S.R.L. - D'AGOSTINO ANGELO ANTONIO COSTRUZIONI GENERALI S.R.L. – SC CONCORDIA CON. STRADE S.R.L – SC SERCONSTRUCT

ROADS S.R.L.;

4. ASOCIEREA SC MAVGO HOLDING S.R.L. – SC BDU MAXI CONSTRUCT S.R.L.;

5. OZALTIN INSAAT TICARET VE SANAYI A.S.

VALOAREA ESTIMATA A CONTRACTULUI ESTE CUPRINSA IN INTERVALUL 243.801.103,00 - 289.093.324,00 LEI FARA TVA.

DURATA CONTRACTULUI ESTE DE 6 LUNI PERIOADA DE PROIECTARE TI 20 DE LUNI PENTRU EXECUTIA LUCRARILOR.

COMISIA DE EVALUARE VA ANALIZA OFERTELE IN CONFORMITATE CU PREVEDERILE DOCUMENTATIILOR DE ATRIBUIRE TI CU LEGISLATIA IN VIGOARE IN DOMENIUL ACHIZITIILOR PUBLICE.

ANALIZA SI EVALUAREA OFERTELOR CU STABILIREA OFERTANTULUI CASTIGATOR: 29.04.2021;

COMUNICAREA REZULTATULUI PROCEDURII: 29.04.2021;

TERMEN DEPUNERE CONTESTATII: 10.05.2021;

ESTIMAT SEMNARE CONTRACT, IN IPOTEZA FARA CONTESTATII: 25.05.2021

14DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN6 132+435 185+230

REABILITARE DN 6, ALEXANDRIA -

CRAIOVA, KM 90+190 - KM 222+182

LOT 2: KM 132+435 - KM 185+230

(RELICITARE)

48.009 2021 2024 ANUL 2024267.15 MIL. LEI

FARA TVA

CONTRACT REALIZARE EXPERTIZA TEHNICA SEMNAT IN DATA DE 06.06.2020

ORDINUL DE INCEPERE A FOST EMIS IN DATA DE 10.07.2020, CU O DURATA CONTRACTUALA DE 90 DE ZILE, TERMEN DE FINALIZARE 08.10.2020

CALENDAR PROCEDURA DE LICITATIE LOTUL 2, KM 132+435 - 185+230 - RELICITARE

DEPUNERE OFERTE: 29.06.2021

PROCEDURA IN CURS DE ANALIZA SI EVALUARE A OFERTELOR

15DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN66 106+220 106+965

ASOCIEREA S.C. FREYROM S.A. -

PROCONS GROUP S.R.L

REABILITARE DN66 PRIN

REAMENAJAREA SECTORULUI

CUPRINS INTRE KM 105+000 – KM

105+580 IN VEDEREA CONSTRUIRII

UNUI POD NOU PESTE JIU DE LA

MERI LA KM 105+250,

REAMENAJARE SECTOR KM 106+220

– KM 106+965

1.325 40.00% 10.75% 12.11.2020 12.07.2022 ANUL 202219.85 MIL. LEI

FARA TVA

CONTRACT EXECUTIE LUCRARI SEMNAT IN DATA DE 02.11.2020

DURATA DE REALIZARE A INVESTITIEI: 12 LUNI (EXCLUSIV PERIOADA DE TIMP FRIGUROS, DE REGULA, CUPRINSA IN PERIOADA 15.11- 15.03 ), CU O PERIOADA DE GARANTIE A LUCRARILOR ACORDATA DE EXECUTANT DE 96 LUNI (8 ANI).

APROBATA SITUATIA DE LUCRARI NR. 1 IN VALOARE DE 673.083,63 LEI FARA TVA. APROBATA SITUATIA DE LUCRARI NR. 2 IN VALOARE DE 991.685,77 LEI FARA TVA.

DOCUMENTATIA TEHNICA REPREZENTAND MODIFICARILE PREVAZUTE IN DISPOZITIILE DE SANTIER 1-7 A FOST AVIZATA IN CTE DRDP CRAIOVA CU AVIZ NR.545/01.07.2021 SI IN CTE CNAIR SA IN DATA DE 21.07.2021. DISPOZITIILE DE SANTIER 1-6 CONSUMA REZERVELE DE

IMPLEMENTARE, IN VALOARE DE 1.893.728,52 LEI FARA TVA. MODIFICARILE DIN DISPOZITIA DE SANTIER NR. 7 CONDUC LA O DEPASIRE CU 4.122.679,12 LEI FARA TVA A VALORII CONTRACTULUI , CEEA CE REPREZINTA 20.77 % DIN VALOAREA CONTRACTULUI. S-A

TRANSMIS CATRE CNAIR O ADRESA PENTRU COMUNICAREA SURSEI DE FINANTARE AFERENTA LUCRARILOR SUPLIMENTARE AVIZATE AFERENTE PODULUI PESTE JIU DE LA MERI. DIRECTIA ECONOMICA SI FINANCIARA A CNAIR A COMUNICAT EXISTENTA RESURSELOR

BUGETARE IN VEDEREA SEMNARII ACTULUI ADITIONAL LA CONTRACTUL DE LUCRARI. PROCEDURA PENTRU INCHEIEREA ACTULUI ADITIONAL A FOST SELECTATA DE ANAP IN VEDEREA CONTROLULUI EX-ANTE.

16DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN2L 60+165 76+277

MODERNIZARE DN 2L, SOVEJA -

LEPSA, KM 60+165 - KM 76+27716.112

PROIECTARE IN

DERULARE

ORDINUL DE

INCEPERE

PENTRU

PROIECTARE A

FOST EMIS IN

DATA DE

22.09.2020

DECEMBRIE 2023 DECEMBRIE 2023106.54 MIL. LEI

FARA TVA

CONTRACT DE PROIECTARE SI EXECUTIE LUCRARI SEMNAT IN DATA DE 24.07.2020.

VALOARE CONTRACT PROIECTARE + EXECUTIE LUCRARI: 126.778.219,70 LEI CU TVA, DIN CARE:

PROIECTARE: 3.655.098,42 LEI CU TVA

EXECUTIE LUCRARI: 123.123.121,28 LEI CU TVA

AVIZAT DTAC CTE DRDP IASI 16918/ 10.05.2021; AVIZAT DTAC CTE CNAIR SA - 08.06.2021

DURATA CONTRACTULUI ESTE: 30 LUNI PERIOADA DE PROIECTARE SI EXECUTIE A LUCRARILOR:

- 6 LUNI PROIECTARE;

- 24 LUNI EXECUTIE LUCRARI;

- 84 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.

PTE IN CURS DE REVIZUIRE.

17DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN7 256+675 258+950

PROIECTARE SI EXECUTIE

"REALIZARE BANDA A TREIA DN 7

VALEA OLTULUI INTRE KM 256+675

– KM 258+950”

2.2748.46 MIL. LEI

FARA TVA

18DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN69 0+000 10+000

TODINI COSTRUZIONI GENERALI

S.P.A.

DRUM DE LEGATURA INTRE DN69 SI

AUTOSTRADA A19,90

CTR SEMNAT IN

DATA DE

01.02.2021

01.03.2021 01.04.2023 ANUL 2023 189.57 MIL LEI

FARA TVA

CONTRACT SEMNAT IN DATA DE 01.02.2021, CU O PERIOADA CONTRACTUALA DE 2 ANI (6 LUNI PROIECTAREA ȘI 18 LUNI EXECUTIE ) ȘI ARE O GARANȚIE DE 84 DE LUNI. IN DATA DE 02.07.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 35 (NR MTI 26799 DIN

02.07.2021) - ETAPA I. AVIZ CTE CNAIR NR. 5075 DIN 30.06.2021 .

19DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN7 0+000 14+300

DRUM DE LEGATURA A1 - DN7

(TITU) (DJ 711A) - LARGIRE LA 4

BENZI DE CIRCULATIE

14.3 OCTOMBRIE 2019 Aug-2173.33 MIL. LEI

FARA TVA

STUDIUL DE FEZABILITATE IN VARIANTA DRAFT PREDAT DE CATRE PRESTATOR IN CURS DE ANALIZA.

S-AU EMIS OBSERVATII ASUPRA VARIANTEI DRAFT A STUDIUL DE FEZABILITATE SI SE ASTEAPTA VARIANTA FINALA.

IN DATA DE 29.04.2021 PRESTATORUL A TRANSMIS STUDIUL DE FEZABILITATE. STUDIUL DE FEZABILITATE SE AFLA IN ANALIZA LA BENEFICIAR. IN DATA DE 25.05.2021 AU FOST TRANSMISE OBSERVATIILE BENEFICIARULUI LA DOCUMENTATIA INAINTATA IN DATA DE

29.04.2021. PRESTATORUL IMPLEMENTEAZA OBSERVATIILE FORMULATE PENTRU SF.

20DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL

DRUM TRANSREGIO

GILAU - APAHIDA0+000 38+800 GILAU - APAHIDA 38.8

CONTRACT

SERVICII DE

PROIECTARE

DERULAT IN BAZA

UNUI PROTOCOL

DE CATRE UAT

CLUJ NAPOCA

2345.52 MIL.

FARA TVA

STUDIU DE FEZABILITATE IN ELABORARE

FINALIZARE SF - TRIM. IV 2021

21DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN24C 106+650 142+250

S.C. SEARCH CORPORATION S.R.L. -

ELABORARE SF / S.C. BEST

CONSULTING & DESIGN S.R.L.

BUCURESTI - REVIZUIRE S.F.

MANOLEASA - RADAUTI PRUT 35.6 33.63% 0%109.69 MIL. LEI

FARA TVA

SF REVIZUIT IN ANUL 2016 / HG NR. 460/28.06.2018 PENTRU APROBAREA INDICATORILOR TEHNICO-ECONOMICI

LIPSA FINANTARE LUCRARI

22DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL

POD PE DN13C PESTE

RAUL TARNAVA MARE

LA VANATORI

1+200 1+252POD PE DN 13C PESTE RAUL

TARNAVA MARE LA VANATORI0.0521

5.45 MIL. LEI

FARA TVACONTRACT SEMNAT IN LUNA OCTOMBRIE 2020.

Page 12: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

23DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN1H 6+000 12+000 SC MECANO BAU TRADING SRL

REMEDIERE DEFECTIUNI PE DN1H

KM 6+000 - KM 12+0006 94.00% 61.16% 15.10.2020 15.11.2021 ANUL 2021

12.761 MIL. LEI

FARA TVAORDINUL DE INCEPERE A FOST EMIS INCEPAND CU DATA DE 15.10.2020. Estimare Receptie la Terminarea lucrarilor noiembrie 2021.

24DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN51 2+600 43+783 ZIMNICEA - ALEXANDRIA 41.183

0.1953 MIL. LEI

FARA T.V.A.DOCUMENTATIE INTOCMITA IN VEDEREA PROMOVARII SPRE LICITATIE.

25DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN2

PASAJ SUPERIOR PE DN2, PESTE CF

LA ROMAN, KM 332+9612

841.094 MIL. LEI

FARA TVA

26DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN57 152+990 200+745

152+990 - 200+745 (ORAVITA -

MORAVITA)47.755

1.638 MII LEI

FARA TVADOCUMENTATIE PREDATA LA DIRECTIA ACHIZITI

27DRUMURI NATIONALE IN REABILITARE/

MODERNIZAREDRUM NATIONAL DN21 104+160 106+900

PROIECTARE SI EXECUTIE PASAJ

SUPERIOR PE DN 21, KM105+5002.74 0% 0% 15.03.2021 01.09.2023 ANUL 2023

98.120 MIL LEI

FARA TVA

S-A EMIS ORDINUL DE INCEPERE IN DATA DE 15.03.2021.

DURATA DE EXECUTIE CONTRACT :

- 360 ZILE PERIOADA DE PROIECTARE

- 540 ZILE PERIOADA DE EXECUTIE.

STADIU: S-A EMIS AVIZUL PENTRU DECLARATIA DE PROIECTARE.

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1VARIANTE OCOLITOARE PROIECTE IN

EXECUTIEVARIANTA OCOLITOARE CENTURA BUCURESTI

STRACO GRUP SRL - SC COMNORD

SRL - SPECIALIST CONSULTING SRL

PASAJ SUPRATERAN PE DJ 602

CENTURA BUCURESTI DOMNESTIDOMNESTI - DJ 602 0.536 43.62% 32.27%

15.01.2019 -

PENTRU

LUCRARILE

AUTORIZATE PRIN

AC 140/

20.12.2018

16.09.2019

PENTRU

LUCRARILE

AUTORIZATE PRIN

AC 69/28.08.2019

23.09.2020 -

PENTRU

LUCRARILE

AUTORIZATE PRIN

AC 54/23.09.2020

24 LUNI DE LA

EMITEREA

AUTORIZATIEI DE

CONSTRUIRE

(ESTIMAT LUNA

09.2022)

ANUL 202291.55 MIL. LEI

FARA TVA

CONTRACTUL DE PROIECTARE SI EXECUTIE PASAJ DOMNESTI A FOST SEMNAT IN DATA DE 10.05.2017

AUTORIZATIA DE CONSTRUIRE NR. 140/ 20.12.2018, NR. 69/ 28.08.2019 SI NR. 54/ 23.09.2020

LUCRARI IN EXECUȚIE: STRAT FUNDATIE DIN BALAST STABILIZAT - BRETEA INTOARCERE PRELUNGIREA GHENCEA HIDROIZOLATIE PE BALAST STABILIZAT - BRETEA INTOARCERE PRELUNGIREA GHENCEA STRAT DE MIXTURA DENSA AB31,5 - BRETEA PRELUNGIREA GHENCEA

HIDROIZOLATIE PE STRAT DE BAZA AB 31,5 - BRETEA PRELUNGIREA GHENCEA STRAT DE LEGATURA, BINDER BAD 22,4 - BRETEA PRELUNGIREA GHENCEA COFRARE ELEVATIE - ETAPA III CULEE C2 BETONARE ELEVATIE - ETAPA III - CULEE C2 ARMARE ELEVATIE - ETAPA III -

CULEE C2 ARMARE ELEVATIE - ETAPA III - CULEE C1 BETONARE ELEVATIE - ETAPA III - CULEE C1 LISE PREFABRICATE (PROCURARE SI MONTAJ) - ST3 TABLIER METALIC MONTAT - ST1 - GIRATIE COFRARE ELEVATIE - ETAPA III - CULEE C1 BETONARE ELEVATIE - ETAPA III -

CULEE C1 MONTARE BORDURI 20X25 CM - BRETEA INTOARCERE PRELUNGIREA GHENCEA UMPLUTURA GRANULARA - RAMPA PAMANT ARMAT COBORARE C3 PANOURI PREFABRICATE TERRE ARMEE - RAMPA PAMANT ARMAT COBORARE C3 EXCAVATI PT. TEREN

FUNDARE - RAMPA PAMANT ARMAT C7

2VARIANTE OCOLITOARE PROIECTE IN

EXECUTIEVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

BACAU0+000 30+842

SPEDITION UMB SRL –

TEHNOSTRADE SRLBACAU

OBIECT 1: 0+000 -20+299,

OBIECT 2: 0+000 - 3+177

OBIECT 3: 0+000 -7+366

30.842 100.00% 99.78%

23.01.2019 -

DATA DE

INCEPERE

PERIOADA DE

PROIECTARE

08.03.2019 -

DATA DE

INCEPERE A

LUCRARILOR IN

BAZA AC

040/15.07.20150

3.07.2019 - DATA

DE INCEPERE A

LUCRARILOR IN

BAZA AC

051/28.06.2019

IANUARIE 2022 ANUL 2020668.33 MIL. LEI

FARA TVA

DESCHIDERE TRAFIC

03.09.2020 - OBIECT 3;

02.12.2020 - OBIECT 1

VARIANTE OCOLITOARE PROIECTE IN EXECUTIE - OCTOMBRIE 2021

VARIANTE OCOLITOARE

Page 13: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

3VARIANTE OCOLITOARE PROIECTE IN

EXECUTIEVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

BARLAD0+000 11+281

ASOCIEREA SC TEHNIC ASIST SRL – SC

TASS INFRA LOGISTIC SRLBARLAD 1 11.281 29.00% 18.98%

05.12.2018

(DATA DE

INCEPERE A

ACTIVITATII DE

PROIECTARE)

06.08.2020 -

DATA DE

INCEPERE A

LUCARILOR)

ESTIMAT IUNIE

2022

132.051 MIL. LEI

FARA TVA

CONTRACTUL A FOST SEMNAT IN DATA DE 24.10.2018. ORDINUL DE INCEPERE PENTRU PROIECTAREA LUCRARILOR A FOST EMIS.

A FOST AVIZAT PROIECTUL TEHNIC IN SEDINTA CTE DIN DATA DE 19.06.2020

AUTORIZATIE DE CONSTRUIRE A FOST EMISA.

ORDINUL DE INCEPERE A LUCRARILOR A FOST EMIS IN DATA DE 06.08.2020

AMPLASAMENTUL LUCRARILOR A FOST PREDAT CATRE ANTREPRENOR IN DATA DE 06.08.2020.

4VARIANTE OCOLITOARE PROIECTE IN

EXECUTIEVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

GALATI0+000 33+600

ASOCIEREA S.C. SA&PE CONSTRUCT

S.R.L. – S.C. SPEDITION UMB S.R.L. –

S.C. TEHNOSTRADE S.R.L.

GALATI 1 33.6 0% 0% IUNIE 2021 DECEMBRIE 2025 ANUL 2025705.28 MIL. LEI

FARA TVA

PRETUL PE KM ESTE DE CCA. 20.990.555 LEI FĂRĂ TVA, REPREZENTAND CCA. 4,327,949 EURO FARA TVA.

DURATA CONTRACTULUI ESTE DE 174 DE LUNI, DIN CARE:

• 12 LUNI PERIOADA DE PROIECTARE,

• 42 LUNI PERIOADA DE EXECUTIE A LUCRĂRILOR,

• 64 DE LUNI PERIOADĂ DE GARANȚIE A LUCRĂRILOR.

5VARIANTE OCOLITOARE PROIECTE IN

EXECUTIEVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

MIHAILESTI0+000 3+180 S.C. VIAROM CONSTRUCT S.R.L. MIHAILESTI RELICITARE 3.18

30.7% - PROGRES

IN CADRUL

CONTRACTULUI

REZILIAT;

80% IN CADRUL

NOULUI

CONTRACT

31.94% -

PROGRES IN

CADRUL

CONTRACTULUI

REZILIAT;

35.03 % IN

CADRUL NOULUI

CONTRACT

FEBRUARIE 2021 -

DEMARARE

LUCRARI RAMASE

DE EXECUTAT

FEBRUARIE 202236.9 MIL. LEI

FARA TVA

CONTRACT REZILIAT IN DATA DE 04.04.2019 DE CATRE CNAIR SA PENTRU NEINDEPLINIREA DE CATRE ANTREPRENOR A MAI MULTOR INSTIINTARI DE REMEDIERE.

EXPERTIZA TEHNICA REALIZATA - 2019

IN DATA DE 23.12.2020 CNAIR A SEMNAT CONTRACTUL AVAND CA OBIECT “CONSTRUCTIA VARIANTEI DE OCOLIRE MIHAILESTI - FINALIZARE LUCRARI”, CU OFERTANTUL DECLARAT CASTIGATOR S.C. VIAROM CONSTRUCT S.R.L.

VALOAREA CONTRACTULUI ESTE DE 36.862.651,20 LEI FARA TVA.

SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE.

TRASEUL ARE O LUNGIME DE 3,18 KM.

DURATA CONTRACTULUI ESTE DE 72 DE LUNI, DIN CARE:

12 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,

60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.

A FOST EMIS ORDINUL DE INCEPERE LUCRARI PENTRU DATA DE 15.02.2021.

6VARIANTE OCOLITOARE PROIECTE IN

EXECUTIEVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

SATU MARE0+000 19+540

ASOCIEREA ITINERA SPA COLLINI

LAVORI SPA - VIA DESIGN SRLSATU MARE 1 19.54 77.82% 63.03%

30.06.2017

(SERVICII DE

PROIECTARE)

28.06.2018

(EXECUTIE

LUCRARI)

ESTIMAT

DECEMBRIE 2021

304.791 MIL. LEI

FARA TVA

CONTRACTUL DE PROIECTARE SI EXECUTIA VARIANTEI DE OCOLIRE SATU MARE A FOST SEMNAT IN DATA DE16.11.2015

DATA DE INCEPERE A PERIOADEI DE PROIECTARE ESTE 30.06.2017.

DATA DE INCEPERE EXECUTIE LUCRARi ESTE 28.06.2019-ETAPA I.

DATA DE INCEPERE EXECUTIE LUCRARI ETAPA II ESTE 02.12.2020

7VARIANTE OCOLITOARE PROIECTE IN

EXECUTIEVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

TARGU JIU0+000 19+987

COLLINI LAVORI SPA - CONTRACT

REZILIAT

CONTRACT RELICITAT - ASOCIEREA

SECOL SOCIETA EDILE COSTRUZIONI

E LAVORI S.A.

TARGU JIU RELICITARE 19.987

40% PROGRES

INREGISTRAT IN

CADRUL

CONTRACTULUI

DE LUCRARI

REZILIAT;

14.50% IN

CADRUL NOULUI

CONTRACT

37.5% PROGRES

INREGISTRAT IN

CADRUL

CONTRACTULUI

DE LUCRARI

REZILIAT;

2.27% IN CADRUL

NOULUI

CONTRACT

14.10.2014 - CTR

REZILIAT

NOV. 2020 -

CONTRACT

RELICITAT

SEMNAT

CONTRACT

REZILIAT DE

CATRE

ANTREPRENOR IN

LUNA 05.2018.

CONFORM

CONTRACT

RELICITAT -

AUGUST 2022

207 MIL. LEI FARA

TVA

IN DATA DE 24.11.2020 A FOST SEMNAT CONTRACTUL NR 92/79265.

A FOST EMIS ORDINUL DE INCEPERE LUCRARI PENTRU DATA DE 15.02.2021.

IN DATA DE 18.02.2021 A FOST PREDAT AMPLASAMENTUL.

8VARIANTE OCOLITOARE PROIECTE IN

EXECUTIEVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

TECUCI0+000 6+945

ASOCIEREA S.C. MAVGO HOLDING

S.R.L. – S.C. ANTREPRIZA DE

CONSTRUCȚII DRUMURI ȘI

AUTOSTRĂZI S.R.L. (FOSTA S.C. AQUA

PARC S.R.L.) – S.C. BDU MAXI

CONSTRUCT S.R.L. – HYDROSTROY

AD

TECUCI (RELICITARE) RELICITARE 6.945

58% - PROGRES

FIZIC

INREGISTRAT LA

DATA REZILIERII

17% IN CADRUL

NOULUI

CONTRACT

29.63% -

PROGRES

INREGISTRAT IN

CADRUL

CONTRACTULUI

DE LUCRARI

REZILIAT

9.49% IN CADRUL

NOULUI

CONTRACT

CONTRACTUL

PENTRU

"CONSTRUCTIA

VARIANTEI DE

OCOLIRE TECUCI -

REST DE

EXECUTAT” A

FOST SEMNAT IN

16.04.2021. A

FOST EMIS

ORDINUL DE

INCEPE LUCRARI

IN 20.05.2021.IN

21.05.2021 A

AVUT LOC

PREDAREA

AMPLASAMENTUL

UI

CONTRACT

REZILIAT IN DATA

DE

20.05.2019.CONT

RACTUL PENTRU

"CONSTRUCTIA

VARIANTEI DE

OCOLIRE TECUCI -

REST DE

EXECUTAT” A

FOST SEMNAT IN

16.04.2021. A

FOST EMIS

ORDINUL DE

INCEPE LUCRARI

IN 20.05.2021.IN

21.05.2021 A

AVUT LOC

PREDAREA

AMPLASAMENTUL

UI

41.74 MIL. LEI

FARA TVA

VINERI, 16.04.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL PENTRU "CONSTRUCTIA VARIANTEI DE OCOLIRE TECUCI - REST DE EXECUTAT”, CU ASOCIEREA S.C. MAVGO HOLDING S.R.L. – S.C. ANTREPRIZA DE CONSTRUCTII DRUMURI SI AUTOSTRAZI S.R.L. (FOSTA S.C. AQUA

PARC S.R.L.) – S.C. BDU MAXI CONSTRUCT S.R.L. – HYDROSTROY AD.

VALOAREA CONTRACTULUI ESTE DE 41.735.534,38 LEI FARA TVA.

SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE.

VARIANTA DE OCOLIRE TECUCI ARE O LUNGIME DE 6,945 KM.

VARIANTA SE DESPRINDE DIN DN24, TRAVERSEAZĂ CU UN PASAJ SUPERIOR DN24 ȘI LINA CF MARASESTI - TECUCI LA KM 0+385,95, CONTINUA IN ALINIAMENT PANA LA INTERSECTIA LA NIVEL CU DJ252H LA KM 2+490, TRAVERSEAZA CU PASAJ SUPERIOR LINIA CF FAUREI -

TECUCI LA KM 6+416,29 SI SE FINALIZEAZA LA KM 6+945 (ECHIVALENT CU KM 6+801,29), LA INTERSECȚIA CU DN25.

PERIOADA CONTRACTUALA DE EXECUTIE A LUCRARILOR ESTE DE 12 DE LUNI, IAR PERIOADA DE GARANTIE ESTE DE 60 DE LUNI.

9VARIANTE OCOLITOARE PROIECTE IN

EXECUTIEVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

TIMISOARA SUD0+000 25+690 TIRRENA SCAVI S.P.A TIMISOARA - SECTOR SUD 25.69 38.68% 32.34%

29.01.2019 -

DATA DE

INCEPERE

PERIOADA DE

PROIECTARE

25.03.2020 -

ORDIN - INCEPERE

EXECUTIE

LUCRARI

ESTIMAT 2022 ANUL 2022272.43 MIL. LEI

FARA TVA

PROIECT TEHNIC FINALIZAT

AUTORIZATIE DE CONSTRUIRE EMISA IN LUNA MARTIE 2020.

EXECUTIE LUCRARI IN DERULARE.

10VARIANTE OCOLITOARE PROIECTE IN

EXECUTIEVARIANTA OCOLITOARE

VARIANTA

OCOLITOARE ZALAU

VO DN 1V0+000 5+535

ASOCIEREA SINOHYDRO

CORPORATION LIMITED – SC GOOD

PROOD S.R.L.

ETAPA 2 - 7 KM INTRE DN 1F KM

79+625 - DJ 191C1

5.535 KM (5

VIADUCTE, 2

PODURI, 2

INTERSECTII TIP

GIRATIE)

9% 16% 2020 2023 2023185.54 MIL. LEI

FARA TVA

ORDINUL DE INCEPERE A CONTRACTULUI A FOST COMUNICAT CA FIIND 25.09.2020 (PROIECTARE+EXECUTIE). PERIOADA DE PROIECTARE ESTE DE 6 LUNI (FINALIZARE 24.03.2021) SI 24 LUNI EXECUTIE LUCRARI (FINALIZARE 23.03.2023).

DECIZIA DE EXPROPRIERE NR. 1848 DIN 10.11.2020.

A FOST ACORDATA ANTREPRENORULUI POSESIA SANTIERULUI.

A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 17/26.03.2021.

A FOST EMISA HOTARAREA DE GUVERN NR.622 DIN 03.06.2021 PRIVIND SCOATEREA DEFINITIVA DIN FONDUL FORESTIER NATIONAL.

11VARIANTE OCOLITOARE PROIECTE IN

EXECUTIEVARIANTA OCOLITOARE

DRUM DE LEGATURA

DN5 - SOSEAUA DE

CENTURA - POD

PRIETENIEI

0+000 5+720 PORR CONSTRUCT S.R.L.

DRUM DE LEGATURA DN5 -

SOSEAUA DE CENTURA - POD

PRIETENIEI

5.72 66.10% 36.45% APRILIE 2020 ESTIMAT 2022 ESTIMAT 2022106.638 MIL. LEI

FARA TVA

IN DATA DE 19.11.2019 A FOST SEMNAT CONTRACTUL DE PROIECTARE SI EXECUTIE AFERENT ACESTUI OBIECTIV.

IN DATA DE 05.03.2020 A FOST SEMNAT CONTRACTUL DE SUPERVIZARE AFERENT LUCRARILOR.

IN DATA DE 15.04.2020 A FOST EMIS ORDINUL DE INCEPERE PENTRU PROIECTARE

IN DATA DE 21.10.2020 A FOST EMIS ORDINUL DE INCEPRE PENTRU EXECUTIA LUCRARILOR

Page 14: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1VARIANTE OCOLITOARE IN PREGATIRE

FAZA EXECUTIE LUCRARIVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

SIGHISOARA0+000 13+057

PROCEDURA DE LICITATIE ATRIBUIRE

CONTRACT PROIECTARE SI EXECUTIE

IN DERULARE

SIGHISOARA 13.057 0.00% 0.00% 14.06.2021ESTIMAT

23.11.2021ESTIMAT 2021

293.084 MIL LEI

FARA TVA14.06.2021 - DATA PUBLICARII ANUNTULUI, 31.08.2021 - DATA DE DEPUNERE A OFERTELOR, 23.11.2021 - DATA FINALIZARE PROCEDURA DE EVALUARE

2VARIANTE OCOLITOARE IN PREGATIRE

FAZA EXECUTIE LUCRARIVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

SFANTU GHEORGHE0+000 8+000 CONTRACT ELABORARE SF FINALIZAT SFANTU GHEORGHE 1 8 07.05.2018

2020 -

FINALIZARE

PROIECTARE,

ETAPA STUDIU DE

FEZABILITATE

41.47 MIL. LEI

FARA TVAPROCEDURA DE ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE - IN DERULARE, ETAPA EVALUARE OFERTE.

3VARIANTE OCOLITOARE IN PREGATIRE

FAZA EXECUTIE LUCRARIVARIANTA OCOLITOARE CENTURA BUCURESTI 35+600 55+465

LARGIRE LA 4 BENZI A CENTURII

RUTIERE A MUNICIPIULUI

BUCURESTI SUD INTRE A1 (KM

55+520) SI DN 5 (KM 40+000) - LOT

1 SI LOT 2

18,68

31,508LEI FARA

TVA - LOT 1

638,945 LEI FARA

TVA - LOT 2

DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL DE MAI JOS

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1VARIANTE OCOLITOARE IN PREGATIRE

FAZA SF/PT/DTACVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

GIURGIU0+000 12+068

CONTRACT ELABORARE FAZE DE

PROIECTARE SF+PT+DE+DTAC+AT IN

DERULARE

GIURGIU 1

12.068 CONFORM

VARIANTEI DE

TRASEU

APROBATA

70% - SF

FINALIZAT SI

APROBAT PRIN

HG INDICATORI

TEHNICO -

ECONOMICI NR.

58/24.02.2021

57% 14.03.2018

2021 -

FINALIZARE

ETAPA DE

PROIECTARE.

DURATA DE

EXECUTIE A

LUCRARILOR : 36

DE LUNI DE LA

ORDINUL DE

INCEPERE, DUPA

FINALIZAREA

SERVICIILOR DE

PROIECTARE SI

OBTINEREA

AUTORIZATIEI DE

CONSTRUCTIE

VALOARE

PROIECT 1.6 MIL

LEI FARA TVA;

VALOARE

LUCRARI CF. SF -

VARIANTA 4

AVIZATA: TOTAL

GENERAL - 343.36

MIL LEI FARA TVA

CONTRACT PRESTARI SERVICII DE PROIECTARE FAZELE SF+PT+DE+DATC+AT SEMNAT IN DATA DE 14.03.2018.

ORDIN DE INCEPERE NR.3B/4773/26.03.2018 EMIS IN DATA DE 26.03.2018 PENTRU SERVICII DE PROIECTARE IN FAZA SF.

SF FINALIZAT SI APROBAT PRIN HG INDICATORI TEHNICO-ECONOMICI NR. 58/24.02.2021.

ORDIN DE INCEPERE PENTRU PT+DTAC SI AVIZE - NR. 3B/4773/26.03.2018 - INCEPAND CU 01.10.2020. PROIECTUL TEHNIC A FOST PREDAT IN 29.01.2021.

DOCUMENTATIA PENTRU PROMOVAREA HG DE EXPROPRIERI SI DOCUMENTATIA PT + DTAC AU FOST CONDIȚIONATE DE SUPRAPUNEREA OBIECTIVULUI CU UN OBIECTIV PRIVAT FINANTAT DIN FONDURI EUROPENE AFIR, FIIND NECESARE URMATOARELE:

* AVIZAREA IN CTE DRDP BUCURESTI A DOCUMENTATIEI PT+DTAC IN VARIANTA NOUA PROPUSA PENTRU CORELAREA OBIECTIVELOR, AVIZ OBTINUT IN DATA 04.06.2021;

* AVIZAREA IN CTE CNAIR A DOCUMENTATIEI PT+DTAC A DOCUMENTATIEI CU SOLUTIA MODIFICATA FATA DE CEA DIN SF, AVIZ OBTINUT CU NR. 5094/01.09.2021 TRANSMIS SI INREGISTRAT LA DRDP BUCURESTI CU NR.8/33194/16.09.2021;

* AVIZARE IN CTE CNAIR SIGURANTA CIRCULATIEI PENTRU PROIECT VO GIURGIU IMPREUNA CU PROIECTUL DE SEMNALIZARE SI MARCAJE SI CU PROIECTUL DE PARAPETE, DOCUMENT DE AVIZARE NR. 92/61651/27.07.2021, INREGISTRAT LA DRDP BUCURESTI CU NR.

8/31123/31.08.2021;

MAI SUNT DE ELABORAT :

* DETALII DE EXECUTIE 1 LUNA;

*PREGATIRE DOCUMENTATIE DE ATRIBUIRE PENTRU ACHIZITIA LUCRARI DE EXECUTIE: 2 LUNI;

* DOCUMENTATIA CADASTRALA PENTRU HG DE EXPROPRIERI DE UTILITATE PUBLICA;

MAI SUNT DE OBTINUT:

* AUTORIZATIA DE CONSTRUIRE SI HG DE EXPROPRIERI DE UTILITATE PUBLICA;

* AVIZ CTE DRDP BUCURESTI PENTRU FAZA DE;

IN DATA DE 25.06.2021 CA URMARE A SOLICITARII CNAIR - DEPARTAMENT OBTINERE FINANTARI PRIN ADRESA NR. 3B/ 2737/25.06.2021, DRDP BUCURESTI A INAINTAT DOCUMENTATIILE TEHNICE IN FAZELE SF - FINAL AVIZAT, PT + DTAC IN VARIANTA INAINTATA LA CTE

CNAIR, PENTRU A FI PUSE LA DISPOZITIA CONSILIULUI JUDETEAN GIURGIU PENTRU INCHEIEREA UNUI PARTENERIAT PENTRU IMPLEMENTAREA OBIECTIVULUI IN TEMEIUL OUG NR. 101/2020.

IN DATA DE 31.08.2021 S-A TRANSMIS LA DRDP BUCURESTI DOCUMENTUL DE AVIZARE EMIS DE COMISIA DE SIGURANTA CIRCULATIEI DIN CADRUL CNAIR CU NR. 92/61651/27.07.2021 CE A FOST INREGISTRAT CU NR. 8/31123/31.08.2021.

IN DATA DE 16.09.2021 S-A TRANSMIS LA DRDP BUCURESTI AVIZUL CTE CNAIR PENTRU FAZA PT+DTAC CU NR. 5094/01.09.2021.

2VARIANTE OCOLITOARE IN PREGATIRE

FAZA SF/PT/DTACVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

RAMNICU VALCEA0+000 21+837 SC SEARCH CORPORATION SRL RAMNICU VALCEA PROIECTARE 21.84 30% 0% 16.12.2019 2022

276.36 MIL. LEI

FARA TVA

CONTRACT DE SERVICII DE PROIECTARE ACTUALIZARE A STUDIULUI INITIAL INCLUSIV DOCUMENTATII PENTRU AVIZE,OBTINERE AVIZE SI ACORDURI, ELABORARE PROIECT TEHNIC INCLUSIV DTAC, DETALII DE EXECUTIE SI ASISTENTA TEHNICA PENTRU OBIECTIVUL VARIANTA

DE OCOLIRE RM. VALCEA NR. 148 /04.10.2019, CU ORDIN DE INCEPERE ACTIVITATI EMIS IN DATA DE 16.12.2019, IN DERULARE. PRESTATOR SC SEARCH CORPORATION SRL.

VALOAREA CONTRACT PROIECTARE: 3,832,075.75 LEI FARA TVA.

DOCUMENT DE AVIZARE CTE-CNAIR NR. 4915/09.04.2020 - ACTUALIZARE SF - ALTERNATIVE DE TRASEU.

CERTIFICATUL DE URBANISM NR. 12/10054/06.08.2020 EMIS DE C.J. VALCEA ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARIEI ORASULUI CALIMANESTI.

DOCUMENT DE AVIZARE CTE-CNAIR NR. 4992/19.10.2020 - ACTUALIZARE SF - ALTERNATIVE DE TRASEU (AMC ETAPA 4) - VARIANTE PENTRU RACORDAREA LA CENTURA CALIMANESTI.

C.J. VALCEA A EMIS UN NOU CERTIFICAT DE URBANISM, NR. 70/16141/23.11.2020, CARE SPECIFICA FAPTUL CA ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARULUI COMUNEI DAESTI.

DOCUMENT DE AVIZARE CTE-DRDP CRAIOVA NR. 3/20.01.2021 - STUDIUL ALTERNATIVELOR DE TRASEU IN ZONA LOCALITATII FEDELESOIU, COMUNA DAESTI - ETAPA 5. DOCUMENTATIA TEHNICA A FOST INAINTATA LA CJ VALCEA CARE A EMIS CERTIFICATUL DE URBANISM

NR. 05/19899/26.01.2021 CARE ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARULUI COMUNEI DAESTI. S-A EMIS

ORDIN DE SISTARE DIN DATA DE 29.01.2021. AU FOST INITIATE DEMERSURI IN VEDEREA ADRESARII INSTANTELOR JUDECATORESTI COMPETENTE PENTRU CHEMARE IN JUDECATA A C.J. VALCEA SI A REPREZENTANTULUI UAT DAESTI.

3VARIANTE OCOLITOARE IN PREGATIRE

FAZA SF/PT/DTACVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

REGHIN0+000 10+440 SC TPF INGINERIE SRL REGHIN 1 10.44 05.12.2019 2021

108.11 MIL. LEI

FARA TVA

CONTRACT PRESTARI SERVICII COMPLETARE STUDIU DE FEZABILITATE SEMNAT LA DATA DE 05.12.2019, IN DERULARE.

CONTRACT COMPLETARE SF IN DERULARE - FINALIZARE 2021

VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE LUCRARI - OCTOMBRIE 2021

VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC - OCTOMBRIE 2021

Page 15: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

4VARIANTE OCOLITOARE IN PREGATIRE

FAZA SF/PT/DTACVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

TARGU MURES0+000 11+643 TARGU MURES

RELICITAREA LUCRARILOR

RAMASE DE EXECUTAT SE VA

REALIZA IN 2 ETAPE:

ETAPA 1: REVIZUIRE PROIECT

TEHNIC

ETAPA 2: LICITATIE LUCRARI

RAMASE DE EXECUTAT,

CORELATE CU PROIECTUL

TEHNIC REVIZUIT

11.643

34.26% -

PROGRES

INREGISTRAT IN

CADRUL

CONTRACTULUI

DE LUCRARI

REZILIAT

37.55% -

PROGRES

FINANCIAR

INREGISTRAT LA

DATA REZILIERII

09.10.2014

(ORDIN DE

INCEPERE

PENTRU

CONTRACTUL

REZILIAT)

ORDIN DE

INCEPERE A

LUCRARILOR -

PENTRU

CONTRACTUL

RELICITAT - VA FI

SPECIFICAT

ULTERIOR

SEMNARII

ACESTUIA

CONTRACT 1

INCETAT PE CALE

AMIABILA IN

29.12.2017

ANUL 2023134.80 MIL. LEI

FARA TVA

COPISA CONSTRUCTORA PIRENAICA SA - CONTRACT REZILIAT

LICITATIE ATRIBUIRE CONTRACT REST LUCRARI RAMASE DE EXECUTAT, CU TERMEN DEPUNERE OFERTE: 26.08.2020

PROCEDURA ANULATA ADMINISTRATIV PENTRU NEDEPUNERE DE OFERTE

DEMERSURILE IN VEDEREA ACTUALIZARII PROIECTULUI TEHNIC SUNT DEMARATE DE CATRE DRDP BRASOV.

IN DATA DE 23.02.2021, A FOST PUBLICAT IN SEAP ANUNTUL NR. CN1029446 CU PRIVIRE LA ACHIZITIA PUBLICA CARE VA AVEA CA SCOP ACTUALIZAREA DOCUMENTATIEI TEHNICE PT+DDE VARIANTA DE OCOLIRE TARGU MURES.

PROCEDURA DE LICITATIE IN DERULARE LA NIVELUL DRDP BRASOV

5VARIANTE OCOLITOARE IN PREGATIRE

FAZA SF/PT/DTACVARIANTA OCOLITOARE

ALTERNATIVA

TECHIRGHIOL0+000 28+833

SC CONSITRANS SRL - CONTRACT

PROIECTARE ELABORARE SF, PT SI

DTAC

TECHIRGHIOL 1 28.833 30% 0% FEBRUARIE 2020 DECEMBRIE 2021 DECEMBRIE 20215.372 MIL. LEI

FARA TVA

"CONTRACTUL PENTRU ELABORARE SF, PT SI DTAC A FOST SEMNAT IN DATA DE 26.07.2019 .

ORDINUL DE INCEPERE A FOST EMIS IN LUNA FEBRUARIE 2020.

STUDIU DE FEZABILITATE FINALIZAT, URMEAZA PARCURGEREA PROCEDURII PRIVIND APROBAREA INDICATORILOR TEHNICO-ECONOMICI (AVIZ CTE CNAIR, AVIZ MT, AVIZ CI SI HG). DUPA EMITEREA HG, TERMENUL CONTRACTUAL PENTRU EMITERE PT ESTE 3 LUNI.

AMC 1+2 A FOST AVIZAT IN CADRUL CTE CNAIR SA.

IN CURS DE FINALIZARE INVESTIGATIILE GEOTEHNICE DE TEREN."

6VARIANTE OCOLITOARE IN PREGATIRE

FAZA SF/PT/DTACVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

VASLUI0+000 14+940

CONTRACT REVIZUIRE SF IN

DERULAREVASLUI 1 14.94 2019 2021

142.8 MIL. LEI

FARA TVA

SF - 2006 (AVIZ MT 36/27/19.03.2007).

CONTRACT REVIZUIRE SF SI ELABORARE PT + DTAC SEMNAT IN LUNA MAI 2019 - IN DERULARE, CU TERMEN DECALAT FINALIZARE OCTOMBRIE 2021

DURATA REVIZUIRE SF – 8 LUNI AVIZ CTE DRDP IASI NR. 16891/19.04.2021 IN AVIZARE LA CTE CNAIR SA

DURATA ELABORARE PT – 6 LUNI

VALOARE CONTRACT PROIECTARE: 1.478.500 LEI

7VARIANTE OCOLITOARE IN PREGATIRE

FAZA SF/PT/DTACVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

HUSI

CONTRACT REVIZUIRE SF IN

DERULARE14.4

8VARIANTE OCOLITOARE IN PREGATIRE

FAZA SF/PT/DTACVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

PITESTI VEST0+000 20+000 TPF INGINERIE SRL PITESTI VEST 20 0% 0%

VALOARE SPF + SF

2.732 MIL LEI

FARA TVA

CONTRACT IN DERULARE.

IN DATA DE 26.04.2021 PRESTATORUL A TRANSMIS STUDIUL DE PREFEZABILITATE CONFORM GRAFICULUI ACTIVITATILOR. AU FOST FORMULATE OBSERVATII ASUPRA DOCUMENTATIE STUDIUL DE PREFEZABILITATE. PRESTATORUL A TRANSMIS SPF-UL REVIZUIT.

A FOST PREDAT STUDIUL DE TRAFIC REVIZUIT. SPF A FOST ANALIZAT IN CADRUL CTE-CNAIR S.A. AU FOST FORMULATE OBSERVATII DE CATRE CTE-CNAIR.

9VARIANTE OCOLITOARE IN PREGATIRE

FAZA SF/PT/DTACVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

DOROHOI0+000 13+900 SC NV CONSTRUCT SRL DOROHOI 13.9 0% 0% 429.22 MII LEI IN CURS DE FINALIZARE STUDIUL DE FEZABILITATE, DUPA APROBARE PUZ DOROHOI

10VARIANTE OCOLITOARE IN PREGATIRE

FAZA SF/PT/DTACVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

TIMISOARA VEST0+000 22+000 SEARCH CORPORATION SRL TIMISOARA 22 18.01.2021 18.04.2022

3.66 MIL. LEI

FARA TVA

CONTRACT IN DERULARE.

IN DATA DE 20.05.2021 FOST AVIZAT IN CTE CNAIR SA - ANALIZA MULTICRITERIALA ETAPA 1.

DOCUMENTATIA AMC ETAPA 2 A FOST PREDATA IN DATA DE 27.08.2021. AU FOST FORMULATE OBSERVATII DIN PARTEA BENEFICIARULUI IN DATA DE 16.09.2021.

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1VARIANTE OCOLITOARE IN PREGATIRE

FAZA PROIECTAREVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

BISTRITA0+000 15+000 BISTRITA 1 15

2.33 MIL LEI FARA

TVA (VALOARE

ESTIMATA

CONTRACT S.F.)

PROCEDURA DE ACHIZITIE PUBLICA PENTRU CONTRACTUL DE SERVICII DE „ELABORARE STUDIU DE FEZABILITATE PENTRU VARIANTA DE OCOLIRE BISTRITA”, A FOST ANULATA.

OBIECTIVUL FACE PARTE DIN ,,AUTOSTRADA NORDULUI” – FIIND SPECIFICAT IN STUDIUL DE FEZABILITATE CA DRUMUL DE MARE VITEZA BAIA MARE-SUCEAVA: LOT 1 BAIA MARE-BISTRITA SI LOT 2 BISTRITA-VATRA DORNEI, VA INDEPLINI SI FUNCTIA DE VARIANTA DE

OCOLIRE PENTRU LOCALITATILE INTERSECTATE DE ACESTA.

2VARIANTE OCOLITOARE IN PREGATIRE

FAZA PROIECTAREVARIANTA OCOLITOARE

DRUM DE LEGATURA

DN6 - DRUM EXPRES

CRAIOVA-PITESTI

(TRONSONUL 1)

INITIERE PROCEDURA DE ACHIZITIE

ATRIBUIRE CONTRACT DE PRESTARI

SERVICII DE PROIECTARE

10

CNAIR SA A TRANSMIS CATRE MINISTERUL TRANSPORTURILOR SI INFRASTRUCTURII CEREREA DE FINANTARE PENTRU PROIECTUL: """"ELABORARE STUDIU DE FEZABILITATE, PROIECT TEHNIC DE EXECUTIE INCLUSIV PAC, DETALII DE EXECUTIE, ASIGURAREA ASISTENTEI

TEHNICE PE PARCURSUL EXECUTIEI DE LUCRARI SI IN PERIOADA DE GARANTIE A LUCRARILOR EXECUTATE PENTRU OBIECTIVUL DE INVESTITIE: DRUM DE LEGATURA PENTRU SPORIREA CAPACITATII DE TRAFIC INTRE DN6 (ZONA UZINEI FORD) SI DRUMUL EXPRES CRAIOVA –

PITESTI (TRONSONUL 1)"""".

PROCEDURA DE ACHIZITIE IN DERULARE CU O VALOARE ESTIMATA A CONTRACTULUI DE 1.500.000 LEI INCLUSIV TVA. TERMEN LIMITA DE DEPUNERE A OFERTELOR: 08.09.2021. CELE 2 OFERTE DEPUSE SUNT IN ANALIZA.

DURATA ESTIMATA A PRESTARII SERVICIILOR ESTE DE 89 LUNI (3 LUNI – ELABORARE SF INCLUSIV DOCUMENTATII PENTRU OBTINERE AVIZE/ACORDURI; 2 LUNI – ELABORARE PT INCLUSIV DTAC SI DE; 24 LUNI – ASISTENTA TEHNICA PE PARCURSUL EXECUTIEI LUCRARILOR;

60 LUNI – ASISTENTA TEHNICA IN PERIOADA DE GARANTIE A LUCRARILOR).

VARIANTE OCOLITOARE IN PREGATIRE FAZA PROIECTARE - OCTOMBRIE 2021

Page 16: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1VARIANTE OCOLITOARE IN

REABILITARE/MODERNIZAREVARIANTA OCOLITOARE CENTURA BUCURESTI 29+500 33+190 ITINERA SPA

LARGIRE LA 4 BENZI A CENTURII

RUTIERE A MUNICIPIULUI

BUCURESTI SUD INTRE A2 KM

23+600 SI A1 KM 55+520

AMENAJARE NOD RUTIER LOT

1: OLTENITA - DN 43.69 31.50% 35.53%

31.07.2019 -

DATA DE

INCEPERE

PERIOADA DE

PROIECTARE

ESTIMAT 2022 SEPTEMBRIE 2022169.5 MIL. LEI

FARA TVA

CONTRACTUL DE EXECUTIE LUCRARI A FOST SEMNAT IN DATA DE 20.06.2019/ AUTORIZATIE DE CONSTRUIRE VALABILA.

LUCRARI IN EXECUTIE:

DRUM - LUCRARI DE EXCAVATIE DN4 SI CB, LUCRARI DE UMPLUTURI, EXECUTIE STRAT DE FORMA, EXECUTIE FUNDATIE DIN BALAST,ASTERNERE STRAT DE BALSAT STABILIZAT.

PASAJ - TURNARE BETON EGALIZARE: 31 DE FUNDATII; TURNARE RADIERE: 31 BUC; EXECUTIE ELEVATII PILE: 27 BUC; EXECUTIE ELEVATII CULEE: 4 BUC; EXECUTIE RIGLE: 9 BUC, ARMARE SI COFRARE 2 BUC, CUZINETI SI ORPITORI SEISMICI SP1A, SP1B SI P2B, P4B, P1B,

COFRARE SI ARMARE RIGLE: P2B1, P3, P5B1, APROVIZIONARE APARATE DE REAZEM.

CONSOLIDARI - RAMPA A1: BETON DE EGALIZARE RAMPA A1; RADIERE BETONATE ZID TIP L – 7 BUC; ELEVATII BETONATE ZID TIP L – 6 BUC, EXCAVATIE SEGMENT 2 ZID TIP U, RADIER BETONAT SEGMENT 1 TIP U, ELEVATII BETONATE SEGMENT 1 TIP U; RAMPA A:

EXCAVATIE PRIMUL ZID TIP L, BETON DE EGALIZARE ZID TIP L – 7 BUC, RADIERE ZID TIP L, 7 SEGMENTE; ELEVATII ZID TIP L – 4 BUC.

RAMPA B: EXECUTATA IN PROPORTIE DE 90 %; MONTARE GEODREN, BETON DE PANTA PE ZIDUL TIP L; RAMPA B1: EXECUTATA IN PROPORTIE DE 75 %; RAMPA BUCURESTI: EXCAVATIE ZID DE SPRIJIN TIP L; BETON DE EGALIZARE; RADIERE BETONATE; ELEVATII BETONATE;

RAMPA OLTENITA: RADIERE BETONATE ZID DE SPRIJIN TIP L; BETON DE EGALIZARE; RADIERE BETONATE; ELEVATII BETONATE

RETELE DE UTILITATI - RETEA DE DISTRIBUTIE GAZE NATURALE – INTREGIRE CONDUCTA NOUA DN CB SI BRANSAMENTE NOI, S-A DEVIAT RETEAUA PE NOUL TRASEU PE DN4, KM 1+140 LA KM 1+580, SE PREGATESTE O NOUA CUPLARE PE DN4; RETEA DE TELECOMUNICATII

– FINALIZATA, TREBUIE INTOCMIT PV LA TERMINAREA LUCRARILOR; RETEA E-DISTRIBUTIE – S-AU DEVIAT TRASEELE JT ANTENA VODAFONE SI REMAT SI TRASEU MT 20 kV – PORCINE 1, SE MONTEAZA CABLURILE PE DN 4, PE TRASEELE DE MEDIE TENSIUNE.

RETEA DE CANALIZARE PLUVIALA - RETEA DN 4, REALIZAT APROXIMATIV 2600 M, 83,00%; RETEA CB, REALIZAT APROXIMATIV 1260 M, 32,12 %.

2VARIANTE OCOLITOARE IN

REABILITARE/MODERNIZAREVARIANTA OCOLITOARE CENTURA BUCURESTI 12+300 23+750 TIRRENA SCAVI S.P.A

MODERNIZAREA CENTURII RUTIERE

A MUNICIPIULUI BUCURESTI INTRE

A1 - DN7 SI DN2 - A2

SECTIUNEA DN 2 - A2 11.524 11.28% 17.77% 04.05.2020 ESTIMAT 2022 ANUL 2022235.75 MIL. LEI

FARA TVA

1. CONTRACTUL DE EXECUTIE LUCRARI A FOST SEMNAT IN DATA DE 02.03.2020/ AUTORIZATIE DE CONSTRUIRE VALABILA.

LUCRARI IN EXECUTIE: 3000 MP CURATARE AMPLASAMENT; 2250 MC DECAPARE PAMANT VEGETAL; 2400 MC SAPATURA CORP DRUM; 800 MC UMPLUTURI TERASAMENTE; 500 M RIGOLA DREPTUNGHIULARA; 600 MC STRAT DE FORMA DIN BALAST; 650 MC STRAT DE

FUNDATIE DIN BALAST; 25 MP COFRARE PILE; 3 TONE ARMATURA ELEVATII PASAJE; 10 MC BETONARE ELEVATII PASAJE; 500 M PILOTI DE INDESARE; ACTIVITATI GENERALE.

3VARIANTE OCOLITOARE IN

REABILITARE/MODERNIZAREVARIANTA OCOLITOARE CENTURA BUCURESTI 33+190 35+600

ASOCIEREA S.C. TRAMECO S.A. -

VAHOSTAV -SK, A.S. - CONSTRUCTII

ERBASU S.A. - GRAFIC TENDS S.R.L.

S.C. (LIDER DE ASOCIERE TRAMECO

S.A.)

LARGIRE LA 4 BENZI A CENTURII

RUTIERE A MUNICIPIULUI

BUCURESTI SUD INTRE A2 KM

23+600 SI A1 KM 55+520

AMENAJARE NOD RUTIER LOT

2: BERCENI - DJ 4012.41 33.57% 20.27% 06.05.2019 ESTIMAT 2022 IUNIE 2022

146 MIL. LEI FARA

TVA

CONTRACTUL DE PROIECTARE SI EXECUTIE PASAJ BERCENI A FOST SEMNAT IN DATA DE 19.03.2019.

ORDIN DE INCEPERE PROIECTARE: 06.05.2019

ORDIN DE INCEPERE EXECUTIE:

23.06.2020 - etapa 1; 10.08.2020 - etapa 2; 21.09.2020 - etapa 3; 06.06.2021 – etapa 4

AUTORIZATIE DE CONSTRUIRE:

AC nr. 27/12.06.2020 - etapa 1; AC 37/30.07.2020 - etapa 2; AC 52/10.09.2020 - etapa 3;

AC nr. 24/31.05.2021

FAZA PROIECTULUI: IN CURS DE EXECUTIE LUCRARI

4VARIANTE OCOLITOARE IN

REABILITARE/MODERNIZAREVARIANTA OCOLITOARE CENTURA BUCURESTI 55+465 64+160

ASOCIEREA S.C. DELTA A.C.M. 93 SRL

& AZVIRT LLC & S.C. MAXIDESIGN

S.R.L. - CONTRACT REZILIAT

MODERNIZAREA CENTURII RUTIERE

A MUNICIPIULUI BUCURESTI INTRE

A1 - DN 7 SI DN 2-A2:SECTIUNEA A1

(KM 55+465) - DN 7 (KM 64+160)

SECTIUNEA A1 KM 55+465 -

DN7 KM 64+1608.695

86.5% - PROGRES

FIZIC LA DATA

REZILIERII

77.73% -

PROGRES

FINANCIAR LA

DATA REZILIERII

2021 TRIM IV 2022106.6 MIL. LEI

FARA TVA

A FOST DEMARATA PROCEDURA DE ACHIZITIE PUBLICA PENTRU LUCRARI DE REMEDIERE SI FINALIZARE LUCRARI - REST DE EXECUTAT.

A FOST PUBLICAT ANUNTUL DE PARTICIPARE.

DETALII IN LINK-UL DE MAI JOS:

5VARIANTE OCOLITOARE IN

REABILITARE/MODERNIZAREVARIANTA OCOLITOARE CENTURA BUCURESTI SC STRABAG SRL

PROIECTARE SI EXECUTIE PASAJ

MOGOSOAIA PE CENTURA

BUCURESTI PESTE DN 1A

MOGOSOAIA/ DN 1A 0.8 97.00% 39.00%

04.12.2018 -

PROIECTARE;

02.04.2020 -

EXECUTIE

2021- CONFORM

ASUMARI

ANTREPRENOR

ANUL 2022 CONFORM

GRAFIC CONTRACT

32.26 MIL. LEI

FARA TVATRAFICUL A FOST DESCHIS IN DATA DE 30.09.2021

6VARIANTE OCOLITOARE IN

REABILITARE/MODERNIZAREVARIANTA OCOLITOARE CENTURA BUCURESTI

PENETRATIE PRELUNGIREA

GHENCEA – DOMNESTI SI

SUPRALARGIRE BULEVARDUL

GHENCEA INTRE STRADA BRASOV SI

TERMINAL TRAMVAI 41” CU

PROIECTUL “PASAJ SUPRATERAN PE

DJ 602, CENTURA BUCURESTI -

DOMNESTI

1.1

139.255 MII lei

FARA TVA -

VALOARE

PROIECTARE

CAIET DE SARCINI, APROBAT

REFERAT DE NECESITATE,

PAAP APROBAT 02.02.2021

PUBLICAT IN SEAP 05.03.2021

DESCHIDEREA OFERTELOR 08.04.2021

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1VARIANTE OCOLITOARE - PROIECTE IN

COLABORARE CU AUTORITATILE LOCALEVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

ALESD0+000 16+840 ALESD 16.84

OBIECTIVUL A FOST TRANSFERAT CATRE CJ BIHOR IN VEDEREA REVIZUIRII DOCUMENTATIEI TEHNICE SI IMPLEMENTARII ACESTUIA IN BAZA OUG 101/2020.

DECEMBRIE 2020 - A FOST SEMNAT UN PARTENERIAT INTRE CNAIR SI CJ BIHOR IN ACEST SENS

IN DATA DE 20.05.2021 A FOST AVIZAT IN CADRUL CTE CNAIR SA STUDIUL DE FEZABILITATE.

IN DATA DE 21.05.2021 A FOST AVIZAT IN CADRUL CTE MTI STUDIUL DE FEZABILITATE

IUNIE 2021- URMEAZA AVIZAREA IN CADRUL CTE IM SI PROMOVAREA HG DE APROBARE A INDICATORILOR TEHNICO ECONOMICI

2VARIANTE OCOLITOARE - PROIECTE IN

COLABORARE CU AUTORITATILE LOCALEVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

IASI

19+690

(SELGROS)

26+460

(DN28)

ETAPA I – VARIANTA SUD OBIECT 3 –

VARIANTA TRAFIC GREU6.77

126.88 MIL. LEI

FARA TVA

(VALOARE

ESTIMATA)

PENTRU IMPLEMENTAREA ACESTUI OBIECTIV PRIMARIA MUNICIPIULUI IASI A INAINTAT O PROPUNERE DE SCHIMBARE A TRASEULUI, CA URMARE A IMPOSIBILITATII PASTRARII TRASEULUI PE BULEVARDUL POITIERS SI STRADA TREI FANTANI (KM 19+690 - KM 26+460).

PROPUNEREA A FOST ACCEPTATA DE CNAIR, URMAND A SE IDENTIFICA SURSA DE FINANTARE.

3VARIANTE OCOLITOARE - PROIECTE IN

COLABORARE CU AUTORITATILE LOCALEVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

MEDIAS0+000 8+500 MEDIAS 1 8.5 2022 2024

PENTRU IMPLEMENTAREA ACESTUI OBIECTIV A FOST SEMNAT UN PARTENERIAT DE IMPLEMENTARE INTRE CNAIR SA SI PRIMARIA MEDIAS IN BAZA PREVEDERILOR OUG 101/2020.

OBIECTIVUL SE IMPLEMENTEAZA DE CATRE UAT MEDIAS.

A FOST SEMNAT CONTRACTUL DE REVIZUIRE A STUDIULUI DE FEZABILITATE DE CATRE PRIMARIA MEDIAS IN LUNA IUNIE 2021.

A FOST EMIS ORDINUL DE INCEPERE IN DATA DE 10.06.2021 - TERMEN PENTRU EMITEREA RAPORTULUI DE INCEPUT- 31.07.2021

4VARIANTE OCOLITOARE - PROIECTE IN

COLABORARE CU AUTORITATILE LOCALEVARIANTA OCOLITOARE

VARIANTA OCOLITOARE

STEI0+000 27+230

COPISA CONSTRUCTORA PIRENAICA

SA - CONTRACT REZILIAT LICITATIE

ATRIBUIRE CONTRACT REST LUCRARI

RAMASE DE EXECUTAT, CU TERMEN

DEPUNERE OFERTE : 22.06.2020

STEI 1 27.23 0% 0%

CONTRACT

REZILIAT DE

CATRE

ANTREPRENOR

CONTRACT

REZILIAT DE

CATRE

ANTREPRENOR

CONTRACT REZILIAT DE

CATRE ANTREPRENOR

257.413 MIL. LEI

FARA TVA

OBIECTIVUL A FOST TRANSFERAT CATRE CJ BIHOR IN VEDEREA REVIZUIRII DOCUMENTATIEI TEHNICE SI IMPLEMENTARII ACESTUIA IN BAZA OUG 101/2020.

A FOST SEMNAT IN LUNA DECEMBRIE 2020, PARTENERIATUL INTRE CNAIR SI CJ BIHOR IN ACEST SENS.

CONTRACT REVIZUIRE STUDIU DE FEZABILITATE IN DERULARE - ESTIMAT FINALIZARE TRIM. III 2021

VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE LOCALE - OCTOMBRIE 2021

VARIANTE OCOLITOARE IN REABILITARE / MODERNIZARE - OCTOMBRIE 2021

Page 17: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - …

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km)

PÂNĂ LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km)

STADIUL FIZIC

ACTUAL

STADIUL

FINANCIAR

ACTUAL

DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDEREVALOARE

PROIECTOBSERVAȚII

1 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOAREVARIANTA OCOLITOARE

RADAUTI0+000 16+580

SPEDITION UMB - SC TEHNOSTRADE

SRLRADAUTI 1 16.58 08.10.2018 20.11.2020 ANUL 2020

97.44 MIL. LEI

FARA TVA

LUCRARI FINALIZATE - 20.11.2020

PENTRU ACEST PROIECT A FOST FINALIZAT PROCESUL DE ACCESARE A FINANTARII NERAMBURSABILE ALOCATE IN CADRUL POIM 2014-2020, FIIND EMISA NOTA DE APROBARE A FINANTARII ACESTUIA DIN FONDURI NERAMBURSABILE IN LUNA DEC. 2020.

CONTRACT DE FINANTARE A LUCRARILOR EXECUTATE IN CADRUL POIM 2014-2020 SEMNAT IN LUNA IANUARIE 2021

2 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOAREVARIANTA OCOLITOARE

SACUENI0+000 7+620

SC ANTREPRIZA DE REPARATII SI

LUCRARI ARL CLUJ SASACUENI 7.62 10.09.2019 12.08.2020 DECEMBRIE 2020

42.83 MIL. LEI

FARA TVA

LUCRARILE AU FOST FINALIZATE SI VARIANTA DE OCOLIRE SACUENI ESTE IN DATA IN CIRCULATIE INCEPAND CU 09.12.2020.

MOMENTAN SE AFLA IN PROCEDURA DE RECEPTIE LA TERMINAREA LUCRARILOR, LA DATA DE 15.09.2021 FIIND EMISA DECIZIA DIRECTORULUI GENERAL AL C.N.A.I.R.S.A. NR.1413/15.09.2021 PRIN CARE ESTE NUMITA COMISIA PENTRU EFECTUAREA R.T.L. S-A STABILIT

DATA LA CARE SE VA EFECTUA RECEPTIA LA TERMINAREA LUCRARILOR: 29.09.2021

3 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOAREVARIANTA OCOLITOARE

SUCEAVA0+000 7+285

ASOCIEREA S.C. AUTOTEHNOROM

S.R.L. (LIDER) – S.C. OPERATIONAL

AUTOLEASING S.R.L. – S.C. OPR

ASFALT S.R.L. – OBRAS PUBLICAS Y

REGADIOS S.A. – S.C.

FLORCONSTRUCT S.R.L. – S.C.

CALCARUL S.A.

SUCEAVA 1 7.285

DESCHISA

TRAFICULUI - IN

DATA DE 27 SEPT.

2019

77% 01.10.2018

OCTOMBRIE 2021

- RECEPTIE LA

TERMINAREA

LUCRARILOR

OCTOMBRIE 2028

- RECEPTIE FINALA

OCTOMBRIE 2021 -

FINALIZARE LUCRARI

AUXILIARE

63.85 MIL. LEI

FARA TVA

4 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOAREVARIANTA OCOLITOARE

CARACAL - RELICITARE0+000 10+345

ASOCIEREA SECOL S.A. - S.E.C.O.L

S.P.A.CARACAL 10.345 100% 97.05% 16.10.2014 RTL: 24.05.2018

41.69 MIL. LEI

FARA TVA

24.05.2018 - A FOST REALIZATA RTL

IN DATA DE 10.11.2020 A FOST REALIZATA RECEPTIA FINALA

5 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOAREVARIANTA OCOLITOARE

BRASOV0+000 7+292

ASOCIEREA CHIRULLI ANDREA

IMPRESA INDIVIDUALE - ALEANDRI

SPA - SMART BUILDING PROJECT-

PASQUALE ALO' SRL

TRONSON I, DN1 - DN 11 LOT 1 - RELICITARE 100% 98.56% 16.12.2014RTL: 28.11.2016;

RF:19.12.2019

59.56 MIL. LEI

FARA TVA

IN DATA DE 29.11.2016 A AVUT LOC RECEPTIA LA TERMINAREA LUCRARILOR. LA DATA PREZENTEI CONTRACTUL SE AFLA IN PERIOADA DE NOTIFICARE A DEFECTIUNILOR.

IN DATA DE 19.12.2019 A FOST APROBAT PROCESUL VERBAL DE RECEPTIE FINALA.

6 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOAREVARIANTA OCOLITOARE

BRASOV0+000 4+924

ASOCIEREA SC VIAROM CONSTRUCT

SA - SC BETA COPS SRL - SC

MAXIDESIGN SRL

TRONSON II, DN11 - DN13 LOT 3 4.924 100% 98.77% 07.08.2014

RECEPTIE LA

TERMINAREA

LUCRARILOR:

29.11.2019

64.42 MIL. LEI

FARA TVAPROCESUL VERBAL DE RECEPTIE LA TERMINAREA LUCRARILOR A FOST APROBAT DE DIRECTORUL GENERAL AL CNAIR IN DATA DE 29.11.2019.

VARIANTE OCOLITOARE IN FOLOSINTA - OCTOMBRIE 2021